Project Review Comments
- Project Name
- Ford Dimensional Boundary Line Adjustment
- Description
- Location
- Parcels
- 6214000032 6214000032 6214000097 6214000097
- Applicant
-
Eric Leffler
Eric Leffler ( ericleffler81@gmail.com )
(719) 493-8617 Eric Leffler ( ericleffler81@gmail.com )
(719) 493-8617 - EA Number
- EA2231
- File Number
- EXBL252
- Project Manager
- Lisa Elgin
- Status
- Active
- Created
- 3/3/2022 11:50:38 AM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
EPC Stormwater Review
2/11/2025 2:31:38 PM |
Review 1: EPC DPW Stormwater has no comments on this boundary line adjustment application. This project will not disturb more than 1 acre of soil. Reviewed by: Mikayla Hartford Stormwater Engineer I 719.339.5053 MikaylaHartford@elpasoco.com |
2/11/2025 2:31:38 PM | |
View |
EPC Health Department
2/7/2025 5:10:04 PM |
2/7/2025 5:10:04 PM | |
PCD Engineering Division
2/6/2025 5:29:54 PM |
Engineering Review Ver.1 Please see engineering review comments on the following documents Map Exhibit: A corrected surveyed map is needed to complete the engineering review. Subsequent submittal will be treated as a first review. No engineer comments could be provided on the V1 submission. Edward Schoenheit, Engineer E.P.C. Dept. of Public Works 2880 International Circle Colorado Springs, CO. 80910 Office: 719.520.6813 Cell: 719.502.9659 https://planningdevelopment.elpasoco.com/ |
2/6/2025 5:29:54 PM | |
Academy SD 20 Building Fund
2/3/2025 7:21:11 AM |
Academy District 20 is in receipt of File #EXBL252 for approval of the Ford Dimensional Boundary Line Adjustment. The District is requesting fees in lieu of land dedication per the existing County Code for all additional residential units within this development. The District is experiencing ongoing residential development. The District gained approximately 12,000 new residential units between 2018 and 2024 which included 5,278 Single Family, 1,156 Single Family Attached, and 5,576 Apartments as reported to the District by local developers. During that same timeframe, the District only experienced a total membership increase of 138 students. This information is updated annually in October. A drop in the birth rate plus the significant increase in the cost of housing has slowed student growth in the District. The District is able to serve each student who is a resident of District 20. If you need additional information, please contact me. Don Smith Planning Consultant |
2/3/2025 7:21:11 AM | |
Mountain View Electric Association, Inc.
1/27/2025 3:35:40 PM |
Please submit a development plan/site plan for review. | 1/27/2025 3:35:40 PM | |
PCD Project Manager
1/24/2025 3:18:24 PM |
Survey not included in the submittal. I spoke with the applicant who agreed to proceed with first review when the survey is completed and submitted. | 1/24/2025 3:18:24 PM |