| 9/22/2025 12:05:56 PM | Submission request sent to Applicant | 
                
                    | 9/3/2024 2:22:24 PM | Submission request sent to Applicant | 
                
                    | 9/3/2024 2:21:27 PM | Submission request sent to Applicant | 
                
                    | 9/3/2024 12:58:24 PM | Request for Review Comments returned by PCD Engineering Division | 
                
                    | 9/3/2024 12:57:54 PM | Request for Review Comments returned by PCD Project Manager | 
                
                    | 8/29/2024 4:35:37 PM | Request for Review Comments returned by EPC Stormwater Review | 
                
                    | 8/12/2024 1:42:43 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Shannon Mustoe on behalf of EPC Stormwater Review | 
                
                    | 8/12/2024 1:42:41 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Mikayla Hartford on behalf of EPC Stormwater Review | 
                
                    | 8/12/2024 1:42:39 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Glenn Reese on behalf of EPC Stormwater Review | 
                
                    | 8/12/2024 1:42:37 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Christina Prete on behalf of EPC Stormwater Review | 
                
                    | 8/12/2024 1:42:35 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by  on behalf of EPC Public Works, County Engineer | 
                
                    | 8/12/2024 1:42:34 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by  on behalf of EPC Public Works, County Engineer | 
                
                    | 8/12/2024 1:42:31 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Kari Parsons on behalf of PCD Project Manager | 
                
                    | 8/12/2024 1:42:28 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Gilbert LaForce on behalf of PCD Engineering Division | 
                
                    | 8/12/2024 1:42:26 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Engineering Manager on behalf of PCD Engineering Division | 
                
                    | 8/12/2024 1:40:07 PM | Submission Triaged | 
                
                    | 8/12/2024 1:37:53 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Daniel Delgado on behalf of US Army Corps of Engineers-Pueblo | 
                
                    | 8/12/2024 1:37:51 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Shannon Mustoe on behalf of EPC Stormwater Review | 
                
                    | 8/12/2024 1:37:49 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Mikayla Hartford on behalf of EPC Stormwater Review | 
                
                    | 8/12/2024 1:37:47 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Glenn Reese on behalf of EPC Stormwater Review | 
                
                    | 8/12/2024 1:37:46 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Christina Prete on behalf of EPC Stormwater Review | 
                
                    | 8/12/2024 1:37:44 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by  on behalf of EPC Public Works, County Engineer | 
                
                    | 8/12/2024 1:37:42 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by  on behalf of EPC Public Works, County Engineer | 
                
                    | 8/12/2024 1:37:40 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Kari Parsons on behalf of PCD Project Manager | 
                
                    | 8/12/2024 1:37:36 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Gilbert LaForce on behalf of PCD Engineering Division | 
                
                    | 8/12/2024 1:37:34 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Engineering Manager on behalf of PCD Engineering Division | 
                
                    | 8/12/2024 1:35:42 PM | Submission received from Applicant | 
                
                    | 8/1/2024 5:03:08 PM | Request for Review Comments returned by EPC Stormwater Review | 
                
                    | 8/1/2024 4:50:48 PM | Submission request sent to Applicant | 
                
                    | 8/1/2024 4:49:39 PM | Request for Review Comments returned by PCD Project Manager | 
                
                    | 8/1/2024 4:07:37 PM | Request for Review Comments returned by PCD Engineering Division | 
                
                    | 7/11/2024 4:47:07 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Shannon Mustoe on behalf of EPC Stormwater Review | 
                
                    | 7/11/2024 4:47:05 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Mikayla Hartford on behalf of EPC Stormwater Review | 
                
                    | 7/11/2024 4:47:03 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Glenn Reese on behalf of EPC Stormwater Review | 
                
                    | 7/11/2024 4:47:01 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Christina Prete on behalf of EPC Stormwater Review | 
                
                    | 7/11/2024 4:46:59 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Kari Parsons on behalf of PCD Project Manager | 
                
                    | 7/11/2024 4:46:55 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Gilbert LaForce on behalf of PCD Engineering Division | 
                
                    | 7/11/2024 4:46:53 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Engineering Manager on behalf of PCD Engineering Division | 
                
