10/28/2025 8:52:53 AM
|
Project Closed
|
|
10/28/2025 8:52:53 AM
|
Project Approved: 10/28/2025
|
|
10/22/2025 10:30:07 AM
|
Project Ready for Approval requests. Review Comment period is complete.
|
|
10/22/2025 10:29:47 AM
|
Request for Review Comments returned by PCD Project Manager
|
|
10/21/2025 4:10:04 PM
|
Project reopened for Review Comments
|
|
10/21/2025 3:37:24 PM
|
Request for Review Comments email sent for Project Crystal Park Site S-179 Plat for review by Justin Kilgore on behalf of PCD Project Manager
|
|
10/21/2025 3:36:54 PM
|
Submission Triaged
|
|
10/21/2025 1:44:04 PM
|
Submission received from Applicant
|
|
10/20/2025 2:37:00 PM
|
Submission request sent to Applicant
|
|
10/17/2025 10:53:26 AM
|
Project Ready for Approval requests. Review Comment period is complete.
|
|
10/17/2025 10:52:52 AM
|
Request for Review Comments returned by PCD Project Manager
|
|
10/16/2025 3:54:14 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
|
10/15/2025 12:07:52 PM
|
Request for Review Comments email sent for Project Crystal Park Site S-179 Plat for review by on behalf of Pikes Peak Regional Building Department
|
|
10/15/2025 12:07:50 PM
|
Request for Review Comments email sent for Project Crystal Park Site S-179 Plat for review by Justin Kilgore on behalf of PCD Project Manager
|
|
10/15/2025 12:03:27 PM
|
Submission Triaged
|
|
10/15/2025 11:56:15 AM
|
Submission received from Applicant
|
|
10/15/2025 11:28:49 AM
|
Submission request sent to Applicant
|
|
7/3/2025 2:08:09 PM
|
Submission request sent to Applicant
|
|
7/3/2025 2:07:16 PM
|
Request for Review Comments returned by PCD Project Manager
|
|
7/3/2025 2:06:41 PM
|
Request for Review Comments email resent for Project Crystal Park Site S-179 Plat for review by Justin Kilgore on behalf of PCD Project Manager
|
|
7/3/2025 2:05:59 PM
|
Request for Review Comments returned by PCD Project Manager
|
|
7/1/2025 4:10:25 PM
|
Request for Review Comments email resent for Project Crystal Park Site S-179 Plat for review by Justin Kilgore on behalf of PCD Project Manager
|
|
7/1/2025 4:08:45 PM
|
Request for Review Comments returned by PCD Project Manager
|
|
6/25/2025 4:06:36 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
|
6/18/2025 1:25:40 PM
|
Request for Review Comments email sent for Project Crystal Park Site S-179 Plat for review by on behalf of Pikes Peak Regional Building Department
|
|
6/18/2025 1:25:38 PM
|
Request for Review Comments email sent for Project Crystal Park Site S-179 Plat for review by Justin Kilgore on behalf of PCD Project Manager
|
|
6/17/2025 9:19:10 AM
|
Fees paid: 6/17/2025 (Receipt: 1010671)
|
|
6/12/2025 12:16:04 PM
|
Payment Request sent: 6/12/2025
|
|
6/12/2025 12:16:04 PM
|
File # Assigned: SF2519
|
|
6/12/2025 12:15:58 PM
|
Submission Triaged
|
|
6/11/2025 4:52:18 PM
|
Submission received from Applicant
|
|
6/11/2025 12:52:57 PM
|
Submission request sent to Applicant
|
|
6/11/2025 12:52:46 PM
|
Submission Triaged
|
|
6/10/2025 4:15:42 PM
|
Submission received from Applicant
|
|
6/10/2025 8:43:31 AM
|
Submission request sent to Applicant
|
|
6/10/2025 8:37:46 AM
|
Project Manager Assigned: Miranda Benson
|
|
6/10/2025 8:37:46 AM
|
Project Created
|