5/21/2025 7:53:51 AM
|
Submission request sent to Applicant
|
5/5/2025 11:49:20 AM
|
Submission request sent to Applicant
|
5/5/2025 11:48:36 AM
|
Request for Review Comments returned by PCD Project Manager
|
5/5/2025 11:24:51 AM
|
Request for Review Comments returned by PCD Engineering Division
|
5/5/2025 9:44:13 AM
|
Request for Review Comments email resent for Project Ford Dimensional Boundary Line Adjustment for review by Engineering Manager on behalf of PCD Engineering Division
|
4/29/2025 4:08:31 PM
|
Request for Review Comments returned by PCD Engineering Division
|
4/9/2025 8:57:15 AM
|
Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by Justin Kilgore on behalf of PCD Project Manager
|
4/9/2025 8:57:14 AM
|
Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by Gilbert LaForce on behalf of PCD Engineering Division
|
4/9/2025 8:57:12 AM
|
Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by Engineering Manager on behalf of PCD Engineering Division
|
4/9/2025 8:53:22 AM
|
Submission Triaged
|
4/8/2025 4:15:12 PM
|
Submission received from Applicant
|
4/8/2025 1:10:01 PM
|
Submission request sent to Applicant
|
4/8/2025 1:09:39 PM
|
Submission Triaged
|
4/7/2025 4:41:35 PM
|
Submission received from Applicant
|
2/12/2025 2:11:36 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
2/7/2025 5:10:38 PM
|
Request for Review Comments returned by EPC Health Department
|
2/6/2025 5:39:58 PM
|
Request for Review Comments returned by PCD Engineering Division
|
2/3/2025 7:21:18 AM
|
Request for Review Comments returned by Academy SD 20 Building Fund
|
1/27/2025 3:35:51 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
1/24/2025 3:18:52 PM
|
Request for Review Comments returned by PCD Project Manager
|
1/24/2025 3:05:15 PM
|
Submission request sent to Applicant
|
1/23/2025 11:31:47 AM
|
Project Manager Assigned: Lisa Elgin
|
1/23/2025 11:30:48 AM
|
Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by General Email on behalf of Mountain View Electric Association, Inc.
|
1/23/2025 11:30:47 AM
|
Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by on behalf of Black Forest Fire Protection District
|
1/23/2025 11:30:46 AM
|
Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by Tom Gregory on behalf of Academy SD 20 Building Fund
|
1/23/2025 11:30:44 AM
|
Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by Donald Smith on behalf of Academy SD 20 Building Fund
|
1/23/2025 11:30:43 AM
|
Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by Becky Allan on behalf of Academy SD 20 Building Fund
|
1/23/2025 11:30:42 AM
|
Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
1/23/2025 11:30:41 AM
|
Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by Glenn Reese on behalf of EPC Stormwater Review
|
1/23/2025 11:30:40 AM
|
Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by Christina Prete on behalf of EPC Stormwater Review
|
1/23/2025 11:30:39 AM
|
Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by Mike McCarthy on behalf of EPC Health Department
|
1/23/2025 11:30:38 AM
|
Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by Catherine McGarvy on behalf of EPC Health Department
|
1/23/2025 11:30:37 AM
|
Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by HEAEH LandUse on behalf of EPC Health Department
|
1/23/2025 11:30:35 AM
|
Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by Justin Kilgore on behalf of PCD Project Manager
|
1/23/2025 11:30:34 AM
|
Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by Gilbert LaForce on behalf of PCD Engineering Division
|
1/23/2025 11:30:33 AM
|
Request for Review Comments email sent for Project Ford Dimensional Boundary Line Adjustment for review by Engineering Manager on behalf of PCD Engineering Division
|
1/21/2025 6:04:06 PM
|
Fees paid: 1/21/2025 (Receipt: 1010076)
|
1/21/2025 12:00:29 PM
|
Payment Request sent: 1/21/2025
|
1/21/2025 12:00:22 PM
|
File # Assigned: EXBL252
|
1/21/2025 11:59:24 AM
|
Submission Triaged
|
1/17/2025 12:08:56 PM
|
Submission received from Applicant
|
1/3/2025 10:37:53 AM
|
Submission request sent to Applicant
|
1/3/2025 10:22:43 AM
|
Submission request sent to Applicant
|
1/3/2025 10:22:20 AM
|
Project reopened for Review Comments
|
3/4/2023 12:00:00 AM
|
Project Closed
|
3/4/2023 12:00:00 AM
|
Project Expired one year after 03/04/2022 Submission Request 03/04/2023
|
3/4/2022 1:55:30 PM
|
Submission request sent to Applicant
|
3/3/2022 11:50:43 AM
|
Project Manager Assigned: Kylie Bagley
|
3/3/2022 11:50:42 AM
|
EA Assigned: EA2231
|
3/3/2022 11:50:42 AM
|
Project Created
|