6/10/2025 3:06:38 PM
|
Request for Review Comments returned by PCD Engineering Division
|
6/10/2025 2:14:49 PM
|
Request for Review Comments returned by PCD Project Manager
|
5/27/2025 10:23:59 AM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Justin Kilgore on behalf of PCD Project Manager
|
5/27/2025 10:23:58 AM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
|
5/27/2025 10:23:56 AM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
|
5/27/2025 10:21:50 AM
|
Submission Triaged
|
5/23/2025 5:05:27 PM
|
Submission received from Applicant
|
5/22/2025 3:57:36 PM
|
Project Manager Assigned: Kylie Bagley
|
5/19/2025 3:32:01 PM
|
Submission request sent to Applicant
|
5/19/2025 3:30:38 PM
|
Request for Review Comments returned by PCD Project Manager
|
5/19/2025 2:01:56 PM
|
Request for Review Comments returned by PCD Engineering Division
|
5/13/2025 11:15:30 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
5/2/2025 2:37:21 PM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Zachary Jannusch on behalf of EPC Stormwater Review
|
5/2/2025 2:37:20 PM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
5/2/2025 2:37:19 PM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Glenn Reese on behalf of EPC Stormwater Review
|
5/2/2025 2:37:18 PM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Christina Prete on behalf of EPC Stormwater Review
|
5/2/2025 2:37:17 PM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Justin Kilgore on behalf of PCD Project Manager
|
5/2/2025 2:37:15 PM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
|
5/2/2025 2:37:13 PM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
|
5/2/2025 2:36:05 PM
|
Submission Triaged
|
5/2/2025 2:33:52 PM
|
Submission received from Applicant
|
4/21/2025 7:34:53 AM
|
Submission request sent to Applicant
|
1/28/2025 2:39:01 PM
|
Submission request sent to Applicant
|
7/30/2024 8:02:40 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
7/26/2024 3:41:29 PM
|
Request for Review Comments returned by PCD Project Manager
|
7/26/2024 9:51:27 AM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Shannon Mustoe on behalf of EPC Stormwater Review
|
7/26/2024 9:51:25 AM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
7/26/2024 9:51:24 AM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Glenn Reese on behalf of EPC Stormwater Review
|
7/26/2024 9:51:22 AM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Christina Prete on behalf of EPC Stormwater Review
|
7/25/2024 3:23:37 PM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Kari Parsons on behalf of PCD Project Manager
|
7/25/2024 3:22:52 PM
|
Submission Triaged
|
7/25/2024 11:28:24 AM
|
Submission received from Applicant
|
7/25/2024 10:59:26 AM
|
Submission request sent to Applicant
|
7/25/2024 10:58:47 AM
|
Request for Review Comments returned by PCD Project Manager
|
7/24/2024 5:51:31 PM
|
Request for Review Comments returned by PCD Engineering Division
|
7/10/2024 9:15:47 AM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Kari Parsons on behalf of PCD Project Manager
|
7/10/2024 9:15:43 AM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
|
7/10/2024 9:15:39 AM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
|
7/10/2024 9:14:08 AM
|
Submission Triaged
|
7/9/2024 4:39:52 PM
|
Submission received from Applicant
|
6/10/2024 8:29:43 AM
|
Submission request sent to Applicant
|
6/10/2024 8:28:27 AM
|
Request for Review Comments returned by PCD Project Manager
|
6/6/2024 1:59:09 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
6/6/2024 12:46:08 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
6/4/2024 11:29:50 AM
|
Request for Review Comments returned by PCD Engineering Division
|
5/23/2024 1:02:52 PM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Lori Seago on behalf of County Attorney - Development Review
|
5/23/2024 1:02:51 PM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Erika Keech on behalf of County Attorney - Development Review
|
5/23/2024 1:02:49 PM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by April Willie on behalf of County Attorney - Development Review
|
5/23/2024 12:50:23 PM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Shannon Mustoe on behalf of EPC Stormwater Review
|
5/23/2024 12:50:22 PM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
5/23/2024 12:50:20 PM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Glenn Reese on behalf of EPC Stormwater Review
|
5/23/2024 12:50:18 PM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Christina Prete on behalf of EPC Stormwater Review
|
5/23/2024 12:50:16 PM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Kari Parsons on behalf of PCD Project Manager
|
5/23/2024 12:50:12 PM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
|
5/23/2024 12:50:08 PM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
|
5/23/2024 12:48:41 PM
|
Submission Triaged
|
5/22/2024 10:21:56 AM
|
Submission received from Applicant
|
1/9/2024 12:23:40 PM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