                    | 7/11/2024 4:45:26 PM | Submission Triaged | 
                
                    | 7/11/2024 3:48:20 PM | Submission received from Applicant | 
                
                    | 6/11/2024 10:57:47 AM | Submission request sent to Applicant | 
                
                    | 6/11/2024 10:56:08 AM | Request for Review Comments returned by PCD Project Manager | 
                
                    | 6/11/2024 8:49:27 AM | Request for Review Comments returned by PCD Engineering Division | 
                
                    | 6/10/2024 12:56:32 PM | Request for Review Comments returned by EPC Stormwater Review | 
                
                    | 5/20/2024 5:04:03 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Daniel Delgado on behalf of US Army Corps of Engineers-Pueblo | 
                
                    | 5/20/2024 5:04:01 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Shannon Mustoe on behalf of EPC Stormwater Review | 
                
                    | 5/20/2024 5:03:59 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Mikayla Hartford on behalf of EPC Stormwater Review | 
                
                    | 5/20/2024 5:03:57 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Glenn Reese on behalf of EPC Stormwater Review | 
                
                    | 5/20/2024 5:03:55 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Christina Prete on behalf of EPC Stormwater Review | 
                
                    | 5/20/2024 5:03:53 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Kari Parsons on behalf of PCD Project Manager | 
                
                    | 5/20/2024 5:03:49 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Gilbert LaForce on behalf of PCD Engineering Division | 
                
                    | 5/20/2024 5:03:48 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Engineering Manager on behalf of PCD Engineering Division | 
                
                    | 5/20/2024 5:02:02 PM | Submission Triaged | 
                
                    | 5/20/2024 4:24:41 PM | Submission received from Applicant | 
                
                    | 5/6/2024 9:53:29 AM | Submission request sent to Applicant | 
                
                    | 5/6/2024 8:49:27 AM | Request for Review Comments returned by RBD Floodplain | 
                
                    | 5/6/2024 8:40:13 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Tracy Doran on behalf of Upper Black Squirrel Creek GWMD | 
                
                    | 5/6/2024 8:40:11 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Keith Curtis on behalf of RBD Floodplain | 
                
                    | 5/6/2024 8:40:09 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Joseph Martinez on behalf of US Army Corps of Engineers-Pueblo | 
                
                    | 5/6/2024 8:40:07 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Travis Sauder on behalf of Colorado Parks and Wildlife | 
                
                    | 5/6/2024 8:40:05 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Tim Kroening on behalf of Colorado Parks and Wildlife | 
                
                    | 5/6/2024 8:40:03 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Karen Voltura on behalf of Colorado Parks and Wildlife | 
                
                    | 5/6/2024 8:40:01 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Cassidy English on behalf of Colorado Parks and Wildlife | 
                
                    | 5/6/2024 8:39:55 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office | 
                
                    | 5/6/2024 8:39:53 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office | 
                
                    | 5/6/2024 8:39:51 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Arthur Gonzales on behalf of Colorado Department of Transportation - Pueblo Office | 
                
                    | 5/6/2024 8:39:49 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office | 
                
                    | 5/6/2024 8:39:47 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Shannon Mustoe on behalf of EPC Stormwater Review | 
                
                    | 5/6/2024 8:39:45 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Mikayla Hartford on behalf of EPC Stormwater Review | 
                
                    | 5/6/2024 8:39:44 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Glenn Reese on behalf of EPC Stormwater Review | 
                
                    | 5/6/2024 8:39:42 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Christina Prete on behalf of EPC Stormwater Review | 
                
                    | 5/6/2024 8:39:40 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Kari Parsons on behalf of PCD Project Manager | 
                
                    | 5/6/2024 8:39:36 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Gilbert LaForce on behalf of PCD Engineering Division | 
                
                    | 5/6/2024 8:39:34 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Engineering Manager on behalf of PCD Engineering Division | 
                
