| 9/17/2025 6:04:00 PM | Submission request sent to Applicant | 
                
                    | 9/17/2025 5:54:19 PM | Request for Review Comments returned by EPC DPW Development Services - Engineering | 
                
                    | 9/17/2025 3:14:30 PM | Request for Review Comments returned by PCD Project Manager | 
                
                    | 8/28/2025 5:24:45 PM | Request for Review Comments email sent for Project 1015 Valley St - Covered parking and curb cut for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering | 
                
                    | 8/28/2025 5:24:44 PM | Request for Review Comments email sent for Project 1015 Valley St - Covered parking and curb cut for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering | 
                
                    | 8/28/2025 5:24:42 PM | Request for Review Comments email sent for Project 1015 Valley St - Covered parking and curb cut for review by Justin Kilgore on behalf of PCD Project Manager | 
                
                    | 8/28/2025 5:22:48 PM | Request for Review Comments email sent for Project 1015 Valley St - Covered parking and curb cut for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering | 
                
                    | 8/28/2025 5:22:47 PM | Request for Review Comments email sent for Project 1015 Valley St - Covered parking and curb cut for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering | 
                
                    | 8/28/2025 5:22:45 PM | Request for Review Comments email sent for Project 1015 Valley St - Covered parking and curb cut for review by Justin Kilgore on behalf of PCD Project Manager | 
                
                    | 8/28/2025 3:16:15 PM | Request for Review Comments returned by EPC DPW Stormwater | 
                
                    | 8/28/2025 2:54:39 PM | Request for Review Comments email sent for Project 1015 Valley St - Covered parking and curb cut for review by Zachary Jannusch on behalf of EPC DPW Stormwater | 
                
                    | 8/28/2025 2:54:38 PM | Request for Review Comments email sent for Project 1015 Valley St - Covered parking and curb cut for review by Mikayla Hartford on behalf of EPC DPW Stormwater | 
                
                    | 8/28/2025 2:54:37 PM | Request for Review Comments email sent for Project 1015 Valley St - Covered parking and curb cut for review by Glenn Reese on behalf of EPC DPW Stormwater | 
                
                    | 8/28/2025 2:54:36 PM | Request for Review Comments email sent for Project 1015 Valley St - Covered parking and curb cut for review by Christina Prete on behalf of EPC DPW Stormwater | 
                
                    | 8/28/2025 2:54:35 PM | Request for Review Comments email sent for Project 1015 Valley St - Covered parking and curb cut for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering | 
                
                    | 8/28/2025 2:54:34 PM | Request for Review Comments email sent for Project 1015 Valley St - Covered parking and curb cut for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering | 
                
                    | 8/28/2025 2:54:32 PM | Request for Review Comments email sent for Project 1015 Valley St - Covered parking and curb cut for review by Justin Kilgore on behalf of PCD Project Manager | 
                
                    | 8/25/2025 7:05:20 AM | Fees paid: 8/25/2025 (Receipt: 1010958) | 
                
                    | 8/18/2025 10:37:12 AM | Payment Request sent: 8/18/2025 | 
                
                    | 8/18/2025 10:37:12 AM | File # Assigned: COM2520 | 
                
                    | 8/18/2025 10:37:08 AM | Submission Triaged | 
                
                    | 8/18/2025 10:19:33 AM | Submission received from Applicant | 
                
                    | 8/17/2025 7:01:08 PM | Submission request sent to Applicant | 
                
                    | 8/17/2025 7:00:37 PM | Submission Triaged | 
                
                    | 8/15/2025 9:18:12 AM | Submission received from Applicant | 
                
                    | 8/13/2025 12:22:57 PM | Submission request sent to Applicant | 
                
                    | 8/13/2025 10:20:42 AM | Project Manager Assigned: Lacey Dean | 
                
                    | 8/13/2025 10:20:42 AM | Project Created |