Project Details

Search | All Active Projects


File Number
CDR246
Project Name
CDR Fishers Canyon Channel
Description
Fishers Canyon channel improvements across from Walmart-Sams Club, north of Pikes Peak State College. Potential for trails and open space along creek.
Parcels
6504300049 6504300049
Applicant
Kimley-Horn Associates
Jim Houk ( jim.houk@kimley-horn.com )
(719) 284-7280
Jim Houk ( jim.houk@kimley-horn.com )
(719) 284-7280
EA Number
EA2343
File Prefix
CDR - Construction Drawing Review
Year
2024
Project Manager
Daniel Torres
Status
Active
Created
5/15/2024 1:31:18 PM

View: Review Comments



Additional Documents (1)

Link Document Comment
View MS4 Overlap Letter - SIGNED


Review Documents (16)

Link Document Date
View Grading & Erosion Control checklist 5/31/2025 9:34:34 PM
View Letter of Intent 7/11/2025 2:21:24 PM
View Vicinity/Location Map 6/4/2024 10:54:24 AM
View Erosion and Stormwater Quality Control Permit (ESQCP) 7/11/2025 2:21:24 PM
View Financial Assurance Forms 7/11/2025 2:21:23 PM
View Floodplain Development Permit 2/24/2025 10:40:14 PM
View PBMP Applicability Form 5/31/2025 9:34:35 PM
View SWMP checklist 5/31/2025 9:34:35 PM
View US Army Corps of Engineer's Permit 2/24/2025 10:40:15 PM
View Construction Drawings (Plans/Profiles) 7/14/2025 5:09:49 PM
View Storm Water Management Plan (SWMP) 5/31/2025 9:34:32 PM
View Wetlands Analysis Report 7/11/2025 2:21:25 PM
View Channel Design Report 7/11/2025 2:21:27 PM
View Channel Maintenance Agreement 7/14/2025 5:09:52 PM
View Comment Response Tracker 7/14/2025 5:20:16 PM
View Reponses to Comments 2/24/2025 10:40:21 PM



Events (178)

