7/30/2025 2:20:11 PM
|
Project Ready for Approval requests. Review Comment period is complete.
|
7/30/2025 2:03:09 PM
|
Request for Review Comments returned by PCD Project Manager
|
7/24/2025 7:59:24 AM
|
Request for Review Comments returned by EPC DPW Stormwater
|
7/22/2025 1:54:49 PM
|
Request for Review Comments returned by EPC DPW Development Services - Engineering
|
7/21/2025 11:51:26 AM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by Zachary Jannusch on behalf of EPC DPW Stormwater
|
7/21/2025 11:51:25 AM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by Mikayla Hartford on behalf of EPC DPW Stormwater
|
7/21/2025 11:51:24 AM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by Glenn Reese on behalf of EPC DPW Stormwater
|
7/21/2025 11:51:23 AM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by Christina Prete on behalf of EPC DPW Stormwater
|
7/21/2025 11:51:21 AM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
|
7/21/2025 11:51:20 AM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
7/21/2025 11:51:18 AM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by Justin Kilgore on behalf of PCD Project Manager
|
7/21/2025 11:44:09 AM
|
Submission Triaged
|
7/18/2025 4:09:49 PM
|
Submission received from Applicant
|
7/11/2025 3:48:24 PM
|
Request for Review Comments returned by EPC Health Department
|
6/26/2025 4:35:49 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
6/24/2025 3:29:28 PM
|
Submission request sent to Applicant
|
6/24/2025 3:28:31 PM
|
Request for Review Comments returned by PCD Project Manager
|
6/24/2025 3:25:32 PM
|
Request for Review Comments email resent for Project 836 North Gate Large Childcare Center for review by Justin Kilgore on behalf of PCD Project Manager
|
6/23/2025 4:05:37 PM
|
Request for Review Comments returned by PCD Project Manager
|
6/20/2025 9:10:49 AM
|
Request for Review Comments returned by Colorado Springs Public Works
|
6/16/2025 10:14:43 AM
|
Request for Review Comments returned by Colorado Springs Planning & Community Development
|
6/11/2025 8:26:32 AM
|
Request for Review Comments returned by EPC DPW Development Services - Engineering
|
6/10/2025 11:17:43 AM
|
Request for Review Comments returned by PCD Administrative Notice
|
6/9/2025 12:24:48 PM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
6/5/2025 2:00:07 PM
|
Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
|
6/5/2025 10:50:09 AM
|
Request for Review Comments returned by EPC DPW Stormwater
|
5/30/2025 12:13:59 PM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by Jamey Bumgarner on behalf of Tri-Lakes-Monument Fire Protection District
|
5/30/2025 12:13:58 PM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by Jonathan Bradley on behalf of Tri-Lakes-Monument Fire Protection District
|
5/30/2025 12:13:57 PM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by General Email on behalf of Mountain View Electric Association, Inc.
|
5/30/2025 12:13:56 PM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by LBS Review on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
5/30/2025 12:13:55 PM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
5/30/2025 12:13:54 PM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by Zaker Alazzeh on behalf of Colorado Springs Public Works
|
5/30/2025 12:13:53 PM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by LaShunda Simpson on behalf of Colorado Springs Public Works
|
5/30/2025 12:13:52 PM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by Jonathan Scherer on behalf of Colorado Springs Public Works
|
5/30/2025 12:13:51 PM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by Joel Dagnillo on behalf of Colorado Springs Public Works
|
5/30/2025 12:13:50 PM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by Jeff Bailey on behalf of Colorado Springs Public Works
|
5/30/2025 12:13:49 PM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by Hao Vo on behalf of Colorado Springs Public Works
|
5/30/2025 12:13:48 PM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by Erin Powers on behalf of Colorado Springs Public Works
|
5/30/2025 12:13:47 PM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by General Email on behalf of Colorado Springs Public Works
|
5/30/2025 12:13:46 PM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by Dana Davison on behalf of Colorado Springs Public Works
|
5/30/2025 12:13:45 PM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by Brian Shevock on behalf of Colorado Springs Public Works
|
5/30/2025 12:13:44 PM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by Tamara Baxter on behalf of Colorado Springs Planning & Community Development
|
5/30/2025 12:13:43 PM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by Drew Fox on behalf of Colorado Springs Planning & Community Development
|
5/30/2025 12:13:41 PM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by Mike McCarthy on behalf of EPC Health Department
|
5/30/2025 12:13:40 PM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by Catherine McGarvy on behalf of EPC Health Department
|
5/30/2025 12:13:39 PM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by HEAEH LandUse on behalf of EPC Health Department
|
5/30/2025 12:13:38 PM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by Zachary Jannusch on behalf of EPC DPW Stormwater
|
5/30/2025 12:13:37 PM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by Mikayla Hartford on behalf of EPC DPW Stormwater
|
5/30/2025 12:13:36 PM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by Glenn Reese on behalf of EPC DPW Stormwater
|
5/30/2025 12:13:35 PM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by Christina Prete on behalf of EPC DPW Stormwater
|
5/30/2025 12:13:34 PM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
|
5/30/2025 12:13:33 PM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
5/30/2025 12:13:31 PM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by Justin Kilgore on behalf of PCD Project Manager
|
5/30/2025 12:13:30 PM
|
Request for Review Comments email sent for Project 836 North Gate Large Childcare Center for review by on behalf of PCD Administrative Notice
|
5/29/2025 1:40:45 PM
|
Fees paid: 5/29/2025 (Receipt: 1010584)
|
5/29/2025 9:28:58 AM
|
Payment Request sent: 5/29/2025
|
5/29/2025 9:28:57 AM
|
File # Assigned: AL2512
|
5/29/2025 9:28:54 AM
|
Submission Triaged
|
5/28/2025 3:53:49 PM
|
Submission received from Applicant
|
5/21/2025 1:34:10 PM
|
Submission request sent to Applicant
|
5/15/2025 8:26:41 AM
|
Submission request sent to Applicant
|
5/14/2025 12:14:37 PM
|
Project Manager Assigned: Miranda Benson
|
5/14/2025 12:14:36 PM
|
Project Created
|