Project Review Comments
- File Number
- ID258
- Project Name
- Rock Creek Metropolitan District - Service Plan Amendment
- Description
- Service Plan Amendment:Amendment provides: (i) an update regarding the current status of the District, (ii) an updated boundary map and legal description, (iii) updated capital costs and the corresponding infrastructure maps, and (iv) an updated financial plan.- increases max mill levy from 65 to 75; increases O and M from 10 to 20; keeps 5 mills special purpose; keeps 50 mills residential; eliminates 35 mills for commercial; increases debt from $8 to $48 million. Term of 40-year debt payoff requested to start at refi of ex-bonds or new indebtedness.
- Parcels
- 6530307001 6530307001
- Applicant
-
Spencer Fane LLC
Nicole Peykov ( npeykov@spencerfane.com )
(303) 839-3715 Nicole Peykov ( npeykov@spencerfane.com )
(303) 839-3715 - File Number
- ID258
- Project Manager
- Kari Parsons
- Status
- Active
- Created
- 12/9/2025 1:40:16 PM
View: Project Documents | Submit/View Public Comment
| Agency | Review # | Comment | ||
|---|---|---|---|---|
|
PCD Project Manager
4/22/2026 11:39:47 AM |
5 | Item is scheduled for hearing May 7th, Planning Commission; BoCC May 19, and June 11 | 4/22/2026 11:39:47 AM | |
|
County Attorney - Development Review
4/17/2026 11:45:30 AM |
4 |
Applicant must provide specific, robust justification for any requests to deviate from the Special Districts Policy or Model Service Plan. Reviewed by: Erika Keech, Sr. County Attorney, erikakeech2@elpasoco.com. |
4/17/2026 11:45:30 AM | |
|
PCD Project Manager
4/15/2026 1:05:23 PM |
4 | Please note: the existing service plan clearly depicts a designated 35 mills for commercial and 50 mills for residential. The current plan under consideration does not speak to commercial development and it presumes an elimination of 35 mills for commercial development. Staff has included that in the staff report. If the applicant wants to retain 35 commercial mills, please justify the need in the letter of intent (LOI) and the financial plan. If the applicant is seeking to raise the 35 mills to 50 mills for commercial, please add and justify to LOI, and service plan. Please see previous staff reports and BOCC resolutions, which clearly identify residential or commercial mills based on the applicant's LOI, service plan and financial plan. | 4/15/2026 1:05:23 PM | |
| View |
PCD Project Manager
4/6/2026 3:36:33 PM |
3 | Service Plan Comments 2 | 4/6/2026 3:36:33 PM |
| View |
PCD Project Manager
4/6/2026 3:36:14 PM |
3 | Letter of intent comments- further clarification requested | 4/6/2026 3:36:14 PM |
|
PCD Project Manager
4/6/2026 1:28:49 PM |
3 |
Please provide the separate pro forma prepared by DA Davidson showing the difference of the revenue the District would collect from a 10 mill operations and maintenance mill levy verses the 20 mills requested. |
4/6/2026 1:28:49 PM | |
|
PCD Project Manager
4/6/2026 12:33:40 PM |
3 | Clarify who is to pay $300 Traffic impact fee and provide documentation that they agree to do so if outside of the District. Is this for new lots within the District or outside the District? | 4/6/2026 12:33:40 PM | |
|
PCD Project Manager
4/6/2026 12:31:56 PM |
3 | Provide documentation that Rock Creek Mesa will pay the Pledge Revenue on an annual basis. Include the range $ amount they are agreeing to pay. | 4/6/2026 12:31:56 PM | |
|
PCD Project Manager
4/6/2026 12:29:36 PM |
3 |
