Project Details

Search


File Number
PPR253
Project Name
10850 E Woodmen Road D49 Addition PPR
Description
D49 is adding covered parking and storage buildings to their existing site.
Parcels
5301002006 5301002006
Applicant
DLR Group
David Riggs ( driggs@DLRGROUP.com )
(719) 313-5730
David Riggs ( driggs@DLRGROUP.com )
(719) 313-5730
File Prefix
PPR - Plot Plan Review
Year
2025
Project Manager
Lacey Dean
Status
Closed
Created
1/22/2025 7:36:00 AM

View: Review Comments


Approved Documents (2)

Link Document
View Site Development Plan
View Drainage Letter


Review Documents (13)

Link Document Date
View Application/Petition Form 1/30/2025 9:55:43 AM
View Landscape Plan drawings 4/9/2025 10:32:25 AM
View Legal Description (MS WORD Version required) 1/30/2025 9:55:45 AM
View Letter of Intent 3/18/2025 12:50:11 PM
View Site Development Plan 3/18/2025 12:50:11 PM
View Floor Plans (24" x 36") 1/30/2025 9:55:44 AM
View Elevation Plans 3/18/2025 12:50:09 PM
View Lighting Plan 1/30/2025 9:55:47 AM
View Soils Report Pursuant to Appendix C of the ECM 1/30/2025 9:55:48 AM
View Approved Water Plan 3/18/2025 12:50:12 PM
View Light fixture product data sheets 1/30/2025 9:55:48 AM
View Non-standard MS4 permit 1/30/2025 9:55:49 AM
View Response Letter to comments 4/9/2025 10:32:26 AM



Events (91)

