Project Details

Search | All Active Projects


File Number
PPR2347
Project Name
4-Way Commercial Site Development Plan
Description
SEE EMAIL IN ADDITIONAL DOCS FOR ROAD IMPACT FEE DETAIL. *Site Development Plan for mini-warehouse and boat/RV storage. REF: CS223
Parcels
4200000399 4200000399
Applicant
SMH Consultants
Brett Louk ( blouk@smhconsultants.com )
(719) 465-2145
Brett Louk ( blouk@smhconsultants.com )
(719) 465-2145
EA Number
EA22107
File Prefix
PPR - Plot Plan Review
Year
2023
Project Manager
Miranda Benson
Status
Active
Created
2/3/2023 10:47:58 AM

View: Review Comments



Additional Documents (2)

Link Document Comment
View Email Communication Landscaping along Stapleton Rd
View Email Communication Collection of Road Impact Fees at different stages of this development.


Review Documents (38)

Link Document Date
View Application/Petition Form 2/2/2026 4:42:49 PM
View Grading & Erosion Control checklist 2/2/2026 4:43:02 PM
View Legal Description (MS WORD Version required) 5/12/2025 12:22:23 PM
View Letter of Intent 7/1/2026 2:15:08 PM
View Vicinity/Location Map 5/12/2025 12:22:26 PM
View Erosion and Stormwater Quality Control Permit (ESQCP) 2/2/2026 4:42:58 PM
View Financial Assurance Forms 7/1/2026 2:15:05 PM
View Floor Plans (24" x 36") 2/2/2026 4:42:53 PM
View MS4 Post Construction Form 5/12/2025 12:22:28 PM
View PBMP Applicability Form 7/1/2026 2:15:12 PM
View PCM - Notice of Intent to Construct a Non-Juris. Water Impoundment Structure (proof of submittal) 7/1/2026 2:15:11 PM
View PDB/BMP Operations & Maintenance Manual 5/13/2025 10:16:31 AM
View Stormwater Detention & Infiltration Design Data Worksheet (SDI Worksheet) 7/1/2026 2:15:11 PM
View SWMP checklist 2/2/2026 4:43:02 PM
View Grading & Erosion Control Plan 7/1/2026 2:53:34 PM
View Landscape Plan drawings 7/1/2026 2:15:07 PM
View Lighting Plan 7/1/2026 2:15:09 PM
View Sign Plan 5/12/2025 12:22:24 PM
View Site Development Plan 7/1/2026 2:15:10 PM
View Storm Water Management Plan (SWMP) 2/2/2026 4:42:59 PM
View Soils Report Pursuant to Appendix E of the ECM 5/12/2025 12:30:49 PM
View Drainage Report - Final 7/1/2026 2:15:06 PM
View Traffic Impact Study 7/1/2026 2:15:09 PM
View Detention Maintenance Agreement (MS WORD version required - attachments included) 7/1/2026 2:15:04 PM
View 4-Way - Fire Apparatus Turning_Exhibit 5/12/2025 12:28:19 PM
View 4-Way - MS4-Post-Construction-Form-South-Pond 5/12/2025 12:39:18 PM
View 4-Way - SDI_Design_Data-Ultimate 5/12/2025 12:39:19 PM
View Applicant Response to V3 Comments (1) 7/2/2026 10:41:06 AM
View Applicant Response to V3 Comments (2) 7/2/2026 10:41:06 AM
View Construction Documents Checklist 5/12/2025 12:32:19 PM
View Detention Maintenance Agreement - Exhibit B 5/12/2025 12:33:02 PM
View Elevation Plans 2/2/2026 4:42:50 PM
View Final Drainage Report Checklist 5/12/2025 12:32:20 PM
View Fire Truck Turning Exhibits 2/2/2026 4:43:04 PM
View I&M Plans/O&M Manual 2/2/2026 4:43:04 PM
View Responses to comments 2/2/2026 4:43:05 PM
View Responses to comments 5/13/2025 10:43:51 AM
View Site Development Plans Checklist 5/12/2025 12:32:19 PM



Events (246)

Date Comment
7/21/2026 3:34:10 PM Submission request sent to Applicant
7/21/2026 3:25:31 PM Request for Review Comments returned by PCD Engineering Division
7/21/2026 3:20:53 PM Request for Review Comments email resent for Project 4-Way Commercial Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
7/21/2026 2:58:44 PM Request for Review Comments returned by PCD Engineering Division
7/21/2026 11:19:09 AM Request for Review Comments returned by PCD Project Manager
7/16/2026 2:38:02 PM Request for Review Comments returned by EPC Stormwater Review
7/13/2026 3:50:53 PM Request for Review Comments returned by Pikes Peak Regional Building Department
7/10/2026 2:29:24 PM Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
7/10/2026 10:13:49 AM Request for Review Comments returned by County Attorney - Development Review
7/2/2026 12:49:17 PM Request for Review Comments returned by Falcon Fire Protection District
7/2/2026 12:35:13 PM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Trent Harwig on behalf of Falcon Fire Protection District
7/2/2026 12:35:12 PM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Curtis Kauffman on behalf of Falcon Fire Protection District
7/2/2026 12:35:11 PM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by on behalf of Pikes Peak Regional Building Department
7/2/2026 12:35:10 PM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Julie Reeves on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
7/2/2026 12:35:09 PM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by george san miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
