8/28/2025 5:24:45 PM
|
Request for Review Comments email sent for Project 1015 Valley St - Covered parking and curb cut for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
|
8/28/2025 5:24:44 PM
|
Request for Review Comments email sent for Project 1015 Valley St - Covered parking and curb cut for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
8/28/2025 5:24:42 PM
|
Request for Review Comments email sent for Project 1015 Valley St - Covered parking and curb cut for review by Justin Kilgore on behalf of PCD Project Manager
|
8/28/2025 5:22:48 PM
|
Request for Review Comments email sent for Project 1015 Valley St - Covered parking and curb cut for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
|
8/28/2025 5:22:47 PM
|
Request for Review Comments email sent for Project 1015 Valley St - Covered parking and curb cut for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
8/28/2025 5:22:45 PM
|
Request for Review Comments email sent for Project 1015 Valley St - Covered parking and curb cut for review by Justin Kilgore on behalf of PCD Project Manager
|
8/28/2025 3:16:15 PM
|
Request for Review Comments returned by EPC DPW Stormwater
|
8/28/2025 2:54:39 PM
|
Request for Review Comments email sent for Project 1015 Valley St - Covered parking and curb cut for review by Zachary Jannusch on behalf of EPC DPW Stormwater
|
8/28/2025 2:54:38 PM
|
Request for Review Comments email sent for Project 1015 Valley St - Covered parking and curb cut for review by Mikayla Hartford on behalf of EPC DPW Stormwater
|
8/28/2025 2:54:37 PM
|
Request for Review Comments email sent for Project 1015 Valley St - Covered parking and curb cut for review by Glenn Reese on behalf of EPC DPW Stormwater
|
8/28/2025 2:54:36 PM
|
Request for Review Comments email sent for Project 1015 Valley St - Covered parking and curb cut for review by Christina Prete on behalf of EPC DPW Stormwater
|
8/28/2025 2:54:35 PM
|
Request for Review Comments email sent for Project 1015 Valley St - Covered parking and curb cut for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
|
8/28/2025 2:54:34 PM
|
Request for Review Comments email sent for Project 1015 Valley St - Covered parking and curb cut for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
8/28/2025 2:54:32 PM
|
Request for Review Comments email sent for Project 1015 Valley St - Covered parking and curb cut for review by Justin Kilgore on behalf of PCD Project Manager
|
8/25/2025 7:05:20 AM
|
Fees paid: 8/25/2025 (Receipt: 1010958)
|
8/18/2025 10:37:12 AM
|
Payment Request sent: 8/18/2025
|
8/18/2025 10:37:12 AM
|
File # Assigned: COM2520
|
8/18/2025 10:37:08 AM
|
Submission Triaged
|
8/18/2025 10:19:33 AM
|
Submission received from Applicant
|
8/17/2025 7:01:08 PM
|
Submission request sent to Applicant
|
8/17/2025 7:00:37 PM
|
Submission Triaged
|
8/15/2025 9:18:12 AM
|
Submission received from Applicant
|
8/13/2025 12:22:57 PM
|
Submission request sent to Applicant
|
8/13/2025 10:20:42 AM
|
Project Manager Assigned: Lacey Dean
|
8/13/2025 10:20:42 AM
|
Project Created
|