Project Review Comments
- Project Name
- Flying Horse North Clubhouse CDR
- Description
- Roadway and storm sewer Construction Drawings
- Location
- Old Stagecoach Road & Allen Ranch Road
- Parcels
- 6136000006 6136000006
- Applicant
- 
            HR Green Inc. 
                
 Blaine Perkins ( blaine.perkins@hrgreen.com )
 (719) 394-2430 Blaine Perkins ( blaine.perkins@hrgreen.com )
 (719) 394-2430
- File Number
- CDR259
- Project Manager
- Daniel Torres
- Status
- Active
- Created
- 6/23/2025 8:58:26 AM
View: Project Documents
| Agency | Comment | ||
|---|---|---|---|
| PCD Project Manager 10/21/2025 3:05:40 PM | Review comments on the CD's have been uploaded to EDARP. | 10/21/2025 3:05:40 PM | |
| View | EPC DPW Development Services - Engineering 10/21/2025 12:50:46 PM | CD_V1 | 10/21/2025 12:50:46 PM | 
| EPC DPW Development Services - Engineering 10/21/2025 12:07:13 PM | Engineering Review Ver.1 Please seen engineer comments on the following documents CD_V1 Note the GEC plans must be submitted with the CDs since those sheets are not included in the CD sheet set. Please submit those or add to the CD sheet set and update the sheet index. Edward Schoenheit, Engineer E.P.C. Dept. of Public Works 2880 International Circle Colorado Springs, CO. 80910 Office: 719.520.6813 Cell: 719.502.9659 edwardschoenheit@elpasoco.com https://publicworks.elpasoco.com/department-public-works/county-engineer/ | 10/21/2025 12:07:13 PM | |
| EPC DPW Stormwater 10/2/2025 1:43:40 PM | Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded document(s): - CDs.....(to be uploaded with Development Services comments) Reviewed by: Glenn Reese, P.E. Principal Engineer - Stormwater 719.675.2654 GlennReese@elpasoco.com | 10/2/2025 1:43:40 PM | 
 EDARP
                    EDARP