Date Comment
7/29/2025 2:30:07 PM Project Manager Assigned: Daniel Torres
7/29/2025 2:03:10 PM Request for Review Comments returned by PCD Project Manager
7/29/2025 1:59:12 PM Request for Review Comments email resent for Project CDR Fishers Canyon Channel for review by Lori Seago on behalf of County Attorney - Development Review
7/25/2025 5:00:00 PM Request for Review Comments returned by County Attorney - Development Review
7/25/2025 3:49:21 PM Request for Review Comments returned by PCD Engineering Division
7/24/2025 2:39:59 PM Request for Review Comments returned by EPC Stormwater Review
7/15/2025 11:53:16 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Zachary Jannusch on behalf of EPC Stormwater Review
7/15/2025 11:53:15 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Mikayla Hartford on behalf of EPC Stormwater Review
7/15/2025 11:53:14 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Glenn Reese on behalf of EPC Stormwater Review
7/15/2025 11:53:13 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Christina Prete on behalf of EPC Stormwater Review
7/15/2025 11:53:11 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Lori Seago on behalf of County Attorney - Development Review
7/15/2025 11:53:10 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Erika Keech on behalf of County Attorney - Development Review
7/15/2025 11:53:09 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by April Willie on behalf of County Attorney - Development Review
7/15/2025 11:53:08 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Justin Kilgore on behalf of PCD Project Manager
7/15/2025 11:53:04 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Gilbert LaForce on behalf of PCD Engineering Division
7/15/2025 11:53:03 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Engineering Manager on behalf of PCD Engineering Division
7/15/2025 11:45:51 AM Submission Triaged
7/14/2025 5:28:34 PM Submission received from Applicant
7/8/2025 1:46:05 PM Project Manager Assigned: Jeff Rice
6/19/2025 2:22:45 PM Request for Review Comments returned by County Attorney - Development Review
6/18/2025 7:28:37 AM Submission request sent to Applicant
6/17/2025 5:31:01 PM Request for Review Comments returned by PCD Project Manager
6/16/2025 9:53:22 PM Request for Review Comments returned by PCD Engineering Division
6/12/2025 9:30:04 AM Request for Review Comments returned by EPC Stormwater Review
6/2/2025 3:40:51 PM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Gilbert LaForce on behalf of PCD Engineering Division
6/2/2025 3:40:50 PM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Engineering Manager on behalf of PCD Engineering Division
6/2/2025 3:39:44 PM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Kristy Martinez on behalf of Fountain
6/2/2025 3:39:43 PM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Brandy Williams on behalf of Fountain
6/2/2025 3:39:42 PM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Ben Sheets on behalf of Fountain
6/2/2025 3:39:41 PM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Zachary Jannusch on behalf of EPC Stormwater Review
6/2/2025 3:39:40 PM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Mikayla Hartford on behalf of EPC Stormwater Review
6/2/2025 3:39:39 PM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Glenn Reese on behalf of EPC Stormwater Review
6/2/2025 3:39:38 PM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Christina Prete on behalf of EPC Stormwater Review
6/2/2025 3:39:37 PM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Lori Seago on behalf of County Attorney - Development Review
6/2/2025 3:39:36 PM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Erika Keech on behalf of County Attorney - Development Review
6/2/2025 3:39:35 PM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by April Willie on behalf of County Attorney - Development Review
6/2/2025 3:39:33 PM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Justin Kilgore on behalf of PCD Project Manager
6/2/2025 3:35:43 PM Request for Review Comments sent for Project CDR Fishers Canyon Channel for review by Engineering Manager on behalf of PCD Engineering Division
6/2/2025 3:28:12 PM Submission Triaged
5/31/2025 9:36:06 PM Submission received from Applicant
3/20/2025 4:33:06 PM Request for Review Comments returned by Fountain
3/20/2025 7:24:08 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Kristy Martinez on behalf of Fountain
3/20/2025 7:24:07 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Brandy Williams on behalf of Fountain
3/20/2025 7:24:06 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Ben Sheets on behalf of Fountain
3/18/2025 1:34:46 PM Submission request sent to Applicant
3/18/2025 1:28:55 PM Request for Review Comments returned by PCD Project Manager
3/18/2025 1:21:59 PM Request for Review Comments returned by Stratmoor Hills Water & San
3/18/2025 1:17:11 PM Request for Review Comments returned by PCD Engineering Division
3/18/2025 12:17:56 PM Request for Review Comments returned by County Attorney - Development Review
3/17/2025 2:48:36 PM Request for Review Comments returned by EPC Stormwater Review
3/17/2025 8:15:19 AM Request for Review Comments email resent for Project CDR Fishers Canyon Channel for review by Lori Seago on behalf of County Attorney - Development Review
3/11/2025 12:24:11 PM Request for Review Comments returned by County Attorney - Development Review
2/25/2025 11:11:17 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Kirk Medina on behalf of Stratmoor Hills Water & San
2/25/2025 11:11:16 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Kevin Niles on behalf of Stratmoor Hills Water & San
2/25/2025 11:11:15 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Kristy Martinez on behalf of Fountain
2/25/2025 11:11:14 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Brandy Williams on behalf of Fountain
2/25/2025 11:11:12 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Ben Sheets on behalf of Fountain
