7/29/2025 2:30:07 PM
|
Project Manager Assigned: Daniel Torres
|
7/29/2025 2:03:10 PM
|
Request for Review Comments returned by PCD Project Manager
|
7/29/2025 1:59:12 PM
|
Request for Review Comments email resent for Project CDR Fishers Canyon Channel for review by Lori Seago on behalf of County Attorney - Development Review
|
7/25/2025 5:00:00 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
7/25/2025 3:49:21 PM
|
Request for Review Comments returned by PCD Engineering Division
|
7/24/2025 2:39:59 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
7/15/2025 11:53:16 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Zachary Jannusch on behalf of EPC Stormwater Review
|
7/15/2025 11:53:15 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
7/15/2025 11:53:14 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Glenn Reese on behalf of EPC Stormwater Review
|
7/15/2025 11:53:13 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Christina Prete on behalf of EPC Stormwater Review
|
7/15/2025 11:53:11 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Lori Seago on behalf of County Attorney - Development Review
|
7/15/2025 11:53:10 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Erika Keech on behalf of County Attorney - Development Review
|
7/15/2025 11:53:09 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by April Willie on behalf of County Attorney - Development Review
|
7/15/2025 11:53:08 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Justin Kilgore on behalf of PCD Project Manager
|
7/15/2025 11:53:04 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Gilbert LaForce on behalf of PCD Engineering Division
|
7/15/2025 11:53:03 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Engineering Manager on behalf of PCD Engineering Division
|
7/15/2025 11:45:51 AM
|
Submission Triaged
|
7/14/2025 5:28:34 PM
|
Submission received from Applicant
|
7/8/2025 1:46:05 PM
|
Project Manager Assigned: Jeff Rice
|
6/19/2025 2:22:45 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
6/18/2025 7:28:37 AM
|
Submission request sent to Applicant
|
6/17/2025 5:31:01 PM
|
Request for Review Comments returned by PCD Project Manager
|
6/16/2025 9:53:22 PM
|
Request for Review Comments returned by PCD Engineering Division
|
6/12/2025 9:30:04 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
6/2/2025 3:40:51 PM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Gilbert LaForce on behalf of PCD Engineering Division
|
6/2/2025 3:40:50 PM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Engineering Manager on behalf of PCD Engineering Division
|
6/2/2025 3:39:44 PM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Kristy Martinez on behalf of Fountain
|
6/2/2025 3:39:43 PM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Brandy Williams on behalf of Fountain
|
6/2/2025 3:39:42 PM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Ben Sheets on behalf of Fountain
|
6/2/2025 3:39:41 PM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Zachary Jannusch on behalf of EPC Stormwater Review
|
6/2/2025 3:39:40 PM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
6/2/2025 3:39:39 PM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Glenn Reese on behalf of EPC Stormwater Review
|
6/2/2025 3:39:38 PM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Christina Prete on behalf of EPC Stormwater Review
|
6/2/2025 3:39:37 PM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Lori Seago on behalf of County Attorney - Development Review
|
6/2/2025 3:39:36 PM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Erika Keech on behalf of County Attorney - Development Review
|
6/2/2025 3:39:35 PM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by April Willie on behalf of County Attorney - Development Review
|
6/2/2025 3:39:33 PM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Justin Kilgore on behalf of PCD Project Manager
|
6/2/2025 3:35:43 PM
|
Request for Review Comments sent for Project CDR Fishers Canyon Channel for review by Engineering Manager on behalf of PCD Engineering Division
|
6/2/2025 3:28:12 PM
|
Submission Triaged
|
5/31/2025 9:36:06 PM
|
Submission received from Applicant
|
3/20/2025 4:33:06 PM
|
Request for Review Comments returned by Fountain
|
3/20/2025 7:24:08 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Kristy Martinez on behalf of Fountain
|
3/20/2025 7:24:07 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Brandy Williams on behalf of Fountain
|
3/20/2025 7:24:06 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Ben Sheets on behalf of Fountain
|
3/18/2025 1:34:46 PM
|
Submission request sent to Applicant
|
3/18/2025 1:28:55 PM
|
Request for Review Comments returned by PCD Project Manager
|
3/18/2025 1:21:59 PM
|
Request for Review Comments returned by Stratmoor Hills Water & San
|
3/18/2025 1:17:11 PM
|
Request for Review Comments returned by PCD Engineering Division
|
3/18/2025 12:17:56 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
3/17/2025 2:48:36 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
3/17/2025 8:15:19 AM
|
Request for Review Comments email resent for Project CDR Fishers Canyon Channel for review by Lori Seago on behalf of County Attorney - Development Review
|
3/11/2025 12:24:11 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
2/25/2025 11:11:17 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Kirk Medina on behalf of Stratmoor Hills Water & San
|
2/25/2025 11:11:16 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Kevin Niles on behalf of Stratmoor Hills Water & San
|
2/25/2025 11:11:15 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Kristy Martinez on behalf of Fountain
|
2/25/2025 11:11:14 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Brandy Williams on behalf of Fountain
