9/6/2022 7:48:58 AM
|
Submission request sent to Applicant
|
9/6/2022 7:48:15 AM
|
Submission Triaged
|
9/2/2022 9:59:56 AM
|
Submission received from Applicant
|
9/2/2022 9:52:29 AM
|
Submission request sent to Applicant
|
9/2/2022 9:52:19 AM
|
Project reopened for Approval requests
|
9/2/2022 8:15:00 AM
|
Submission request sent to Applicant
|
11/20/2018 12:00:00 AM
|
Project Closed
|
11/19/2018 3:20:31 PM
|
Project Approved: 11/19/2018
|
9/20/2018 2:51:55 PM
|
Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
|
7/2/2018 4:32:44 PM
|
Submission Triaged
|
7/2/2018 3:47:55 PM
|
Submission received from Applicant
|
7/2/2018 2:23:11 PM
|
Submission request sent to Applicant
|
7/2/2018 12:47:36 PM
|
Submission Triaged
|
7/2/2018 9:20:28 AM
|
Submission received from Applicant
|
6/28/2018 3:29:13 PM
|
Submission request sent to Applicant
|
6/18/2018 9:05:32 PM
|
Request for Review Comments returned by EPC Health Department
|
6/11/2018 3:43:32 PM
|
Request for Review Comments returned by PCD Project Manager
|
6/11/2018 10:49:00 AM
|
Request for Review Comments returned by EPC County Attorney's Office
|
6/8/2018 9:14:15 AM
|
Submission Triaged
|
6/7/2018 2:26:05 PM
|
Submission received from Applicant
|
6/7/2018 2:19:51 PM
|
Submission request sent to Applicant
|
6/7/2018 2:19:33 PM
|
Submission Triaged
|
6/7/2018 12:13:52 PM
|
Submission received from Applicant
|
6/6/2018 12:14:53 PM
|
Submission request sent to Applicant
|
6/6/2018 11:49:21 AM
|
Request for Review Comments email sent for Project Helton Mini Storage for review by on behalf of EPC Health Department
|
6/6/2018 11:49:19 AM
|
Request for Review Comments email sent for Project Helton Mini Storage for review by Edi Anderson on behalf of EPC County Attorney's Office
|
6/6/2018 11:49:18 AM
|
Request for Review Comments email sent for Project Helton Mini Storage for review by Len Kendall on behalf of PCD Project Manager
|
6/6/2018 11:43:35 AM
|
Submission Triaged
|
6/4/2018 10:32:50 AM
|
Submission received from Applicant
|
6/4/2018 10:12:38 AM
|
Submission request sent to Applicant
|
5/29/2018 5:15:52 PM
|
Request for Review Comments returned by EPC Health Department
|
5/29/2018 8:07:29 AM
|
Request for Review Comments returned by PCD Project Manager
|
5/24/2018 8:05:25 AM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
5/23/2018 4:25:22 PM
|
Request for Review Comments email resent for Project Helton Mini Storage for review by Len Kendall on behalf of PCD Project Manager
|
5/23/2018 4:19:12 PM
|
Request for Review Comments returned by PCD Project Manager
|
5/22/2018 2:39:21 PM
|
Request for Review Comments returned by Colorado Springs Airport Advisory Commission
|
5/22/2018 8:22:47 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
5/18/2018 4:16:27 PM
|
Request for Review Comments email sent for Project Helton Mini Storage for review by UDS Admin Staff on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
5/17/2018 3:43:19 PM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
5/16/2018 1:16:56 PM
|
Request for Review Comments returned by PCD Engineering Division
|
5/10/2018 7:34:54 AM
|
Request for Review Comments returned by Fountain Ft. Carson SD 8
|
5/9/2018 11:47:34 AM
|
Submission Triaged
|
5/9/2018 10:57:51 AM
|
Request for Review Comments returned by EPC County Attorney's Office
|
5/9/2018 8:18:23 AM
|
Submission received from Applicant
|
5/9/2018 7:44:16 AM
|
Request for Review Comments email sent for Project Helton Mini Storage for review by on behalf of Security Fire Protection District
|
5/9/2018 7:44:15 AM
|
Request for Review Comments email sent for Project Helton Mini Storage for review by Thomas Wiersma on behalf of Ft. Carson, Directorate of Public Works, Master Planning
|
5/9/2018 7:44:14 AM
|
Request for Review Comments email sent for Project Helton Mini Storage for review by Scott Stevens on behalf of Fountain Ft. Carson SD 8
|
5/9/2018 7:44:13 AM
|
Request for Review Comments email sent for Project Helton Mini Storage for review by UDS Admin Staff on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
5/9/2018 7:44:12 AM
|
Request for Review Comments email sent for Project Helton Mini Storage for review by Carl Schueler on behalf of Colorado Springs Planning & Community Development
|
5/9/2018 7:44:11 AM
|
Request for Review Comments email sent for Project Helton Mini Storage for review by Kristine Andrews on behalf of Colorado Springs Airport Advisory Commission
|
5/9/2018 7:44:10 AM
|
Request for Review Comments email sent for Project Helton Mini Storage for review by RBD Enumerations & Floodplain on behalf of Pikes Peak Regional Building Department
|
5/9/2018 7:44:09 AM
|
Request for Review Comments email sent for Project Helton Mini Storage for review by Permits Manager Valerie Sword on behalf of Colorado Department of Transportation - Pueblo Office
|
5/9/2018 7:44:07 AM
|
Request for Review Comments email sent for Project Helton Mini Storage for review by on behalf of EPC Health Department
|
5/9/2018 7:44:06 AM
|
Request for Review Comments email sent for Project Helton Mini Storage for review by Edi Anderson on behalf of EPC County Attorney's Office
|
5/9/2018 7:44:05 AM
|
Request for Review Comments email sent for Project Helton Mini Storage for review by Len Kendall on behalf of PCD Project Manager
|
5/9/2018 7:44:04 AM
|
Request for Review Comments email sent for Project Helton Mini Storage for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
5/8/2018 1:43:11 PM
|
Fees paid: 5/8/2018 (Receipt: 1000651)
|
5/8/2018 1:04:34 PM
|
Submission request sent to Applicant
|
5/7/2018 11:22:00 AM
|
Payment Request sent: 5/7/2018
|
5/7/2018 11:21:52 AM
|
File # Assigned: PPR1819
|
5/7/2018 9:15:18 AM
|
Submission Triaged
|
5/7/2018 9:14:18 AM
|
Project Manager Assigned: Len Kendall
|
5/4/2018 10:17:55 AM
|
Submission received from Applicant
|
4/17/2018 7:59:14 AM
|
Submission request sent to Applicant
|
4/17/2018 7:58:05 AM
|
Submission Triaged
|
4/16/2018 12:36:45 PM
|
Submission received from Applicant
|
4/4/2018 5:32:39 PM
|
Submission request sent to Applicant
|
4/4/2018 5:24:02 PM
|
Project Manager Assigned: Raimere Fitzpatrick
|
4/4/2018 5:24:02 PM
|
EA Assigned: EA-16-123
|
4/4/2018 5:24:02 PM
|
Project Created
|