                    | 5/6/2024 8:37:10 AM | Submission Triaged | 
                
                    | 5/6/2024 8:35:20 AM | Submission received from Applicant | 
                
                    | 5/6/2024 7:11:13 AM | Submission request sent to Applicant | 
                
                    | 3/19/2024 9:56:58 AM | Request for Review Comments returned by EPC Stormwater Review | 
                
                    | 3/19/2024 9:38:45 AM | Request for Review Comments returned by PCD Engineering Division | 
                
                    | 3/13/2024 3:04:22 PM | Request for Review Comments returned by PCD Project Manager | 
                
                    | 3/1/2024 10:07:34 AM | Request for Review Comments returned by EPC Parks Department | 
                
                    | 2/26/2024 3:56:01 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Joseph Martinez on behalf of US Army Corps of Engineers-Pueblo | 
                
                    | 2/26/2024 3:55:59 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Justin Osborne on behalf of Colorado State Land Board | 
                
                    | 2/26/2024 3:55:57 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Mikayla Hartford on behalf of EPC Stormwater Review | 
                
                    | 2/26/2024 3:55:55 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Glenn Reese on behalf of EPC Stormwater Review | 
                
                    | 2/26/2024 3:55:53 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Christina Prete on behalf of EPC Stormwater Review | 
                
                    | 2/26/2024 3:55:51 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by  on behalf of EPC Parks Department | 
                
                    | 2/26/2024 3:55:45 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Gilbert LaForce on behalf of PCD Engineering Division | 
                
                    | 2/26/2024 3:55:43 PM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Engineering Manager on behalf of PCD Engineering Division | 
                
                    | 2/26/2024 10:46:57 AM | Submission Triaged | 
                
                    | 2/26/2024 10:44:36 AM | Submission received from Applicant | 
                
                    | 6/5/2023 11:21:26 AM | Request for Review Comments returned by Upper Black Squirrel Creek GWMD | 
                
                    | 5/12/2023 2:23:17 PM | Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office | 
                
                    | 5/5/2023 10:59:30 AM | Request for Review Comments returned by El Paso County Conservation Dist | 
                
                    | 5/3/2023 3:29:07 PM | Submission request sent to Applicant | 
                
                    | 5/3/2023 3:22:43 PM | Request for Review Comments returned by PCD Engineering Division | 
                
                    | 4/28/2023 8:48:59 PM | Submission request sent to Applicant | 
                
                    | 4/28/2023 8:48:01 PM | Request for Review Comments returned by PCD Project Manager | 
                
                    | 4/27/2023 2:06:12 PM | Request for Review Comments returned by EPC Stormwater Review | 
                
                    | 4/20/2023 4:43:08 PM | Request for Review Comments returned by Colorado Parks and Wildlife | 
                
                    | 4/4/2023 11:10:45 AM | Request for Review Comments returned by EPC Parks Department | 
                
                    | 4/3/2023 10:34:20 AM | Request for Review Comments returned by RBD Floodplain | 
                
                    | 3/31/2023 1:56:10 PM | Request for Review Comments returned by EPC Environmental Services | 
                
                    | 3/30/2023 10:41:27 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by District Manager Pamela Davison on behalf of El Paso County Conservation Dist | 
                
                    | 3/30/2023 10:41:26 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD | 
                
                    | 3/30/2023 10:41:25 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Keith Curtis on behalf of RBD Floodplain | 
                
                    | 3/30/2023 10:41:24 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Joseph Martinez on behalf of US Army Corps of Engineers-Pueblo | 
                
                    | 3/30/2023 10:41:23 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Justin Osborne on behalf of Colorado State Land Board | 
                
                    | 3/30/2023 10:41:19 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Tim Kroening on behalf of Colorado Parks and Wildlife | 
                
                    | 3/30/2023 10:41:16 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by CDOT Permits Manager Valerie Vigil on behalf of Colorado Department of Transportation - Pueblo Office | 
                
                    | 3/30/2023 10:41:14 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review | 
                
                    | 3/30/2023 10:41:11 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Joshua Palmer on behalf of EPC Public Works, County Engineer | 
                
                    | 3/30/2023 10:41:09 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by  on behalf of EPC Parks Department | 
                
                    | 3/30/2023 10:41:08 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Kathy Andrew on behalf of EPC Environmental Services | 
                
