Project Review Comments
- Project Name
- Owl Marketplace - QAS Valvoline Instant Oil Change
- Description
- The proposed QAS (Valvoline) Instant Oil Change is anticipated to be approximately 0.894 acres and the building will have a 2,673-SF net area (Footprint 1,339-SF, 1,334-SF Lower level) and will provide two services bays for oil change and service, a small customer waiting area, a restroom, an office, and ancillary spaces. Valvoline would provide 9 parking stalls, including one (1) ADA stall. There is no off-site work anticipated, with the potential exception of utility connections.
- Location
- Parcels
- 5301001015 5301001015
- Applicant
-
Greenbergfarrow
Danielle Benedict ( dbenedict@greenbergfarrow.com )
(224) 289-6607 Danielle Benedict ( dbenedict@greenbergfarrow.com )
(224) 289-6607 - EA Number
- EA24118
- File Number
- PPR2513
- Project Manager
- Lacey Dean
- Status
- Active
- Created
- 10/30/2024 5:35:16 PM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
View |
PCD Engineering Division
3/25/2025 6:31:18 PM |
FAE_V1 | 3/25/2025 6:31:18 PM |
View |
PCD Engineering Division
3/25/2025 6:30:53 PM |
GEC Plan_V1 | 3/25/2025 6:30:53 PM |
View |
PCD Engineering Division
3/25/2025 6:30:33 PM |
FDR_V1 Comment Summary | 3/25/2025 6:30:33 PM |
View |
PCD Engineering Division
3/25/2025 6:30:16 PM |
FDR_V1 | 3/25/2025 6:30:16 PM |
View |
PCD Engineering Division
3/25/2025 6:29:55 PM |
TIS_V1 | 3/25/2025 6:29:55 PM |
View |
PCD Project Manager
3/25/2025 5:19:51 PM |
V1_Letter of Intent_comments | 3/25/2025 5:19:51 PM |
View |
PCD Project Manager
3/25/2025 5:18:50 PM |
V1_Site Development Plan_comments | 3/25/2025 5:18:50 PM |
View |
PCD Project Manager
3/25/2025 5:05:49 PM |
V1_Landscape Plan Drawings_comments | 3/25/2025 5:05:49 PM |
View |
EPC Stormwater Review
3/25/2025 5:04:42 PM |
PCM Applicability Form | 3/25/2025 5:04:42 PM |
View |
EPC Stormwater Review
3/25/2025 5:04:26 PM |
GEC Checklist | 3/25/2025 5:04:26 PM |
View |
EPC Stormwater Review
3/25/2025 5:04:11 PM |
GEC Plan | 3/25/2025 5:04:11 PM |
View |
EPC Stormwater Review
3/25/2025 5:03:55 PM |
ESQCP | 3/25/2025 5:03:55 PM |
PCD Project Manager
3/25/2025 5:03:48 PM |
Review 1: EPC Planning Division has comments in green text boxes on the following documents. - Landscape Plan Drawings - Site Development Plan Reviewed by: Lacey Dean, Associate Planner laceydean2@elpasoco.com |
3/25/2025 5:03:48 PM | |
PCD Engineering Division
3/25/2025 6:36:12 PM |
Engineering Review Ver.1 Please see engineering review comments on the following documents LOI_V1 TIS_V1 SDP_V1 FAE_V1 ESQCP_V1 GEC Plan_V1 FDR_V1 Include utility (gas, water, sewage, power) design plan sheets with signature endorsements from all service providers on next submittal. Road Impact fees are due at time of building permit. See comments in LOI A PRECON meeting is required prior to issuance of Notice to Proceed. Site Development Plan cannot be approved until the Final Plat is recorded. An access permit will be required prior to NTP. This can be submitted online through EDARP. Thank you Edward Schoenheit, Engineer E.P.C. Dept. of Public Works 2880 International Circle Colorado Springs, CO. 80910 Office: 719.520.6813 Cell: 719.502.9659 https://planningdevelopment.elpasoco.com/ |
3/25/2025 6:36:12 PM | |
EPC Stormwater Review
3/25/2025 5:02:37 PM |
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded document(s): - Drainage Report...(to be uploaded with Development Services comments) - ESQCP - FAE.......................(to be uploaded with Development Services comments) - GEC Plan - GEC Checklist - PCM Applicability Form - SWMP --- a set of plans was erroneously uploaded to this slot, so there was no SWMP for us to review. Reviewed by: Glenn Reese, P.E. Principal Engineer - Stormwater 719.675.2654 GlennReese@elpasoco.com |
3/25/2025 5:02:37 PM | |
View |
Mountain View Electric Association, Inc.
3/24/2025 1:54:14 PM |
See attached comments | 3/24/2025 1:54:14 PM |
Falcon School District 49
3/24/2025 7:22:14 AM |
District 49 does not have any comments at this time but respectfully reserves the right to comment on any future submittals. | 3/24/2025 7:22:14 AM | |
Colorado Springs Public Works
3/20/2025 9:48:59 AM |
EDRD has no comments on this item. Reviewed by Hao Vo, P.E. hao.vo@coloradosprings.gov |
3/20/2025 9:48:59 AM | |
Woodmen Hills Metro
3/14/2025 10:23:28 AM |
You need a water and wastewater commitment letter from Woodmen Hills Metropolitan District and a water resource letter (if appliable). | 3/14/2025 10:23:28 AM | |
View |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
3/13/2025 8:30:57 AM |
Good morning Lacey. CSU has three (3) comments to be addressed for PPR2513: Action Item: Gas and electric meter locations on plan view and building elevations must be shown and labeled. Action Item: Add note " Gas meters must be a minimum of 3-feet from doors, operable windows, or any vents or openings in walls." Action Item: Add note “CSU Field Engineer to determine final gas meter and service line locations. Contact Field Engineering at 719-668-4985 (Gas) with any questions.” Best, Matthew Alcuran, MPA| Engineering Support Specialist Sr. Colorado Springs Utilities | Utilities Development Services 1521 South Hancock Expressway| MC 1812 | Colorado Springs, CO 80903 O: 719-668-8261 |malcuran@csu.org |
3/13/2025 8:30:57 AM |
View |
EPC Environmental Services
3/12/2025 10:42:00 AM |
3/12/2025 10:42:00 AM | |
Colorado Springs Public Works
3/11/2025 9:08:03 AM |
Traffic Engineering has no comments on this item. Zaker Alazzeh, P.E. Traffic Engineering Manager/Deputy City Traffic Engineer City of Colorado Springs (719) 385-5468 Zaker.Alazzeh@coloradosprings.gov |
3/11/2025 9:08:03 AM | |
EPC Parks Department
3/11/2025 9:02:43 AM |
El Paso County Parks and Community Services. The 2022 El Paso County Parks Master Plan shows no impacts to existing or proposed parks, trails, or open space. As such, no trail easements or park land dedications are necessary. As this is a commercial site plan development application, no regional park fees will be assessed, however an update to the EPC Land Development Code over the next year and half may or may not change this fee requirement. Thank you! | 3/11/2025 9:02:43 AM |