Project Details
Search |
All Active Projects
-
File Number
-
CDR259
-
Project Name
-
Flying Horse North Clubhouse CDR
-
Description
-
Roadway and storm sewer Construction Drawings
-
Location
-
Old Stagecoach Road & Allen Ranch Road
-
Parcels
-
6136000006
6136000006
-
Applicant
-
HR Green Inc.
Blaine Perkins ( blaine.perkins@hrgreen.com )
(719) 394-2430
Blaine Perkins ( blaine.perkins@hrgreen.com )
(719) 394-2430
-
File Prefix
-
CDR - Construction Drawing Review
-
Year
-
2025
-
Project Manager
-
Daniel Torres
-
Status
-
Active
-
Created
-
6/23/2025 8:58:26 AM
Review Documents (3)
Link
|
Document
|
Date
|
View
|
Financial Assurance Estimate (FAE) Form
|
9/16/2025 8:46:37 AM
|
View
|
Construction Drawings (Plans/Profiles)
|
9/16/2025 8:46:36 AM
|
View
|
Drainage Report - Final
|
9/16/2025 8:46:38 AM
|
Events (15)
Date
|
Comment
|
9/30/2025 7:13:44 AM
|
Request for Review Comments email sent for Project Flying Horse North Clubhouse CDR for review by Zachary Jannusch on behalf of EPC DPW Stormwater
|
9/30/2025 7:13:43 AM
|
Request for Review Comments email sent for Project Flying Horse North Clubhouse CDR for review by Mikayla Hartford on behalf of EPC DPW Stormwater
|
9/30/2025 7:13:41 AM
|
Request for Review Comments email sent for Project Flying Horse North Clubhouse CDR for review by Glenn Reese on behalf of EPC DPW Stormwater
|
9/30/2025 7:13:40 AM
|
Request for Review Comments email sent for Project Flying Horse North Clubhouse CDR for review by Christina Prete on behalf of EPC DPW Stormwater
|
9/30/2025 7:13:39 AM
|
Request for Review Comments email sent for Project Flying Horse North Clubhouse CDR for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
|
9/30/2025 7:13:38 AM
|
Request for Review Comments email sent for Project Flying Horse North Clubhouse CDR for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
9/30/2025 7:13:37 AM
|
Request for Review Comments email sent for Project Flying Horse North Clubhouse CDR for review by Justin Kilgore on behalf of PCD Project Manager
|
9/26/2025 9:20:43 AM
|
Fees paid: 9/26/2025 (Receipt: 1011120)
|
9/16/2025 9:18:20 AM
|
Payment Request sent: 9/16/2025
|
9/16/2025 9:18:20 AM
|
File # Assigned: CDR259
|
9/16/2025 9:18:13 AM
|
Submission Triaged
|
9/16/2025 8:46:49 AM
|
Submission received from Applicant
|
6/23/2025 1:16:26 PM
|
Submission request sent to Applicant
|
6/23/2025 8:58:29 AM
|
Project Manager Assigned: Daniel Torres
|
6/23/2025 8:58:29 AM
|
Project Created
|