6/4/2025 8:25:22 AM
|
Project Manager Assigned: Lacey Dean
|
6/3/2025 12:50:46 PM
|
Submission request sent to Applicant
|
6/3/2025 12:50:36 PM
|
Project reopened for Review Comments
|
5/28/2025 2:00:21 PM
|
Project Closed
|
5/28/2025 2:00:21 PM
|
Project Cancelled: 5/28/2025
|
5/28/2025 12:16:34 PM
|
Submission request sent to Applicant
|
5/28/2025 12:16:19 PM
|
Project reopened for Review Comments
|
5/8/2025 2:58:10 PM
|
Project Closed
|
5/8/2025 2:58:10 PM
|
Project Cancelled: 5/8/2025
|
3/6/2024 8:57:07 AM
|
Submission request sent to Applicant
|
3/6/2024 8:54:32 AM
|
Request for Review Comments returned by PCD Project Manager
|
3/5/2024 6:17:59 PM
|
Request for Review Comments returned by PCD Engineering Division
|
3/4/2024 10:00:48 AM
|
Submission Triaged
|
3/4/2024 9:46:19 AM
|
Submission received from Applicant
|
3/4/2024 9:44:00 AM
|
Submission request sent to Applicant
|
3/2/2024 8:33:23 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
2/20/2024 8:18:40 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
2/20/2024 8:18:38 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by Glenn Reese on behalf of EPC Stormwater Review
|
2/20/2024 8:18:36 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by Christina Prete on behalf of EPC Stormwater Review
|
2/20/2024 8:18:32 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by Gilbert LaForce on behalf of PCD Engineering Division
|
2/20/2024 8:18:29 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by Engineering Manager on behalf of PCD Engineering Division
|
2/20/2024 8:12:41 AM
|
Submission Triaged
|
2/19/2024 11:59:54 AM
|
Submission received from Applicant
|
1/31/2024 1:55:07 PM
|
Submission request sent to Applicant
|
1/9/2024 8:00:09 AM
|
Request for Review Comments returned by PCD Project Manager
|
1/3/2024 11:55:48 AM
|
Submission request sent to Applicant
|
1/2/2024 12:29:15 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
12/28/2023 2:10:15 PM
|
Request for Review Comments returned by PCD Engineering Division
|
12/28/2023 12:58:45 PM
|
Request for Review Comments returned by PCD Project Manager
|
12/27/2023 1:57:21 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
12/22/2023 2:59:46 PM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
12/20/2023 11:00:15 AM
|
Request for Review Comments returned by Cherokee Metro Dist
|
12/15/2023 9:37:23 AM
|
Request for Review Comments returned by Central Marksheffel Metro
|
12/12/2023 9:00:36 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by Tim Thomas on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
12/12/2023 9:00:34 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by Paul Clifton on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
12/12/2023 9:00:32 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by LBS Review on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
12/12/2023 9:00:30 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by Gary Rust on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
12/12/2023 9:00:28 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by Caelen Went on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
12/12/2023 9:00:26 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
12/12/2023 9:00:24 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by Terry Johns on behalf of Colorado Springs SD 11
|
12/12/2023 9:00:22 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by Tom Joyce on behalf of Cimarron Hills Fire
|
12/12/2023 9:00:20 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by John McLeod on behalf of Cimarron Hills Fire
|
12/12/2023 9:00:18 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by Tyler Drennan on behalf of Cherokee Metro Dist
|
12/12/2023 9:00:16 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by Kevin Brown on behalf of Cherokee Metro Dist
|
12/12/2023 9:00:14 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by Jeff Munger on behalf of Cherokee Metro Dist
|
12/12/2023 9:00:12 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by CONNIE HUGHES on behalf of Cherokee Metro Dist
|
12/12/2023 9:00:10 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by Rebecca Hardekopf on behalf of Central Marksheffel Metro
|
12/12/2023 9:00:08 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by Pamela Davidson on behalf of Central CO Conservation District
|
12/12/2023 9:00:05 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by on behalf of Pikes Peak Regional Building Department
|
12/12/2023 9:00:03 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
12/12/2023 9:00:01 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by Glenn Reese on behalf of EPC Stormwater Review
|
12/12/2023 8:59:59 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by Christina Prete on behalf of EPC Stormwater Review
|
12/12/2023 8:59:57 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by Mike McCarthy on behalf of EPC Health Department
|
12/12/2023 8:59:55 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by Catherine McGarvy on behalf of EPC Health Department
|
12/12/2023 8:59:53 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by HEAEH LandUse on behalf of EPC Health Department
|
12/12/2023 8:59:49 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by Lupe Packman on behalf of PCD Engineering Division
|
12/12/2023 8:59:47 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by Gilbert LaForce on behalf of PCD Engineering Division
|
12/12/2023 8:59:45 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
12/12/2023 8:59:43 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by Edward Schoenheit on behalf of PCD Engineering Division
|
12/12/2023 8:59:41 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by Engineering Manager on behalf of PCD Engineering Division
|
12/12/2023 8:59:37 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by Charlene Durham on behalf of PCD Engineering Division
|
12/12/2023 8:59:35 AM
|
Request for Review Comments email sent for Project Claremont Business Park Coffee Shop for review by Carlos Hernandez Martinez on behalf of PCD Engineering Division
|
12/7/2023 1:31:30 PM
|
Fees paid: 12/7/2023 (Receipt: 1008592)
|
11/2/2023 8:23:28 AM
|
Project Manager Assigned: Ashlyn Mathy
|
11/2/2023 8:23:09 AM
|
Payment Request sent: 11/2/2023
|
11/2/2023 8:23:09 AM
|
File # Assigned: PPR2345
|
11/2/2023 8:22:56 AM
|
Submission Triaged
|
11/2/2023 8:05:05 AM
|
Submission received from Applicant
|
8/29/2023 1:36:19 PM
|
Submission request sent to Applicant
|
8/29/2023 1:34:19 PM
|
Project Manager Assigned: Kylie Bagley
|
8/29/2023 1:34:19 PM
|
Project Created
|