7/2/2026 12:35:08 PM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
7/2/2026 12:35:07 PM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
7/2/2026 12:35:06 PM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
7/2/2026 12:35:05 PM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Kimberly Blanchard on behalf of Colorado Department of Transportation - Pueblo Office
7/2/2026 12:35:04 PM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
7/2/2026 12:35:03 PM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Zachary Jannusch on behalf of EPC Stormwater Review
7/2/2026 12:35:02 PM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
7/2/2026 12:35:01 PM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Glenn Reese on behalf of EPC Stormwater Review
7/2/2026 12:35:00 PM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Erica Rylander on behalf of EPC Stormwater Review
7/2/2026 12:34:59 PM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Christina Prete on behalf of EPC Stormwater Review
7/2/2026 12:34:58 PM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Lori Seago on behalf of County Attorney - Development Review
7/2/2026 12:34:57 PM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Erika Keech on behalf of County Attorney - Development Review
7/2/2026 12:34:56 PM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by April Willie on behalf of County Attorney - Development Review
7/2/2026 12:34:54 PM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Justin Kilgore on behalf of PCD Project Manager
7/2/2026 12:34:53 PM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
7/2/2026 12:34:52 PM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
7/1/2026 2:45:21 PM Submission Triaged
7/1/2026 2:17:39 PM Submission received from Applicant
2/26/2026 4:21:14 PM Submission request sent to Applicant
2/26/2026 4:10:22 PM Request for Review Comments returned by PCD Project Manager
2/26/2026 3:29:17 PM Request for Review Comments returned by Black Hills Energy-Aquila
2/25/2026 5:42:57 PM Request for Review Comments returned by PCD Engineering Division
2/19/2026 2:46:22 PM Request for Review Comments returned by EPC Stormwater Review
2/18/2026 10:34:10 AM Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
2/18/2026 6:31:05 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Zachary Jannusch on behalf of EPC Stormwater Review
2/18/2026 6:31:04 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
2/18/2026 6:31:04 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Glenn Reese on behalf of EPC Stormwater Review
2/18/2026 6:31:03 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Christina Prete on behalf of EPC Stormwater Review
2/17/2026 7:41:28 PM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Justin Kilgore on behalf of PCD Project Manager
2/17/2026 7:41:27 PM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
2/17/2026 7:41:26 PM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
2/17/2026 7:40:12 PM Request for Review Comments returned by PCD Project Manager
2/15/2026 9:42:25 AM Request for Review Comments returned by El Paso County Conservation Dist
2/6/2026 10:01:43 AM Request for Review Comments returned by County Attorney - Development Review
2/5/2026 8:38:09 AM Request for Review Comments returned by Pikes Peak Regional Building Department
2/3/2026 1:24:00 PM Request for Review Comments returned by Falcon Fire Protection District
2/3/2026 1:17:09 PM Request for Review Comments returned by Meadow Lake Airport Association
2/3/2026 9:01:36 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Dave Elliott on behalf of Meadow Lake Airport Association
2/3/2026 9:01:35 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Trent Harwig on behalf of Falcon Fire Protection District
2/3/2026 9:01:34 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Curtis Kauffman on behalf of Falcon Fire Protection District
2/3/2026 9:01:33 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by William Vogl on behalf of El Paso County Conservation Dist
2/3/2026 9:01:32 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Harry Thomas on behalf of El Paso County Conservation Dist
2/3/2026 9:01:31 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Katie Miller on behalf of El Paso County Conservation Dist
2/3/2026 9:01:30 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by on behalf of El Paso County Conservation Dist
2/3/2026 9:01:29 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Mariah Hudson on behalf of El Paso County Conservation Dist
2/3/2026 9:01:28 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Trish Riber on behalf of Black Hills Energy-Aquila