|
2/25/2025 11:11:12 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Ben Sheets on behalf of Fountain
|
2/25/2025 11:11:11 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Harry Thomas on behalf of El Paso County Conservation Dist
|
2/25/2025 11:11:10 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Oliver Watkins on behalf of El Paso County Conservation Dist
|
2/25/2025 11:11:09 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Katie Miller on behalf of El Paso County Conservation Dist
|
2/25/2025 11:11:08 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Erica Carter on behalf of El Paso County Conservation Dist
|
2/25/2025 11:11:07 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by on behalf of El Paso County Conservation Dist
|
2/25/2025 11:11:06 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Mariah Hudson on behalf of El Paso County Conservation Dist
|
2/25/2025 11:11:05 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Cassie Olgren on behalf of El Paso County Conservation Dist
|
2/25/2025 11:11:03 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Billy Richard on behalf of El Paso County Conservation Dist
|
2/25/2025 11:11:02 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Santiago Tijerina on behalf of Black Hills Energy-Aquila
|
2/25/2025 11:11:01 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Marcus Henderson on behalf of Black Hills Energy-Aquila
|
2/25/2025 11:11:00 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Bob Swatek on behalf of Black Hills Energy-Aquila
|
2/25/2025 11:10:59 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Adam Magoon on behalf of Black Hills Energy-Aquila
|
2/25/2025 11:10:57 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Daniel Delgado on behalf of US Army Corps of Engineers-Pueblo
|
2/25/2025 11:10:56 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
2/25/2025 11:10:55 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Glenn Reese on behalf of EPC Stormwater Review
|
2/25/2025 11:10:54 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Christina Prete on behalf of EPC Stormwater Review
|
2/25/2025 11:10:53 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Lori Seago on behalf of County Attorney - Development Review
|
2/25/2025 11:10:52 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Erika Keech on behalf of County Attorney - Development Review
|
2/25/2025 11:10:51 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by April Willie on behalf of County Attorney - Development Review
|
2/25/2025 11:10:50 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Justin Kilgore on behalf of PCD Project Manager
|
2/25/2025 11:10:45 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Gilbert LaForce on behalf of PCD Engineering Division
|
2/25/2025 11:10:44 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Engineering Manager on behalf of PCD Engineering Division
|
2/25/2025 10:32:45 AM
|
Submission Triaged
|
2/24/2025 10:40:46 PM
|
Submission received from Applicant
|
1/23/2025 4:14:01 PM
|
Request for Review Comments returned by Fountain
|
1/13/2025 10:01:33 PM
|
Submission request sent to Applicant
|
1/13/2025 9:54:39 PM
|
Request for Review Comments returned by PCD Project Manager
|
1/13/2025 9:48:25 PM
|
Request for Review Comments returned by PCD Engineering Division
|
1/9/2025 1:22:36 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
12/23/2024 3:44:39 PM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Kristy Martinez on behalf of Fountain
|
12/23/2024 3:44:37 PM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Brandy Williams on behalf of Fountain
|
12/23/2024 3:44:35 PM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Ben Sheets on behalf of Fountain
|
12/23/2024 3:44:33 PM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
12/23/2024 3:44:31 PM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Glenn Reese on behalf of EPC Stormwater Review
|
12/23/2024 3:44:29 PM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Christina Prete on behalf of EPC Stormwater Review
|
12/23/2024 3:44:27 PM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Justin Kilgore on behalf of PCD Project Manager
|
12/23/2024 3:44:18 PM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Gilbert LaForce on behalf of PCD Engineering Division
|
12/23/2024 3:44:16 PM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Engineering Manager on behalf of PCD Engineering Division
|
12/23/2024 3:36:47 PM
|
Submission Triaged
|
12/23/2024 12:32:14 PM
|
Submission received from Applicant
|
11/20/2024 10:52:25 AM
|
Project Manager Assigned: Daniel Torres
|
11/6/2024 3:50:44 PM
|
Submission request sent to Applicant
|
11/6/2024 3:44:20 PM
|
Request for Review Comments returned by Fountain
|
10/31/2024 2:30:40 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
10/30/2024 9:59:20 PM
|
Request for Review Comments returned by PCD Project Manager
|
10/30/2024 9:57:12 PM
|
Request for Review Comments returned by PCD Engineering Division
|
10/24/2024 7:53:36 AM
|
Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
|
10/16/2024 8:01:59 AM
|
Request for Review Comments returned by RBD Floodplain
|
10/16/2024 7:40:00 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Kevin Niles on behalf of Stratmoor Hills Water & San
|
10/16/2024 7:39:58 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Kristy Martinez on behalf of Fountain
|
10/16/2024 7:39:56 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Brandy Williams on behalf of Fountain
|
10/16/2024 7:39:54 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Ben Sheets on behalf of Fountain
|
10/16/2024 7:39:52 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Keith Curtis on behalf of RBD Floodplain
|