Date Comment
5/5/2025 3:15:28 PM Project Closed
5/5/2025 3:15:28 PM Project Approved: 5/5/2025
5/5/2025 3:02:41 PM Project Ready for Approval requests. Review Comment period is complete.
5/1/2025 4:11:36 PM Submission request canceled
4/28/2025 5:05:06 PM Submission request sent to Applicant
4/16/2025 4:33:17 PM Request for Review Comments returned by PCD Project Manager
4/9/2025 11:11:18 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Justin Kilgore on behalf of PCD Project Manager
4/9/2025 10:44:31 AM Submission Triaged
4/9/2025 10:33:06 AM Submission received from Applicant
4/8/2025 10:33:27 AM Submission request sent to Applicant
4/8/2025 10:30:27 AM Request for Review Comments returned by PCD Project Manager
4/8/2025 10:29:53 AM Request for Review Comments email resent for Project 10850 E Woodmen Road D49 Addition PPR for review by Justin Kilgore on behalf of PCD Project Manager
4/8/2025 10:29:04 AM Request for Review Comments returned by PCD Project Manager
4/7/2025 3:04:23 PM Request for Review Comments returned by PCD Engineering Division
4/7/2025 9:10:57 AM Request for Review Comments returned by EPC Stormwater Review
4/2/2025 2:27:32 PM Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
3/24/2025 10:54:48 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by LBS Review on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
3/24/2025 10:54:47 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
3/24/2025 10:54:46 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Mikayla Hartford on behalf of EPC Stormwater Review
3/24/2025 10:54:45 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Glenn Reese on behalf of EPC Stormwater Review
3/24/2025 10:54:44 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Christina Prete on behalf of EPC Stormwater Review
3/24/2025 10:54:42 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Justin Kilgore on behalf of PCD Project Manager
3/24/2025 10:54:41 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Gilbert LaForce on behalf of PCD Engineering Division
3/24/2025 10:54:39 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Engineering Manager on behalf of PCD Engineering Division
3/24/2025 10:50:01 AM Submission Triaged
3/18/2025 12:51:59 PM Submission received from Applicant
3/5/2025 8:05:52 PM Submission request sent to Applicant
2/27/2025 4:04:22 PM Request for Review Comments returned by Upper Black Squirrel Creek GWMD
2/20/2025 12:58:02 PM Request for Review Comments returned by Mountain View Electric Association, Inc.
2/19/2025 5:17:27 PM Submission request sent to Applicant
2/19/2025 5:12:03 PM Request for Review Comments returned by PCD Engineering Division
2/18/2025 5:14:31 PM Request for Review Comments returned by PCD Project Manager
2/18/2025 5:13:56 PM Request for Review Comments email resent for Project 10850 E Woodmen Road D49 Addition PPR for review by Justin Kilgore on behalf of PCD Project Manager
2/18/2025 5:11:51 PM Request for Review Comments returned by PCD Project Manager
2/18/2025 2:18:54 PM Request for Review Comments returned by EPC Stormwater Review
2/18/2025 10:07:20 AM Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
2/14/2025 4:40:54 PM Request for Review Comments returned by EPC Health Department
2/13/2025 9:22:03 AM Request for Review Comments returned by County Attorney - Development Review
2/10/2025 1:55:04 PM Request for Review Comments returned by Falcon Fire Protection District
2/7/2025 9:35:54 AM Request for Review Comments returned by EPC Environmental Services
2/7/2025 9:17:12 AM Request for Review Comments returned by Falcon School District 49
2/5/2025 2:55:01 PM Request for Review Comments returned by Pikes Peak Regional Building Department
2/3/2025 3:51:59 PM Request for Review Comments returned by EPC Parks Department
2/3/2025 9:13:02 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by General Email on behalf of Mountain View Electric Association, Inc.
2/3/2025 9:13:01 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Evelyn galanephillips on behalf of Falcon School District 49
2/3/2025 9:12:59 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Trent Harwig on behalf of Falcon Fire Protection District
2/3/2025 9:12:58 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Curtis Kauffman on behalf of Falcon Fire Protection District
2/3/2025 9:12:57 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Harry Thomas on behalf of El Paso County Conservation Dist
2/3/2025 9:12:56 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Oliver Watkins on behalf of El Paso County Conservation Dist
2/3/2025 9:12:55 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Katie Miller on behalf of El Paso County Conservation Dist
2/3/2025 9:12:54 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Erica Carter on behalf of El Paso County Conservation Dist
2/3/2025 9:12:53 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by on behalf of El Paso County Conservation Dist
2/3/2025 9:12:52 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Mariah Hudson on behalf of El Paso County Conservation Dist
2/3/2025 9:12:51 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Cassie Olgren on behalf of El Paso County Conservation Dist
2/3/2025 9:12:50 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Billy Richard on behalf of El Paso County Conservation Dist
2/3/2025 9:12:49 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by LBS Review on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
2/3/2025 9:12:48 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
2/3/2025 9:12:46 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Santiago Tijerina on behalf of Black Hills Energy-Aquila
2/3/2025 9:12:45 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Marcus Henderson on behalf of Black Hills Energy-Aquila
2/3/2025 9:12:44 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Bob Swatek on behalf of Black Hills Energy-Aquila
2/3/2025 9:12:43 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Adam Magoon on behalf of Black Hills Energy-Aquila
2/3/2025 9:12:42 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
2/3/2025 9:12:41 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by on behalf of Pikes Peak Regional Building Department
2/3/2025 9:12:40 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Mikayla Hartford on behalf of EPC Stormwater Review
2/3/2025 9:12:39 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Glenn Reese on behalf of EPC Stormwater Review
2/3/2025 9:12:38 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Christina Prete on behalf of EPC Stormwater Review
2/3/2025 9:12:36 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Jeff Kramer on behalf of EPC Sheriff's Department
2/3/2025 9:12:35 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Christopher Gonzalez on behalf of EPC Sheriff's Department
2/3/2025 9:12:34 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Andrew Prehm on behalf of EPC Sheriff's Department
2/3/2025 9:12:33 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by on behalf of EPC Public Works, County Engineer
2/3/2025 9:12:32 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by on behalf of EPC Public Works, County Engineer
2/3/2025 9:12:31 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by on behalf of EPC Parks Department
2/3/2025 9:12:30 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Mike McCarthy on behalf of EPC Health Department
2/3/2025 9:12:29 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Catherine McGarvy on behalf of EPC Health Department
2/3/2025 9:12:28 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by HEAEH LandUse on behalf of EPC Health Department
2/3/2025 9:12:26 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Kathy Andrew on behalf of EPC Environmental Services
2/3/2025 9:12:25 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Lori Seago on behalf of County Attorney - Development Review
2/3/2025 9:12:24 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Erika Keech on behalf of County Attorney - Development Review
2/3/2025 9:12:23 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by April Willie on behalf of County Attorney - Development Review
2/3/2025 9:12:21 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Justin Kilgore on behalf of PCD Project Manager
2/3/2025 9:12:20 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Gilbert LaForce on behalf of PCD Engineering Division
2/3/2025 9:12:19 AM Request for Review Comments email sent for Project 10850 E Woodmen Road D49 Addition PPR for review by Engineering Manager on behalf of PCD Engineering Division
1/30/2025 4:40:04 PM Project Manager Assigned: Lacey Dean
1/30/2025 4:37:51 PM Project Manager Assigned: Ryan Howser
1/30/2025 12:53:16 PM Fees paid: 1/30/2025 (Receipt: 1010110)
1/30/2025 10:15:57 AM Payment Request sent: 1/30/2025
1/30/2025 10:15:57 AM File # Assigned: PPR253
1/30/2025 10:15:56 AM Submission Triaged
1/30/2025 9:56:58 AM Submission received from Applicant
1/22/2025 7:38:09 AM Submission request sent to Applicant
1/22/2025 7:36:05 AM Project Created