2/25/2025 11:11:11 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Harry Thomas on behalf of El Paso County Conservation Dist
2/25/2025 11:11:10 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Oliver Watkins on behalf of El Paso County Conservation Dist
2/25/2025 11:11:09 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Katie Miller on behalf of El Paso County Conservation Dist
2/25/2025 11:11:08 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Erica Carter on behalf of El Paso County Conservation Dist
2/25/2025 11:11:07 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by on behalf of El Paso County Conservation Dist
2/25/2025 11:11:06 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Mariah Hudson on behalf of El Paso County Conservation Dist
2/25/2025 11:11:05 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Cassie Olgren on behalf of El Paso County Conservation Dist
2/25/2025 11:11:03 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Billy Richard on behalf of El Paso County Conservation Dist
2/25/2025 11:11:02 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Santiago Tijerina on behalf of Black Hills Energy-Aquila
2/25/2025 11:11:01 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Marcus Henderson on behalf of Black Hills Energy-Aquila
2/25/2025 11:11:00 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Bob Swatek on behalf of Black Hills Energy-Aquila
2/25/2025 11:10:59 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Adam Magoon on behalf of Black Hills Energy-Aquila
2/25/2025 11:10:57 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Daniel Delgado on behalf of US Army Corps of Engineers-Pueblo
2/25/2025 11:10:56 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Mikayla Hartford on behalf of EPC Stormwater Review
2/25/2025 11:10:55 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Glenn Reese on behalf of EPC Stormwater Review
2/25/2025 11:10:54 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Christina Prete on behalf of EPC Stormwater Review
2/25/2025 11:10:53 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Lori Seago on behalf of County Attorney - Development Review
2/25/2025 11:10:52 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Erika Keech on behalf of County Attorney - Development Review
2/25/2025 11:10:51 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by April Willie on behalf of County Attorney - Development Review
2/25/2025 11:10:50 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Justin Kilgore on behalf of PCD Project Manager
2/25/2025 11:10:45 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Gilbert LaForce on behalf of PCD Engineering Division
2/25/2025 11:10:44 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Engineering Manager on behalf of PCD Engineering Division
2/25/2025 10:32:45 AM Submission Triaged
2/24/2025 10:40:46 PM Submission received from Applicant
1/23/2025 4:14:01 PM Request for Review Comments returned by Fountain
1/13/2025 10:01:33 PM Submission request sent to Applicant
1/13/2025 9:54:39 PM Request for Review Comments returned by PCD Project Manager
1/13/2025 9:48:25 PM Request for Review Comments returned by PCD Engineering Division
1/9/2025 1:22:36 PM Request for Review Comments returned by EPC Stormwater Review
12/23/2024 3:44:39 PM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Kristy Martinez on behalf of Fountain
12/23/2024 3:44:37 PM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Brandy Williams on behalf of Fountain
12/23/2024 3:44:35 PM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Ben Sheets on behalf of Fountain
12/23/2024 3:44:33 PM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Mikayla Hartford on behalf of EPC Stormwater Review
12/23/2024 3:44:31 PM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Glenn Reese on behalf of EPC Stormwater Review
12/23/2024 3:44:29 PM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Christina Prete on behalf of EPC Stormwater Review
12/23/2024 3:44:27 PM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Justin Kilgore on behalf of PCD Project Manager
12/23/2024 3:44:18 PM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Gilbert LaForce on behalf of PCD Engineering Division
12/23/2024 3:44:16 PM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Engineering Manager on behalf of PCD Engineering Division
12/23/2024 3:36:47 PM Submission Triaged
12/23/2024 12:32:14 PM Submission received from Applicant
11/20/2024 10:52:25 AM Project Manager Assigned: Daniel Torres
11/6/2024 3:50:44 PM Submission request sent to Applicant
11/6/2024 3:44:20 PM Request for Review Comments returned by Fountain
10/31/2024 2:30:40 PM Request for Review Comments returned by EPC Stormwater Review
10/30/2024 9:59:20 PM Request for Review Comments returned by PCD Project Manager
10/30/2024 9:57:12 PM Request for Review Comments returned by PCD Engineering Division
10/24/2024 7:53:36 AM Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
10/16/2024 8:01:59 AM Request for Review Comments returned by RBD Floodplain
10/16/2024 7:40:00 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Kevin Niles on behalf of Stratmoor Hills Water & San
10/16/2024 7:39:58 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Kristy Martinez on behalf of Fountain
10/16/2024 7:39:56 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Brandy Williams on behalf of Fountain
10/16/2024 7:39:54 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Ben Sheets on behalf of Fountain
10/16/2024 7:39:52 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Keith Curtis on behalf of RBD Floodplain
10/16/2024 7:39:50 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Daniel Delgado on behalf of US Army Corps of Engineers-Pueblo
10/16/2024 7:39:48 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
10/16/2024 7:39:46 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
10/16/2024 7:39:43 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
10/16/2024 7:39:40 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Mikayla Hartford on behalf of EPC Stormwater Review
