Project Review Comments
- Project Name
- Meadowbrook Park PUDSP & Final Plat Amendment
- Description
- Amendment to the PUDSP and Final Plat to replace alternating 1 ft. and 5 ft. side setbacks with a uniform 3 ft. setback. Building separation will be the same; structures will now be centered on the lots. This application updates side setbacks, drainage and utility easements, and lot typicals. Revised PUDSP plan and Final Plat will need to be recorded. Original plat recorded under Plat no. 15403.
- Location
- Parcels
- 5408000053 5408000053 5408008002 5408008002 5408403001 5408403001
- Applicant
-
Kimley-Horn Associates
Jim Houk ( jim.houk@kimley-horn.com )
(719) 284-7280 Jim Houk ( jim.houk@kimley-horn.com )
(719) 284-7280 - File Number
- PUDSP254
- Project Manager
- Ryan Howser
- Status
- Active
- Created
- 5/7/2025 3:01:19 PM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Project Manager
6/6/2025 12:00:32 PM |
Review 3: No comments. Please coordinate with PCD Project Manager regarding recording instructions. | 6/6/2025 12:00:32 PM | |
View |
PCD Project Manager
6/5/2025 4:35:33 PM |
Review 2: PCD Planning Division has comments (in green) on the following documents (attached): - Final Plat |
6/5/2025 4:35:33 PM |
EPC DPW Development Services - Engineering
6/5/2025 4:03:31 PM |
No additional comments. The drainage report will be routed for approval by the ECM Administrator. reviewed by: Daniel Torres danieltorres@elpasoco.com |
6/5/2025 4:03:31 PM | |
View |
EPC DPW Development Services - Engineering
5/30/2025 3:26:08 PM |
Final Plat comments | 5/30/2025 3:26:08 PM |
View |
EPC DPW Development Services - Engineering
5/30/2025 3:25:43 PM |
PUD Development Plan comments | 5/30/2025 3:25:43 PM |
EPC DPW Development Services - Engineering
5/30/2025 3:26:27 PM |
Review 1 comments on the following documents will be uploaded: - PUD Development Plan - Final Plat Please submit signed final drainage report. reviewed by: Daniel Torres danieltorres@elpasoco.com |
5/30/2025 3:26:27 PM | |
PCD Project Manager
5/30/2025 8:54:02 AM |
Review 1: PCD Planning Division has comments (in green) on the following documents (to be uploaded by EPC DPW Engineering): - PUD Development Plan - Final Plat |
5/30/2025 8:54:02 AM | |
Cherokee Metro Dist
5/29/2025 11:28:38 AM |
No issue with 3ft setback plan No change to utility plan needed. Refer to PUDSP246 that states "Include the Water and Sewer plan and profile design views that mark how they are tied into Cherokee Metropolitan District's existing infrastructure" |
5/29/2025 11:28:38 AM | |
Pikes Peak Regional Building Department
5/29/2025 9:57:23 AM |
1. There are several site plan submittals that have been affected by the set back change. Please be sure to submit splices to these permits that show that the property lines have shifted to accommodate the 3’ setback on both sides. 2. No further comment. Becky Allen Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org |
5/29/2025 9:57:23 AM | |
EPC DPW Stormwater
5/27/2025 3:05:41 PM |
Review 1: Per the submitted Final Drainage Letter, the proposed platting changes will not change the drainage patterns for anything related to WQ treatment from the previously approved FDR. Therefore, EPC DPW Stormwater does not have any comments on this project. Thanks. Reviewed by: Glenn Reese, P.E. Principal Engineer - Stormwater 719.675.2654 GlennReese@elpasoco.com |
5/27/2025 3:05:41 PM | |
PCD Administrative Notice
5/22/2025 12:13:05 PM |
On 05/22/2025, PCD mailed "Notice of Application" letters to surrounding property owners within a 500-foot range (65 addresses). Copies of the notice, mailing labels, and selected range have been uploaded to the EDARP file. Cost of postage to be billed to the applicant = $44.85. JM | 5/22/2025 12:13:05 PM |