2/3/2026 9:01:27 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Marcus Henderson on behalf of Black Hills Energy-Aquila
2/3/2026 9:01:26 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Bob Swatek on behalf of Black Hills Energy-Aquila
2/3/2026 9:01:25 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Adam Magoon on behalf of Black Hills Energy-Aquila
2/3/2026 9:01:23 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by on behalf of Pikes Peak Regional Building Department
2/3/2026 9:01:22 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Daniel Delgado on behalf of US Army Corps of Engineers-Pueblo
2/3/2026 9:01:21 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
2/3/2026 9:01:20 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
2/3/2026 9:01:19 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Kimberly Blanchard on behalf of Colorado Department of Transportation - Pueblo Office
2/3/2026 9:01:18 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
2/3/2026 9:01:17 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Zachary Jannusch on behalf of EPC Stormwater Review
2/3/2026 9:01:16 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
2/3/2026 9:01:15 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Glenn Reese on behalf of EPC Stormwater Review
2/3/2026 9:01:14 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Christina Prete on behalf of EPC Stormwater Review
2/3/2026 9:01:13 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Mike McCarthy on behalf of EPC Health Department
2/3/2026 9:01:12 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Catherine McGarvy on behalf of EPC Health Department
2/3/2026 9:01:11 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by HEAEH LandUse on behalf of EPC Health Department
2/3/2026 9:01:10 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Lori Seago on behalf of County Attorney - Development Review
2/3/2026 9:01:09 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Erika Keech on behalf of County Attorney - Development Review
2/3/2026 9:01:08 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by April Willie on behalf of County Attorney - Development Review
2/3/2026 9:01:06 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Justin Kilgore on behalf of PCD Project Manager
2/3/2026 9:01:04 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
2/3/2026 9:01:04 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
2/3/2026 8:49:57 AM Submission Triaged
2/2/2026 4:43:29 PM Submission received from Applicant
6/23/2025 11:32:58 AM Request for Review Comments returned by Mountain View Electric Association, Inc.
6/17/2025 10:38:29 AM Request for Review Comments returned by Colorado Parks and Wildlife
6/10/2025 2:38:29 PM Request for Review Comments returned by Upper Black Squirrel Creek GWMD
6/3/2025 3:54:50 PM Submission request sent to Applicant
6/3/2025 3:43:45 PM Request for Review Comments returned by PCD Engineering Division
5/30/2025 7:18:07 AM Project Manager Assigned: Miranda Benson
5/30/2025 6:41:26 AM Request for Review Comments returned by Falcon School District 49
5/29/2025 1:27:33 PM Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
5/28/2025 4:17:03 PM Request for Review Comments returned by EPC Stormwater Review
5/28/2025 4:04:12 PM Request for Review Comments returned by PCD Project Manager
5/23/2025 2:20:23 PM Request for Review Comments returned by County Attorney - Development Review
5/22/2025 3:56:44 PM Project Manager Assigned: Ashlyn Mathy
5/22/2025 3:26:35 PM Project Manager Assigned: Miranda Benson
5/21/2025 1:36:29 PM Request for Review Comments returned by 911 Authority - El Paso/Teller County
5/21/2025 9:13:32 AM Request for Review Comments returned by Meadow Lake Airport Association
5/20/2025 11:06:56 AM Request for Review Comments returned by Pikes Peak Regional Building Department
5/19/2025 10:42:17 AM Request for Review Comments returned by Falcon Fire Protection District
5/14/2025 9:46:10 AM Request for Review Comments returned by RBD Floodplain
5/14/2025 8:43:10 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Lori Seago on behalf of County Attorney - Development Review
5/14/2025 8:43:09 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Erika Keech on behalf of County Attorney - Development Review
5/14/2025 8:43:08 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by April Willie on behalf of County Attorney - Development Review
5/14/2025 8:42:56 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by deric clemons on behalf of Natural Resources Conservation Service (Federal Agency)
5/14/2025 8:42:54 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by General Email on behalf of Mountain View Electric Association, Inc.