Please provide the exclusion from the Southwestern Highway 115 Fire Protection District documentation for the property that is located within the City. Please provide the email or documentation that the Fire District will maintain the hydrants, which is not common. Typically, the District maintains. |
4/6/2026 12:29:36 PM | |
|
PCD Project Manager
4/6/2026 12:25:19 PM |
3 |
Please provide documentation from the Cheyenne Mountain Estates mobile Home Park that they have agreed to pay the Annual Capital Recovery Fee in the amount of $135,324- $185,316. |
4/6/2026 12:25:19 PM | |
|
EPC DPW Development Services - Engineering
4/6/2026 11:17:34 AM |
3 |
DPW Engineering review; no comments on the submitted documents. Review by Bret Dilts, PE bretdilts@elpasoco.com 719-520-6864 |
4/6/2026 11:17:34 AM | |
|
EPC DPW Stormwater
3/25/2026 4:43:39 PM |
3 |
EPC DPW Stormwater does not have comments on any of the submitted documents. Reviewed by: Glenn Reese, P.E. Principal Engineer - Stormwater 719.675.2654 GlennReese@elpasoco.com |
3/25/2026 4:43:39 PM | |
| View |
PCD Project Manager
2/10/2026 4:14:41 PM |
2 | Vicinity map comment 1 | 2/10/2026 4:14:41 PM |
| View |
PCD Project Manager
2/10/2026 4:14:12 PM |
2 | Service Plan Comments review 1 | 2/10/2026 4:14:12 PM |
| View |
PCD Project Manager
2/10/2026 4:13:34 PM |
2 | Letter of Intent comment 1 | 2/10/2026 4:13:34 PM |
|
EPC DPW Stormwater
2/10/2026 12:43:04 PM |
2 |
EPC DPW Stormwater does not have comments on any of the submitted documents. Reviewed by: Glenn Reese, P.E. Principal Engineer - Stormwater 719.675.2654 GlennReese@elpasoco.com |
2/10/2026 12:43:04 PM | |
|
EPC DPW Development Services - Engineering
2/10/2026 1:05:54 PM |
2 |
DPW Engineering review; no comments on the submitted documents. Review by Bret Dilts, PE bretdilts@elpasoco.com 719-520-6864 |
2/10/2026 1:05:54 PM | |
| View |
PCD Project Manager
2/10/2026 4:14:55 PM |
2 | Redline Model and Policies were approved and adopted 2 10 2026. Please update Service Plan and Notice Disclosure form accordingly. As noted in the current and to be adopted Special District Policies, amendments do need to conform to Models and Policies. | 2/10/2026 4:14:55 PM |
| View |
EPC Health Department
2/2/2026 5:42:32 PM |
2 | 2/2/2026 5:42:32 PM | |
|
County Attorney - Development Review
1/29/2026 11:57:49 AM |
2 |
No comments from County Attorney - Development Review at this time. Reviewed by: Erika Keech, Senior County Attorney, erikakeech2@elpasoco.com |
1/29/2026 11:57:49 AM | |
|
Colorado Springs Planning & Community Development
1/29/2026 10:38:23 AM |
2 | City Planning has no comment. | 1/29/2026 10:38:23 AM | |
|
Mountain View Electric Association, Inc.
1/28/2026 2:33:42 PM |
2 | Not within Mountain View Electric Association service territory. Thank you | 1/28/2026 2:33:42 PM | |
| View |
EPC Parks Department
1/27/2026 10:52:39 AM |
2 |
Staff has provided a review for the project. See attached. Thank you! Ashlyn Mathy Parks Planner Park Planning Division El Paso County Parks Department Office: 719.520.6999 |
1/27/2026 10:52:39 AM |
| View |
EPC Environmental Services
1/23/2026 1:04:01 PM |
2 | 1/23/2026 1:04:01 PM | |
|
Black Hills Energy-Aquila
1/22/2026 11:53:56 AM |
2 | BHE has no facilities in area. | 1/22/2026 11:53:56 AM | |
|
PCD Project Manager
1/5/2026 8:49:43 AM |
1 | Please submit a service plan that conforms to todays adopted model service plan format and our policies with all exhibits. Please make sure to incorporate the new legislation on term of debt maxing at 40 years. | 1/5/2026 8:49:43 AM |
EDARP