Project Name
CDR Fishers Canyon Channel
Description
Fischers Canon Creek and across from Walmart-Sams Club, north of Pikes Peak State College. Potential for trails and open space along creek
Location
Parcels
6504300049 6504300049
Applicant
Kimley-Horn Associates
Jim Houk ( jim.houk@kimley-horn.com )
(719) 284-7280
Jim Houk ( jim.houk@kimley-horn.com )
(719) 284-7280
EA Number
EA2343
File Number
CDR246
Project Manager
Daniel Torres
Status
Active
Created
5/15/2024 1:31:18 PM

View: Project Documents



Review Comments (18)

Link Agency Comment
View Fountain
11/5/2024 10:41:20 AM
Please refer to attached City of Fountain comments. 11/5/2024 10:41:20 AM
EPC Stormwater Review
10/31/2024 1:48:03 PM
Review 2: EPC DPW Stormwater review completed by Development Services Engineers for this submittal.

Reviewed by:
Christina Prete, P.E.
Stormwater Manager
ChristinaPrete@elpasoco.com
10/31/2024 1:48:03 PM
PCD Project Manager
10/30/2024 9:58:55 PM
Review 2 comments on the following documents will be uploaded:
-Construction Drawings
-Channel Design Report
-ESQCP

See attached final submittal checklist

Comments have been provided based on the information provided in the submitted documents. Additional comments should be expected as more information/analysis is provided in the design report, construction drawings, and other project documents.

reviewed by:
Jeff Rice
Jeffrice@elpasoco.com
&
Daniel Torres
danieltorres@elpasoco.com
10/30/2024 9:58:55 PM
View PCD Engineering Division
10/30/2024 9:56:26 PM
ESQCP comments 10/30/2024 9:56:26 PM
View PCD Engineering Division
10/30/2024 9:55:14 PM
Construction Drawings comments 10/30/2024 9:55:14 PM
View PCD Engineering Division
10/30/2024 9:54:14 PM
Channel Design Report comments 10/30/2024 9:54:14 PM
View PCD Engineering Division
10/30/2024 9:53:34 PM
Review 2 comments on the following documents will be uploaded:
-Construction Drawings
-Channel Design Report
-ESQCP

See attached final submittal checklist

Comments have been provided based on the information provided in the submitted documents. Additional comments should be expected as more information/analysis is provided in the design report, construction drawings, and other project documents.

reviewed by:
Jeff Rice
Jeffrice@elpasoco.com
&
Daniel Torres
danieltorres@elpasoco.com
10/30/2024 9:53:34 PM
Colorado Department of Transportation - Pueblo Office
10/24/2024 7:53:28 AM
CDOTs previous comments have been addressed. No further comments. 10/24/2024 7:53:28 AM
RBD Floodplain
10/16/2024 8:01:39 AM
This project needs either a no-rise report or an approved CLOMR from FEMA.
Either of these documents will need to be submitted as part of the local floodplain permit application to be approved prior to earth work.
10/16/2024 8:01:39 AM
View PCD Engineering Division
7/2/2024 10:52:37 PM
Channel Design Report comments 7/2/2024 10:52:37 PM
View PCD Engineering Division
7/3/2024 9:59:09 AM
Construction Drawing Comments 7/3/2024 9:59:09 AM
PCD Engineering Division
7/2/2024 9:52:28 PM
Review 1 comments on the following documents will be uploaded:
-Construction Drawings
-Channel Design Report

Comments have been provided based on the information provided in the submitted documents. Additional comments should be expected as more information/analysis is provided in the design report, construction drawings, and other project documents.

reviewed by:
Daniel Torres
danieltorres@elpasoco.com
&
Jeff Rice
7/2/2024 9:52:28 PM
Colorado Department of Transportation - Pueblo Office
7/2/2024 4:31:41 PM
• As the design progresses, suggest including additional notes or detail to identify how channel runoff is treated before discharging from the site.
• The check dams are shown in the initial condition, but there is not a note indicating when they are removed. Verify they are removed after the grouted boulder structure is installed.
7/2/2024 4:31:41 PM
EPC Stormwater Review
7/2/2024 9:00:28 AM
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- CDs.....(to be uploaded with Development Services comments)

Per the information that the applicant uploaded with Submittal #1, all ESQCP related documents were not uploaded with Submittal #1 but will be uploaded with Submittal #2. So I'm just documenting that I will review those documents when they are submitted with Submittal #2.

Reviewed by:
Glenn Reese, P.E.
Stormwater Engineer III
GlennReese@elpasoco.com
7/2/2024 9:00:28 AM
Stratmoor HIlls Fire Department
6/18/2024 2:12:14 PM
The Stratmoor Hills Fire Department has no objections to this plan as described.
Mark Stanwood for SHVFD
6/18/2024 2:12:14 PM
PCD Project Manager
6/14/2024 11:48:48 AM
Construction documents for review - no comment. 6/14/2024 11:48:48 AM
Mountain View Electric Association, Inc.
6/11/2024 2:28:15 PM
This property is not within MVEA territory 6/11/2024 2:28:15 PM
RBD Floodplain
6/11/2024 12:37:22 PM
Floodplain documentation to be provided in the 3rd submittal 6/11/2024 12:37:22 PM