5/14/2025 8:42:53 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Dave Elliott on behalf of Meadow Lake Airport Association
5/14/2025 8:42:52 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Evelyn galanephillips on behalf of Falcon School District 49
5/14/2025 8:42:51 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Trent Harwig on behalf of Falcon Fire Protection District
5/14/2025 8:42:50 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Curtis Kauffman on behalf of Falcon Fire Protection District
5/14/2025 8:42:49 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Harry Thomas on behalf of El Paso County Conservation Dist
5/14/2025 8:42:48 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Oliver Watkins on behalf of El Paso County Conservation Dist
5/14/2025 8:42:47 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Katie Miller on behalf of El Paso County Conservation Dist
5/14/2025 8:42:46 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Erica Carter on behalf of El Paso County Conservation Dist
5/14/2025 8:42:45 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by on behalf of El Paso County Conservation Dist
5/14/2025 8:42:44 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Mariah Hudson on behalf of El Paso County Conservation Dist
5/14/2025 8:42:43 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Cassie Olgren on behalf of El Paso County Conservation Dist
5/14/2025 8:42:42 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Billy Richard on behalf of El Paso County Conservation Dist
5/14/2025 8:42:40 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Santiago Tijerina on behalf of Black Hills Energy-Aquila
5/14/2025 8:42:39 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Marcus Henderson on behalf of Black Hills Energy-Aquila
5/14/2025 8:42:38 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Bob Swatek on behalf of Black Hills Energy-Aquila
5/14/2025 8:42:37 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Adam Magoon on behalf of Black Hills Energy-Aquila
5/14/2025 8:42:36 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
5/14/2025 8:42:35 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Keith Curtis on behalf of RBD Floodplain
5/14/2025 8:42:34 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by on behalf of Pikes Peak Regional Building Department
5/14/2025 8:42:33 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
5/14/2025 8:42:32 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Glenn West on behalf of 911 Authority - El Paso/Teller County
5/14/2025 8:42:30 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Julie Reeves on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
5/14/2025 8:42:29 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by george san miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
5/14/2025 8:42:29 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
5/14/2025 8:42:27 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Daniel Delgado on behalf of US Army Corps of Engineers-Pueblo
5/14/2025 8:42:26 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Travis Sauder on behalf of Colorado Parks and Wildlife
5/14/2025 8:42:25 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Tim Kroening on behalf of Colorado Parks and Wildlife
5/14/2025 8:42:24 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Peter Chapman on behalf of Colorado Parks and Wildlife
5/14/2025 8:42:23 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Karen Voltura on behalf of Colorado Parks and Wildlife
5/14/2025 8:42:22 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Carolyn Craveiro de Sa on behalf of Colorado Parks and Wildlife
5/14/2025 8:42:20 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
5/14/2025 8:42:19 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
5/14/2025 8:42:17 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
5/14/2025 8:42:16 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by on behalf of Parks Advisory Board
5/14/2025 8:42:15 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Zachary Jannusch on behalf of EPC Stormwater Review
5/14/2025 8:42:14 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
5/14/2025 8:42:13 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Glenn Reese on behalf of EPC Stormwater Review
5/14/2025 8:42:12 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Christina Prete on behalf of EPC Stormwater Review
5/14/2025 8:42:11 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Mike McCarthy on behalf of EPC Health Department
5/14/2025 8:42:10 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Catherine McGarvy on behalf of EPC Health Department
5/14/2025 8:42:09 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by HEAEH LandUse on behalf of EPC Health Department
