11/18/2025 8:09:51 AM
|
Request for Review Comments email sent for Project Murphy USA Convenience Store and Fueling for review by on behalf of EPC Public Works, County Engineer
|
|
11/18/2025 8:09:50 AM
|
Request for Review Comments email sent for Project Murphy USA Convenience Store and Fueling for review by on behalf of EPC Public Works, County Engineer
|
|
11/18/2025 8:09:49 AM
|
Request for Review Comments email sent for Project Murphy USA Convenience Store and Fueling for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
|
|
11/18/2025 8:09:47 AM
|
Request for Review Comments email sent for Project Murphy USA Convenience Store and Fueling for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
|
11/18/2025 7:59:32 AM
|
Project reopened for Review Comments
|
|
7/18/2025 5:56:50 PM
|
Project Closed
|
|
7/18/2025 5:56:50 PM
|
Project Approved: 7/18/2025
|
|
7/16/2025 10:51:10 AM
|
Request for Review Comments returned by EPC DPW Stormwater
|
|
7/14/2025 2:46:47 PM
|
Request for Review Comments returned by EPC DPW Development Services - Engineering
|
|
7/3/2025 1:31:04 PM
|
Request for Review Comments email sent for Project Murphy USA Convenience Store and Fueling for review by on behalf of EPC Public Works, County Engineer
|
|
7/3/2025 1:31:03 PM
|
Request for Review Comments email sent for Project Murphy USA Convenience Store and Fueling for review by on behalf of EPC Public Works, County Engineer
|
|
7/3/2025 1:31:02 PM
|
Request for Review Comments email sent for Project Murphy USA Convenience Store and Fueling for review by Zachary Jannusch on behalf of EPC DPW Stormwater
|
|
7/3/2025 1:31:01 PM
|
Request for Review Comments email sent for Project Murphy USA Convenience Store and Fueling for review by Mikayla Hartford on behalf of EPC DPW Stormwater
|
|
7/3/2025 1:31:00 PM
|
Request for Review Comments email sent for Project Murphy USA Convenience Store and Fueling for review by Glenn Reese on behalf of EPC DPW Stormwater
|
|
7/3/2025 1:30:59 PM
|
Request for Review Comments email sent for Project Murphy USA Convenience Store and Fueling for review by Christina Prete on behalf of EPC DPW Stormwater
|
|
7/3/2025 1:30:58 PM
|
Request for Review Comments email sent for Project Murphy USA Convenience Store and Fueling for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
|
|
7/3/2025 1:30:57 PM
|
Request for Review Comments email sent for Project Murphy USA Convenience Store and Fueling for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
|
7/3/2025 1:30:55 PM
|
Request for Review Comments email sent for Project Murphy USA Convenience Store and Fueling for review by Justin Kilgore on behalf of PCD Project Manager
|
|
7/3/2025 1:21:48 PM
|
No Fees
|
|
7/3/2025 1:21:48 PM
|
File # Assigned: OAR2513
|
|
7/3/2025 1:21:47 PM
|
Project Manager Assigned: Lisa Elgin
|
|
7/3/2025 1:21:47 PM
|
Project Created
|