11/30/2023 11:46:25 AM
|
Submission request sent to Applicant
|
11/30/2023 11:44:20 AM
|
Request for Review Comments returned by PCD Project Manager
|
11/30/2023 11:28:11 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
11/30/2023 11:24:01 AM
|
Request for Review Comments email resent for Project Meridian Storage Site Development Plan for review by Christina Prete on behalf of EPC Stormwater Review
|
11/29/2023 3:42:07 PM
|
Request for Review Comments returned by PCD Engineering Division
|
11/29/2023 1:32:57 PM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Mariah Hudson on behalf of El Paso County Conservation Dist
|
11/29/2023 1:24:48 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
11/15/2023 9:47:27 AM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
11/15/2023 9:47:25 AM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Glenn Reese on behalf of EPC Stormwater Review
|
11/15/2023 9:47:22 AM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Christina Prete on behalf of EPC Stormwater Review
|
11/15/2023 9:47:16 AM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Mike McCarthy on behalf of EPC Health Department
|
11/15/2023 9:47:14 AM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Catherine McGarvy on behalf of EPC Health Department
|
11/15/2023 9:47:12 AM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by HEAEH LandUse on behalf of EPC Health Department
|
11/15/2023 9:47:08 AM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Lupe Packman on behalf of PCD Engineering Division
|
11/15/2023 9:47:06 AM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
|
11/15/2023 9:47:04 AM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
11/15/2023 9:47:02 AM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Edward Schoenheit on behalf of PCD Engineering Division
|
11/15/2023 9:46:59 AM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
|
11/15/2023 9:46:55 AM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Charlene Durham on behalf of PCD Engineering Division
|
11/15/2023 9:46:53 AM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Carlos Hernandez Martinez on behalf of PCD Engineering Division
|
11/13/2023 1:41:31 PM
|
Project Manager Assigned: Ashlyn Mathy
|
11/13/2023 9:05:45 AM
|
Submission Triaged
|
11/9/2023 4:11:28 PM
|
Submission received from Applicant
|
11/9/2023 3:20:09 PM
|
Submission request sent to Applicant
|
10/31/2023 3:44:12 PM
|
Request for Review Comments returned by Falcon School District 49
|
10/3/2023 11:11:17 AM
|
Submission request sent to Applicant
|
10/3/2023 11:06:00 AM
|
Request for Review Comments returned by PCD Project Manager
|
9/28/2023 9:46:15 PM
|
Request for Review Comments returned by PCD Engineering Division
|
9/28/2023 5:55:31 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
9/27/2023 10:09:08 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
9/26/2023 12:12:24 PM
|
Request for Review Comments returned by Falcon Fire Protection District
|
9/25/2023 12:40:05 PM
|
Fees paid: 9/25/2023 (Receipt: 1008338)
|
9/18/2023 2:43:00 PM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
9/13/2023 2:38:22 PM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
9/13/2023 2:38:21 PM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Evelyn galanephillips on behalf of Falcon School District 49
|
9/13/2023 2:38:20 PM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Fire Chief Trent Harwig on behalf of Falcon Fire Protection District
|
9/13/2023 2:38:19 PM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by UDS Admin Staff on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
9/13/2023 2:38:18 PM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Supervisor Bob Swatek on behalf of Black Hills Energy-Aquila
|
9/13/2023 2:38:17 PM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
9/13/2023 2:38:13 PM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Catherine McGarvy on behalf of EPC Health Department
|
9/13/2023 2:38:10 PM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Lekishia Bellamy on behalf of PCD Project Manager
|
9/13/2023 2:38:09 PM
|
Request for Review Comments email sent for Project Meridian Storage Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
9/12/2023 12:25:03 PM
|
Project Manager Assigned: Lekishia Bellamy
|
9/12/2023 8:27:56 AM
|
Payment Request sent: 9/12/2023
|
9/12/2023 8:27:46 AM
|
File # Assigned: PPR2336
|
9/12/2023 8:27:21 AM
|
Submission Triaged
|
9/11/2023 3:32:58 AM
|
Submission received from Applicant
|
8/25/2023 2:09:43 PM
|
Submission request sent to Applicant
|
8/25/2023 1:20:24 PM
|
Project reopened for Review Comments
|
4/22/2023 12:00:00 AM
|
Project Closed
|
4/22/2023 12:00:00 AM
|
Project Expired one year after 04/22/2022 Submission Request 04/22/2023
|
4/22/2022 4:17:35 PM
|
Submission request sent to Applicant
|
4/22/2022 9:52:58 AM
|
Project Manager Assigned: Kylie Bagley
|
4/22/2022 9:52:58 AM
|
EA Assigned: EA2270
|
4/22/2022 9:52:58 AM
|
Project Created
|