                    | 3/30/2023 10:41:07 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Kari Parsons on behalf of PCD Project Manager | 
                
                    | 3/30/2023 10:41:05 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Elizabeth Nijkamp on behalf of PCD Engineering Division | 
                
                    | 3/30/2023 10:39:59 AM | Submission Triaged | 
                
                    | 3/30/2023 9:09:09 AM | Submission received from Applicant | 
                
                    | 6/29/2022 11:44:17 AM | Request for Review Comments returned by Colorado Parks and Wildlife | 
                
                    | 6/16/2022 10:07:17 AM | Submission request sent to Applicant | 
                
                    | 6/16/2022 10:00:08 AM | Request for Review Comments returned by PCD Engineering Division | 
                
                    | 6/15/2022 5:34:56 PM | Request for Review Comments returned by EPC Stormwater Review | 
                
                    | 6/14/2022 8:01:29 AM | Request for Review Comments returned by PCD Project Manager | 
                
                    | 6/7/2022 3:43:22 PM | Request for Review Comments returned by EPC Parks Department | 
                
                    | 6/2/2022 7:42:55 PM | Request for Review Comments returned by El Paso County Conservation Dist | 
                
                    | 5/24/2022 10:57:14 AM | Request for Review Comments returned by EPC Environmental Services | 
                
                    | 5/23/2022 9:58:31 AM | Request for Review Comments returned by RBD Floodplain | 
                
                    | 5/23/2022 7:29:15 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by District Manager Pamela Davison on behalf of El Paso County Conservation Dist | 
                
                    | 5/23/2022 7:29:14 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD | 
                
                    | 5/23/2022 7:29:12 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Keith Curtis on behalf of RBD Floodplain | 
                
                    | 5/23/2022 7:29:11 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Joseph Martinez on behalf of US Army Corps of Engineers-Pueblo | 
                
                    | 5/23/2022 7:29:10 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Justin Osborne on behalf of Colorado State Land Board | 
                
                    | 5/23/2022 7:29:09 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Tim Kroening on behalf of Colorado Parks and Wildlife | 
                
                    | 5/23/2022 7:29:08 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by CDOT Permits Manager Valerie Vigil on behalf of Colorado Department of Transportation - Pueblo Office | 
                
                    | 5/23/2022 7:29:03 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review | 
                
                    | 5/23/2022 7:28:58 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer | 
                
                    | 5/23/2022 7:28:57 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by  on behalf of EPC Parks Department | 
                
                    | 5/23/2022 7:28:55 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Kathy Andrew on behalf of EPC Environmental Services | 
                
                    | 5/23/2022 7:28:54 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Kari Parsons on behalf of PCD Project Manager | 
                
                    | 5/23/2022 7:28:52 AM | Request for Review Comments email sent for Project Grandview Reserve Geick Basin Channel  for review by Elizabeth Nijkamp on behalf of PCD Engineering Division | 
                
                    | 5/20/2022 12:13:14 PM | Fees paid: 5/20/2022 (Receipt: 1006367) | 
                
                    | 5/16/2022 5:14:58 PM | Payment Request sent: 5/16/2022 | 
                
                    | 5/16/2022 5:14:58 PM | File # Assigned: CDR228 | 
                
                    | 5/16/2022 5:14:54 PM | Submission Triaged | 
                
                    | 5/16/2022 9:45:59 AM | Submission received from Applicant | 
                
                    | 5/12/2022 1:46:04 PM | Submission request sent to Applicant | 
                
                    | 5/12/2022 1:45:55 PM | Submission Triaged | 
                
                    | 5/12/2022 1:16:06 PM | Submission received from Applicant | 
                
                    | 5/10/2022 2:32:32 PM | Submission request sent to Applicant | 
                
                    | 3/22/2022 5:08:44 PM | Submission request sent to Applicant | 
                
                    | 3/22/2022 5:04:31 PM | Project Manager Assigned: Kari Parsons | 
                
                    | 3/22/2022 5:04:30 PM | EA Assigned: EA20175 | 
                
                    | 3/22/2022 5:04:30 PM | Project Created |