5/14/2025 8:42:08 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Justin Kilgore on behalf of PCD Project Manager
5/14/2025 8:42:04 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
5/14/2025 8:42:03 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
5/14/2025 8:39:53 AM Submission Triaged
5/14/2025 8:16:03 AM Submission received from Applicant
5/8/2025 2:38:09 PM Submission request sent to Applicant
5/7/2025 1:24:56 PM Submission request sent to Applicant
12/19/2024 10:30:18 AM Request for Review Comments returned by RBD Floodplain
12/19/2024 10:11:11 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Keith Curtis on behalf of RBD Floodplain
1/17/2024 11:29:51 AM Request for Review Comments returned by Falcon School District 49
1/16/2024 4:52:55 PM Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
1/9/2024 12:26:03 PM Request for Review Comments returned by El Paso County Conservation Dist
1/9/2024 12:25:33 PM Request for Review Comments returned by El Paso County Conservation Dist
1/4/2024 12:45:46 PM Request for Review Comments returned by Upper Black Squirrel Creek GWMD
1/3/2024 2:59:46 PM Submission request sent to Applicant
12/29/2023 4:09:03 PM Request for Review Comments returned by PCD Engineering Division
12/28/2023 2:01:01 PM Request for Review Comments returned by Colorado Parks and Wildlife
12/28/2023 9:09:46 AM Request for Review Comments returned by EPC Stormwater Review
12/27/2023 9:35:58 AM Request for Review Comments returned by PCD Project Manager
12/26/2023 11:09:34 AM Request for Review Comments returned by Mountain View Electric Association, Inc.
12/26/2023 11:08:53 AM Request for Review Comments returned by Mountain View Electric Association, Inc.
12/26/2023 9:07:57 AM Request for Review Comments returned by Parks Advisory Board
12/25/2023 9:12:27 AM Request for Review Comments returned by Meadow Lake Airport Association
12/25/2023 9:11:19 AM Request for Review Comments returned by Meadow Lake Airport Association
12/18/2023 8:41:25 AM Request for Review Comments returned by Falcon Fire Protection District
12/18/2023 8:39:51 AM Request for Review Comments returned by Falcon Fire Protection District
12/15/2023 10:13:51 AM Request for Review Comments returned by 911 Authority - El Paso/Teller County
12/13/2023 10:41:28 AM Request for Review Comments returned by Pikes Peak Regional Building Department
12/12/2023 9:25:04 AM Request for Review Comments returned by RBD Floodplain
12/12/2023 8:52:25 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by deric clemons on behalf of Natural Resources Conservation Service (Federal Agency)
12/12/2023 8:52:23 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by General Email on behalf of Mountain View Electric Association, Inc.
12/12/2023 8:52:20 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Dave Elliott on behalf of Meadow Lake Airport Association
12/12/2023 8:52:18 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Evelyn galanephillips on behalf of Falcon School District 49
12/12/2023 8:52:16 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Trent Harwig on behalf of Falcon Fire Protection District
12/12/2023 8:52:14 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Mariah Hudson on behalf of El Paso County Conservation Dist
12/12/2023 8:52:12 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Santiago Tijerina on behalf of Black Hills Energy-Aquila
12/12/2023 8:52:10 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Bob Swatek on behalf of Black Hills Energy-Aquila
12/12/2023 8:52:08 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Adam Magoon on behalf of Black Hills Energy-Aquila
12/12/2023 8:52:05 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
12/12/2023 8:52:03 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Keith Curtis on behalf of RBD Floodplain
12/12/2023 8:52:01 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by on behalf of Pikes Peak Regional Building Department
12/12/2023 8:51:59 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
12/12/2023 8:51:57 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Glenn West on behalf of 911 Authority - El Paso/Teller County
12/12/2023 8:51:54 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by george san miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
12/12/2023 8:51:52 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
12/12/2023 8:51:50 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Joseph Martinez on behalf of US Army Corps of Engineers-Pueblo
12/12/2023 8:51:48 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Tyson Floersheim on behalf of Colorado Parks and Wildlife
12/12/2023 8:51:46 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Travis Sauder on behalf of Colorado Parks and Wildlife