10/16/2024 7:39:39 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Glenn Reese on behalf of EPC Stormwater Review
10/16/2024 7:39:37 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Christina Prete on behalf of EPC Stormwater Review
10/16/2024 7:39:35 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Kari Parsons on behalf of PCD Project Manager
10/16/2024 7:39:26 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Gilbert LaForce on behalf of PCD Engineering Division
10/16/2024 7:39:24 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Engineering Manager on behalf of PCD Engineering Division
10/16/2024 7:37:23 AM Submission Triaged
10/16/2024 7:36:11 AM Project Manager Assigned: Engineering Manager
9/16/2024 2:16:04 PM Project Manager Assigned: Gilbert LaForce
9/15/2024 10:52:56 PM Submission received from Applicant
7/10/2024 3:12:06 PM Submission request sent to Applicant
7/3/2024 1:05:53 PM Submission request sent to Applicant
7/3/2024 11:05:19 AM Request for Review Comments returned by PCD Engineering Division
7/3/2024 11:02:05 AM Request for Review Comments email resent for Project CDR Fishers Canyon Channel for review by Engineering Manager on behalf of PCD Engineering Division
7/3/2024 10:00:19 AM Request for Review Comments returned by PCD Engineering Division
7/3/2024 9:57:25 AM Request for Review Comments email resent for Project CDR Fishers Canyon Channel for review by Engineering Manager on behalf of PCD Engineering Division
7/2/2024 10:54:51 PM Request for Review Comments returned by PCD Engineering Division
7/2/2024 4:31:50 PM Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
7/2/2024 9:01:15 AM Request for Review Comments returned by EPC Stormwater Review
6/18/2024 2:12:33 PM Request for Review Comments returned by Stratmoor HIlls Fire Department
6/14/2024 11:49:03 AM Request for Review Comments returned by PCD Project Manager
6/12/2024 12:30:27 PM Submission request canceled
6/11/2024 2:28:23 PM Request for Review Comments returned by Mountain View Electric Association, Inc.
6/11/2024 12:37:31 PM Request for Review Comments returned by RBD Floodplain
6/11/2024 8:44:21 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Kevin Niles on behalf of Stratmoor Hills Water & San
6/11/2024 8:44:19 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Mark Stanwood on behalf of Stratmoor HIlls Fire Department
6/11/2024 8:44:17 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Dottie Barrett on behalf of Stratmoor HIlls Fire Department
6/11/2024 8:44:15 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Jim Pesicka on behalf of Stratmoor Hills
6/11/2024 8:44:13 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by General Email on behalf of Mountain View Electric Association, Inc.
6/11/2024 8:44:11 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Kristy Martinez on behalf of Fountain
6/11/2024 8:44:09 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Brandy Williams on behalf of Fountain
6/11/2024 8:44:06 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Ben Sheets on behalf of Fountain
6/11/2024 8:44:04 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Oliver Watkins on behalf of El Paso County Conservation Dist
6/11/2024 8:44:02 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Katie Miller on behalf of El Paso County Conservation Dist
6/11/2024 8:44:00 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Mariah Hudson on behalf of El Paso County Conservation Dist
6/11/2024 8:43:57 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Santiago Tijerina on behalf of Black Hills Energy-Aquila
6/11/2024 8:43:55 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Bob Swatek on behalf of Black Hills Energy-Aquila
6/11/2024 8:43:53 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Adam Magoon on behalf of Black Hills Energy-Aquila
6/11/2024 8:43:51 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Keith Curtis on behalf of RBD Floodplain
6/11/2024 8:43:48 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Daniel Delgado on behalf of US Army Corps of Engineers-Pueblo
6/11/2024 8:43:46 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
6/11/2024 8:43:44 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
6/11/2024 8:43:42 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Arthur Gonzales on behalf of Colorado Department of Transportation - Pueblo Office
6/11/2024 8:43:40 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
6/11/2024 8:43:38 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Shannon Mustoe on behalf of EPC Stormwater Review
6/11/2024 8:43:35 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Mikayla Hartford on behalf of EPC Stormwater Review
6/11/2024 8:43:33 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Glenn Reese on behalf of EPC Stormwater Review
6/11/2024 8:43:31 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Christina Prete on behalf of EPC Stormwater Review
6/11/2024 8:43:27 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Kari Parsons on behalf of PCD Project Manager
6/11/2024 8:43:25 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Gilbert LaForce on behalf of PCD Engineering Division
6/11/2024 8:43:23 AM Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Engineering Manager on behalf of PCD Engineering Division
6/10/2024 4:00:46 PM Submission request sent to Applicant
6/6/2024 5:22:27 PM Fees paid: 6/6/2024 (Receipt: 1009215)
6/4/2024 2:20:43 PM Payment Request sent: 6/4/2024
6/4/2024 2:20:43 PM File # Assigned: CDR246
6/4/2024 2:20:33 PM Submission Triaged
6/4/2024 10:58:48 AM Submission received from Applicant
5/15/2024 1:49:35 PM Submission request sent to Applicant
5/15/2024 1:47:10 PM Project Manager Assigned: Scott Weeks
5/15/2024 1:43:54 PM Set Applicant to Kimley-Horn Associates
5/15/2024 1:43:10 PM Set Applicant to Kimley Horn & Associates
5/15/2024 1:31:21 PM Project Manager Assigned: Kari Parsons
5/15/2024 1:31:21 PM EA Assigned: EA2343
5/15/2024 1:31:21 PM Project Created