2/19/2026 1:59:53 PM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
|
2/19/2026 11:15:54 AM
|
Request for Review Comments returned by EPC DPW Development Services - Engineering
|
|
2/19/2026 9:54:58 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
|
2/19/2026 8:21:14 AM
|
Request for Review Comments email sent for Project 4490 E Blaney Rd Tower Modification for review by Justin Kilgore on behalf of PCD Project Manager
|
|
2/19/2026 8:19:45 AM
|
Project Manager Assigned: Lisa Elgin
|
|
2/18/2026 2:01:54 PM
|
Request for Review Comments email sent for Project 4490 E Blaney Rd Tower Modification for review by Trent Harwig on behalf of Falcon Fire Protection District
|
|
2/18/2026 2:01:53 PM
|
Request for Review Comments email sent for Project 4490 E Blaney Rd Tower Modification for review by Curtis Kauffman on behalf of Falcon Fire Protection District
|
|
2/18/2026 2:01:52 PM
|
Request for Review Comments email sent for Project 4490 E Blaney Rd Tower Modification for review by LBS Review on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
|
2/18/2026 2:01:51 PM
|
Request for Review Comments email sent for Project 4490 E Blaney Rd Tower Modification for review by on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
|
2/18/2026 2:01:50 PM
|
Request for Review Comments email sent for Project 4490 E Blaney Rd Tower Modification for review by on behalf of Pikes Peak Regional Building Department
|
|
2/18/2026 2:01:49 PM
|
Request for Review Comments email sent for Project 4490 E Blaney Rd Tower Modification for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
|
2/18/2026 2:01:48 PM
|
Request for Review Comments email sent for Project 4490 E Blaney Rd Tower Modification for review by Glenn West on behalf of 911 Authority - El Paso/Teller County
|
|
2/18/2026 2:01:47 PM
|
Request for Review Comments email sent for Project 4490 E Blaney Rd Tower Modification for review by Zachary Jannusch on behalf of EPC DPW Stormwater
|
|
2/18/2026 2:01:46 PM
|
Request for Review Comments email sent for Project 4490 E Blaney Rd Tower Modification for review by Mikayla Hartford on behalf of EPC DPW Stormwater
|
|
2/18/2026 2:01:45 PM
|
Request for Review Comments email sent for Project 4490 E Blaney Rd Tower Modification for review by Glenn Reese on behalf of EPC DPW Stormwater
|
|
2/18/2026 2:01:44 PM
|
Request for Review Comments email sent for Project 4490 E Blaney Rd Tower Modification for review by Christina Prete on behalf of EPC DPW Stormwater
|
|
2/18/2026 2:01:43 PM
|
Request for Review Comments email sent for Project 4490 E Blaney Rd Tower Modification for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
|
|
2/18/2026 2:01:42 PM
|
Request for Review Comments email sent for Project 4490 E Blaney Rd Tower Modification for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
|
2/10/2026 11:09:18 AM
|
Project Manager Assigned: Jen Uhler
|
|
2/10/2026 9:48:45 AM
|
Fees paid: 2/10/2026 (Receipt: 1011661)
|
|
2/10/2026 9:15:31 AM
|
Payment Request sent: 2/10/2026
|
|
2/10/2026 9:15:31 AM
|
File # Assigned: TWR262
|
|
2/10/2026 9:15:28 AM
|
Submission Triaged
|
|
2/10/2026 7:09:21 AM
|
Submission received from Applicant
|
|
2/9/2026 4:35:06 PM
|
Submission request sent to Applicant
|
|
2/9/2026 4:34:59 PM
|
Submission Triaged
|
|
2/9/2026 2:59:09 PM
|
Submission received from Applicant
|
|
2/9/2026 2:54:52 PM
|
Submission request sent to Applicant
|
|
2/9/2026 2:52:55 PM
|
Project Created
|