| 5/21/2025 7:53:51 AM | Submission request sent to Applicant | 
                
                    | 5/5/2025 11:49:20 AM | Submission request sent to Applicant | 
                
                    | 5/5/2025 11:48:36 AM | Request for Review Comments returned by PCD Project Manager | 
                
                    | 5/5/2025 11:24:51 AM | Request for Review Comments returned by PCD Engineering Division | 
                
                    | 5/5/2025 9:44:13 AM | Request for Review Comments email resent for Project Ford Dimensional Boundary Line Adjustment for review by Engineering Manager on behalf of PCD Engineering Division | 
                
                    | 4/29/2025 4:08:31 PM | Request for Review Comments returned by PCD Engineering Division | 
                
                    | 4/9/2025 8:57:15 AM | Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by Justin Kilgore on behalf of PCD Project Manager | 
                
                    | 4/9/2025 8:57:14 AM | Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by Gilbert LaForce on behalf of PCD Engineering Division | 
                
                    | 4/9/2025 8:57:12 AM | Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by Engineering Manager on behalf of PCD Engineering Division | 
                
                    | 4/9/2025 8:53:22 AM | Submission Triaged | 
                
                    | 4/8/2025 4:15:12 PM | Submission received from Applicant | 
                
                    | 4/8/2025 1:10:01 PM | Submission request sent to Applicant | 
                
                    | 4/8/2025 1:09:39 PM | Submission Triaged | 
                
                    | 4/7/2025 4:41:35 PM | Submission received from Applicant | 
                
                    | 2/12/2025 2:11:36 PM | Request for Review Comments returned by EPC Stormwater Review | 
                
                    | 2/7/2025 5:10:38 PM | Request for Review Comments returned by EPC Health Department | 
                
                    | 2/6/2025 5:39:58 PM | Request for Review Comments returned by PCD Engineering Division | 
                
                    | 2/3/2025 7:21:18 AM | Request for Review Comments returned by Academy SD 20 Building Fund | 
                
                    | 1/27/2025 3:35:51 PM | Request for Review Comments returned by Mountain View Electric Association, Inc. | 
                
                    | 1/24/2025 3:18:52 PM | Request for Review Comments returned by PCD Project Manager | 
                
                    | 1/24/2025 3:05:15 PM | Submission request sent to Applicant | 
                
                    | 1/23/2025 11:31:47 AM | Project Manager Assigned: Lisa Elgin | 
                
                    | 1/23/2025 11:30:48 AM | Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by General Email on behalf of Mountain View Electric Association, Inc. | 
                
                    | 1/23/2025 11:30:47 AM | Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by  on behalf of Black Forest Fire Protection District | 
                
                    | 1/23/2025 11:30:46 AM | Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by Tom Gregory on behalf of Academy SD 20 Building Fund | 
                
                    | 1/23/2025 11:30:44 AM | Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by Donald Smith on behalf of Academy SD 20 Building Fund | 
                
                    | 1/23/2025 11:30:43 AM | Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by Becky Allan on behalf of Academy SD 20 Building Fund | 
                
                    | 1/23/2025 11:30:42 AM | Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by Mikayla Hartford on behalf of EPC Stormwater Review | 
                
                    | 1/23/2025 11:30:41 AM | Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by Glenn Reese on behalf of EPC Stormwater Review | 
                
                    | 1/23/2025 11:30:40 AM | Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by Christina Prete on behalf of EPC Stormwater Review | 
                
                    | 1/23/2025 11:30:39 AM | Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by Mike McCarthy on behalf of EPC Health Department | 
                
                    | 1/23/2025 11:30:38 AM | Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by Catherine McGarvy on behalf of EPC Health Department | 
                
                    | 1/23/2025 11:30:37 AM | Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by HEAEH LandUse on behalf of EPC Health Department | 
                
                    | 1/23/2025 11:30:35 AM | Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by Justin Kilgore on behalf of PCD Project Manager | 
                
                    | 1/23/2025 11:30:34 AM | Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by Gilbert LaForce on behalf of PCD Engineering Division | 
                
                    | 1/23/2025 11:30:33 AM | Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by Engineering Manager on behalf of PCD Engineering Division | 
                
                    | 1/21/2025 6:04:06 PM | Fees paid: 1/21/2025 (Receipt: 1010076) | 
                
                    | 1/21/2025 12:00:29 PM | Payment Request sent: 1/21/2025 | 
                
                    | 1/21/2025 12:00:22 PM | File # Assigned: EXBL252 | 
                
                    | 1/21/2025 11:59:24 AM | Submission Triaged | 
                
                    | 1/17/2025 12:08:56 PM | Submission received from Applicant | 
                
                    | 1/3/2025 10:37:53 AM | Submission request sent to Applicant | 
                
                    | 1/3/2025 10:22:43 AM | Submission request sent to Applicant | 
                
                    | 1/3/2025 10:22:20 AM | Project reopened for Review Comments | 
                
                    | 3/4/2023 12:00:00 AM | Project Closed | 
                
                    | 3/4/2023 12:00:00 AM | Project Expired one year after 03/04/2022 Submission Request 03/04/2023 | 
                
                    | 3/4/2022 1:55:30 PM | Submission request sent to Applicant | 
                
                    | 3/3/2022 11:50:43 AM | Project Manager Assigned: Kylie Bagley | 
                
                    | 3/3/2022 11:50:42 AM | EA Assigned: EA2231 | 
                
                    | 3/3/2022 11:50:42 AM | Project Created |