Project Review Comments
- Project Name
- 10850 E Woodmen Road D49 Addition PPR
- Description
- D49 is adding covered parking and storage buildings to their existing site.
- Location
- Parcels
- 5301002006 5301002006
- Applicant
-
DLR Group
David Riggs ( driggs@DLRGROUP.com )
(719) 313-5730 David Riggs ( driggs@DLRGROUP.com )
(719) 313-5730 - File Number
- PPR253
- Project Manager
- Lacey Dean
- Status
- Active
- Created
- 1/22/2025 7:36:00 AM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
View |
PCD Engineering Division
2/19/2025 5:10:29 PM |
2/19/2025 5:10:29 PM | |
PCD Engineering Division
2/19/2025 5:09:54 PM |
Engineering Review Ver.1 See comments on the following documents FDR_V1 Note EPC Road Impact fees for the two new buildings is being reviewed and comments are forthcoming. Edward Schoenheit, Engineer E.P.C. Dept. of Public Works 2880 International Circle Colorado Springs, CO. 80910 Office: 719.520.6813 Cell: 719.502.9659 https://planningdevelopment.elpasoco.com/ |
2/19/2025 5:09:54 PM | |
View |
PCD Engineering Division
2/19/2025 5:10:51 PM |
FDR_V1 | 2/19/2025 5:10:51 PM |
View |
PCD Project Manager
2/18/2025 5:11:44 PM |
V1_Site Development Plan_comments | 2/18/2025 5:11:44 PM |
View |
PCD Project Manager
2/18/2025 5:11:24 PM |
V1_Landscape Plan drawings_comments | 2/18/2025 5:11:24 PM |
View |
PCD Project Manager
2/18/2025 5:10:42 PM |
V1_Letter of Intent_comments | 2/18/2025 5:10:42 PM |
PCD Project Manager
2/18/2025 5:14:15 PM |
Review 1: EPC Planning Division has comments in green text boxes on the following documents: - Letter of Intent - Landscape Plan Drawings - Site Development Plan Reviewed by: Lacey Dean, Associate Planner laceydean2@elpasoco.com |
2/18/2025 5:14:15 PM | |
View |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
2/18/2025 10:07:11 AM |
Good morning Lacey, CSU has three (3) outstanding comments to be addressed: Action Item: Gas meter locations on plan view and building elevations must be shown and labeled. Action Item: Add note " Gas meters must be a minimum of 3-feet from doors, operable windows, or any vents or openings in walls." Action Item: Add note “CSU Field Engineer to determine final gas meter, transformer and service line locations. Contact Field Engineering at 719-668-4985 (Gas) with any questions.” Best, Matthew Alcuran, MPA| Engineering Support Specialist Sr. Colorado Springs Utilities | Utilities Development Services 1521 South Hancock Expressway| MC 1812 | Colorado Springs, CO 80903 O: 719-668-8261 |malcuran@csu.org |
2/18/2025 10:07:11 AM |
EPC Stormwater Review
2/18/2025 1:24:42 PM |
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded document(s) (to be uploaded by the Project Manager): - Drainage Analysis Please provide the following document(s) upon resubmittal (the planner will need to send an upload request): - Maintenance Agreement (see comments on the drainage report) Reviewed by: Mikayla Hartford Stormwater Engineer I 719.339.5053 MikaylaHartford@elpasoco.com |
2/18/2025 1:24:42 PM | |
View |
EPC Health Department
2/14/2025 4:40:42 PM |
2/14/2025 4:40:42 PM | |
County Attorney - Development Review
2/13/2025 9:21:52 AM |
No comments at this time. | 2/13/2025 9:21:52 AM | |
View |
Falcon Fire Protection District
2/10/2025 1:54:31 PM |
2/10/2025 1:54:31 PM | |
View |
EPC Environmental Services
2/7/2025 9:34:05 AM |
2/7/2025 9:34:05 AM | |
Falcon School District 49
2/7/2025 9:17:00 AM |
District 49 is in support of the addition of covered parking and storage buildings. | 2/7/2025 9:17:00 AM | |
Pikes Peak Regional Building Department
2/5/2025 2:54:55 PM |
New commercial detached structure are required to have a separate structure. This was not the case long ago when the other structure were built. The covered parking address is 10868 E Woodmen Road. The new barn address is 10878 E Woodmen Road. No further comments. Amy Vanderbeek Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2930 E: Amy@pprbd.org |
2/5/2025 2:54:55 PM | |
EPC Parks Department
2/3/2025 3:51:52 PM |
El Paso County Parks and Community Services. The 2022 El Paso County Parks Master Plan shows no impacts to existing or proposed parks, trails, or open space. As such, no trail easements or park land dedications are necessary. As this is a site development plan for an existing school facility, no park fees will be assessed. Thank you! | 2/3/2025 3:51:52 PM |