Project Review Comments

Back to List


File Number
SF2519
Project Name
Crystal Park Site S-179 Plat
Description
PLAT NO. 15600. -- Address: 250 Summit Rd. Submittal of administrative final plat for Crystal Park Site S-179 (RR). Situated at Palmer Trail and Summit Ridge Road.
Parcels
7418000230 7418000230
Applicant
M.V.E., Inc.
David Gorman ( daveg@mvecivil.com )
(719) 635-5736
David Gorman ( daveg@mvecivil.com )
(719) 635-5736
File Number
SF2519
Project Manager
Miranda Benson
Status
Closed
Created
6/10/2025 8:37:43 AM

View: Project Documents | Public Comments



Review Comments (6)

Link Agency Review # Comment
PCD Project Manager
10/22/2025 10:29:42 AM
3 V3_ corrected plat drawing was received. No planning comments. Project remains ready for Clerk & Recorder, pending revised mylar drop-off.

Thank you,
Miranda Benson
mirandabenson2@elpasoco.com
10/22/2025 10:29:42 AM
PCD Project Manager
10/17/2025 10:52:47 AM
2 V2_Planning review complete. All comments were addressed. Plat is ready for recording.

Appointment was made for 10/17/2025 9:00 AM to receive mylar and pay fees.

Plat is waiting for PCD Director signature. PCD will then take the plat to the Clerk and Recorder for filing. When the plat is recorded, a copy will be uploaded to the EDARP file.

Thank you,
Miranda Benson
mirandabenson2@elpasoco.com
10/17/2025 10:52:47 AM
Pikes Peak Regional Building Department
10/16/2025 3:54:05 PM
2 no further comments 10/16/2025 3:54:05 PM
View PCD Project Manager
7/3/2025 2:07:09 PM
1 V1_Plat Drawing_COMMENTS 7/3/2025 2:07:09 PM
PCD Project Manager
7/3/2025 2:05:48 PM
1 V1_ Planning review complete.
Please see comments on Final Plat Drawing.

Thank you,
Miranda Benson
mirandabenson2@elpasoco.com
7/3/2025 2:05:48 PM
Pikes Peak Regional Building Department
6/25/2025 4:06:25 PM
1 Enumerations has the following comments:

1. Where is the access to the parcel going to be? This parcel looks like it could access from Derby Rock Loop, Palmer Trail, or Summit Rd. The location of the driveway access will determine the address. Enumerations had previously assigned 280 Palmer Trail as the addresses, but, we need to confirm if that is the correct access. If not, submit a copy of this plat which shows the location of the access so that an appropriate address can be assigned.
2. Enumerations will review the mylar prior to recording as per usual procedure. An Enumerations fee of $10 will be due at the time of mylar review.

Brent Johnson
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2888 E: brent@pprbd.org W: pprbd.org
6/25/2025 4:06:25 PM