12/12/2023 8:51:44 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Tim Kroening on behalf of Colorado Parks and Wildlife
12/12/2023 8:51:42 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Sarah Watson on behalf of Colorado Parks and Wildlife
12/12/2023 8:51:40 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Philip Gurule on behalf of Colorado Parks and Wildlife
12/12/2023 8:51:38 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Karen Voltura on behalf of Colorado Parks and Wildlife
12/12/2023 8:51:36 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Corey Adler on behalf of Colorado Parks and Wildlife
12/12/2023 8:51:34 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Cassidy English on behalf of Colorado Parks and Wildlife
12/12/2023 8:51:32 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Drew Vrbenec on behalf of Colorado Parks and Wildlife
12/12/2023 8:51:30 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Aaron Berscheid on behalf of Colorado Parks and Wildlife
12/12/2023 8:51:28 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
12/12/2023 8:51:25 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
12/12/2023 8:51:23 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Arthur Gonzales on behalf of Colorado Department of Transportation - Pueblo Office
12/12/2023 8:51:21 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
12/12/2023 8:51:19 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by on behalf of Parks Advisory Board
12/12/2023 8:51:16 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
12/12/2023 8:51:14 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Glenn Reese on behalf of EPC Stormwater Review
12/12/2023 8:51:12 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Christina Prete on behalf of EPC Stormwater Review
12/12/2023 8:51:10 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Mike McCarthy on behalf of EPC Health Department
12/12/2023 8:51:08 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Catherine McGarvy on behalf of EPC Health Department
12/12/2023 8:51:06 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by HEAEH LandUse on behalf of EPC Health Department
12/12/2023 8:51:04 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by deric clemons on behalf of Natural Resources Conservation Service (Federal Agency)
12/12/2023 8:51:02 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Lupe Packman on behalf of PCD Engineering Division
12/12/2023 8:51:01 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by General Email on behalf of Mountain View Electric Association, Inc.
12/12/2023 8:50:59 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Dave Elliott on behalf of Meadow Lake Airport Association
12/12/2023 8:50:59 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
12/12/2023 8:50:57 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
12/12/2023 8:50:57 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Trent Harwig on behalf of Falcon Fire Protection District
12/12/2023 8:50:54 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Edward Schoenheit on behalf of PCD Engineering Division
12/12/2023 8:50:53 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Mariah Hudson on behalf of El Paso County Conservation Dist
12/12/2023 8:50:50 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
12/12/2023 8:50:50 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Santiago Tijerina on behalf of Black Hills Energy-Aquila
12/12/2023 8:50:48 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Bob Swatek on behalf of Black Hills Energy-Aquila
12/12/2023 8:50:48 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Charlene Durham on behalf of PCD Engineering Division
12/12/2023 8:50:45 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Carlos Hernandez Martinez on behalf of PCD Engineering Division
12/12/2023 8:50:45 AM Request for Review Comments email sent for Project 4-Way Commercial Site Development Plan for review by Adam Magoon on behalf of Black Hills Energy-Aquila
12/5/2023 3:53:20 PM Fees paid: 12/5/2023 (Receipt: 1008581)
12/5/2023 11:26:50 AM Project Manager Assigned: Ashlyn Mathy
12/5/2023 11:20:51 AM Payment Request sent: 12/5/2023
12/5/2023 11:20:51 AM File # Assigned: PPR2347
12/5/2023 11:20:41 AM Submission Triaged
12/5/2023 9:22:01 AM Submission received from Applicant
12/5/2023 8:16:16 AM Submission request sent to Applicant
12/1/2023 4:05:08 PM Submission request sent to Applicant
12/1/2023 4:04:55 PM Submission Triaged
12/1/2023 10:29:46 AM Submission received from Applicant
11/8/2023 12:44:29 PM Submission request sent to Applicant
2/8/2023 7:38:29 AM Submission request sent to Applicant
2/3/2023 10:48:11 AM Project Manager Assigned: Ryan Howser
2/3/2023 10:48:11 AM EA Assigned: EA22107
2/3/2023 10:48:11 AM Project Created