Project Review Comments

Back to List


Project Name
1015 Valley St - Covered parking and curb cut
Description
New Fire Station (UXXX) wants to add covered parking structures and changes to the curb cut. Related to PPR01033.
Location
Parcels
5407202012 5407202012
Applicant
YOW Architects
Planner Brad Nichols ( bnichols@yowarch.com )
(719) 623-1416
Planner Brad Nichols ( bnichols@yowarch.com )
(719) 623-1416
File Number
COM2520
Project Manager
Lacey Dean
Status
Active
Created
8/13/2025 10:20:40 AM

View: Project Documents



Review Comments (7)

Link Agency Comment
View EPC DPW Development Services - Engineering
9/17/2025 5:53:45 PM
Site Plan comments (Planning and Engineering comments) 9/17/2025 5:53:45 PM
View EPC DPW Development Services - Engineering
9/17/2025 5:45:55 PM
RIF Acknowledgement Form comments 9/17/2025 5:45:55 PM
View EPC DPW Development Services - Engineering
9/17/2025 5:52:29 PM
Deviation request template 9/17/2025 5:52:29 PM
View PCD Project Manager
9/17/2025 3:13:24 PM
V1_Letter of _comments 9/17/2025 3:13:24 PM
PCD Project Manager
9/17/2025 3:12:13 PM
Review 1: EPC Planning Division has comments in green text boxes on the following documents:

- Letter of Intent (copied from the LOI submitted with associated Approval of Location project U251)
- Site Plan Drawing (documents with comments will be uploaded by the Engineer with their review comments)

Reviewed by:
Lacey Dean, Associate Planner
laceydean2@elpasoco.com
9/17/2025 3:12:13 PM
EPC DPW Development Services - Engineering
9/17/2025 5:40:40 PM
Review 1.

Engineering comments on the following documents:
- Site Plan Drawing
- RIF Acknowledgement Form

Additional documents required to be submitted with the next review:
- Deviation Request (template uploaded)

Reviewed by:
Joe Sandstrom, EI, Associate Engineer
josephsandstrom@elpasoco.com
(719) 520-6314
9/17/2025 5:40:40 PM
EPC DPW Stormwater
8/28/2025 3:16:06 PM
Review 1: The proposed disturbances and development is well under 1ac. The proposed improvements will are redevelopment of existing developed land with no additional imperviousness. The site was fully developed prior to 2008. So the cumulative development post-2008 plus the proposed development is well under 1ac. So an ESQCP and PCM are not required.

Reviewed by:
Glenn Reese, P.E.
Principal Engineer - Stormwater
719.675.2654
GlennReese@elpasoco.com
8/28/2025 3:16:06 PM