10/16/2024 7:39:50 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Daniel Delgado on behalf of US Army Corps of Engineers-Pueblo
|
10/16/2024 7:39:48 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
|
10/16/2024 7:39:46 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
|
10/16/2024 7:39:43 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
|
10/16/2024 7:39:40 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
10/16/2024 7:39:39 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Glenn Reese on behalf of EPC Stormwater Review
|
10/16/2024 7:39:37 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Christina Prete on behalf of EPC Stormwater Review
|
10/16/2024 7:39:35 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Kari Parsons on behalf of PCD Project Manager
|
10/16/2024 7:39:26 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Gilbert LaForce on behalf of PCD Engineering Division
|
10/16/2024 7:39:24 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Engineering Manager on behalf of PCD Engineering Division
|
10/16/2024 7:37:23 AM
|
Submission Triaged
|
10/16/2024 7:36:11 AM
|
Project Manager Assigned: Engineering Manager
|
9/16/2024 2:16:04 PM
|
Project Manager Assigned: Gilbert LaForce
|
9/15/2024 10:52:56 PM
|
Submission received from Applicant
|
7/10/2024 3:12:06 PM
|
Submission request sent to Applicant
|
7/3/2024 1:05:53 PM
|
Submission request sent to Applicant
|
7/3/2024 11:05:19 AM
|
Request for Review Comments returned by PCD Engineering Division
|
7/3/2024 11:02:05 AM
|
Request for Review Comments email resent for Project CDR Fishers Canyon Channel for review by Engineering Manager on behalf of PCD Engineering Division
|
7/3/2024 10:00:19 AM
|
Request for Review Comments returned by PCD Engineering Division
|
7/3/2024 9:57:25 AM
|
Request for Review Comments email resent for Project CDR Fishers Canyon Channel for review by Engineering Manager on behalf of PCD Engineering Division
|
7/2/2024 10:54:51 PM
|
Request for Review Comments returned by PCD Engineering Division
|
7/2/2024 4:31:50 PM
|
Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
|
7/2/2024 9:01:15 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
6/18/2024 2:12:33 PM
|
Request for Review Comments returned by Stratmoor HIlls Fire Department
|
6/14/2024 11:49:03 AM
|
Request for Review Comments returned by PCD Project Manager
|
6/12/2024 12:30:27 PM
|
Submission request canceled
|
6/11/2024 2:28:23 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
6/11/2024 12:37:31 PM
|
Request for Review Comments returned by RBD Floodplain
|
6/11/2024 8:44:21 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Kevin Niles on behalf of Stratmoor Hills Water & San
|
6/11/2024 8:44:19 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Mark Stanwood on behalf of Stratmoor HIlls Fire Department
|
6/11/2024 8:44:17 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Dottie Barrett on behalf of Stratmoor HIlls Fire Department
|
6/11/2024 8:44:15 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Jim Pesicka on behalf of Stratmoor Hills
|
6/11/2024 8:44:13 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by General Email on behalf of Mountain View Electric Association, Inc.
|
6/11/2024 8:44:11 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Kristy Martinez on behalf of Fountain
|
6/11/2024 8:44:09 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Brandy Williams on behalf of Fountain
|
6/11/2024 8:44:06 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Ben Sheets on behalf of Fountain
|
6/11/2024 8:44:04 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Oliver Watkins on behalf of El Paso County Conservation Dist
|
6/11/2024 8:44:02 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Katie Miller on behalf of El Paso County Conservation Dist
|
6/11/2024 8:44:00 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Mariah Hudson on behalf of El Paso County Conservation Dist
|
6/11/2024 8:43:57 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Santiago Tijerina on behalf of Black Hills Energy-Aquila
|
6/11/2024 8:43:55 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Bob Swatek on behalf of Black Hills Energy-Aquila
|
6/11/2024 8:43:53 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Adam Magoon on behalf of Black Hills Energy-Aquila
|
6/11/2024 8:43:51 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Keith Curtis on behalf of RBD Floodplain
|
6/11/2024 8:43:48 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Daniel Delgado on behalf of US Army Corps of Engineers-Pueblo
|
6/11/2024 8:43:46 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
|
6/11/2024 8:43:44 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
|
6/11/2024 8:43:42 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Arthur Gonzales on behalf of Colorado Department of Transportation - Pueblo Office
|
6/11/2024 8:43:40 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
|
6/11/2024 8:43:38 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Shannon Mustoe on behalf of EPC Stormwater Review
|
6/11/2024 8:43:35 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
6/11/2024 8:43:33 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Glenn Reese on behalf of EPC Stormwater Review
|
6/11/2024 8:43:31 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Christina Prete on behalf of EPC Stormwater Review
|
6/11/2024 8:43:27 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Kari Parsons on behalf of PCD Project Manager
|
6/11/2024 8:43:25 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Gilbert LaForce on behalf of PCD Engineering Division
|
6/11/2024 8:43:23 AM
|
Request for Review Comments email sent for Project CDR Fishers Canyon Channel for review by Engineering Manager on behalf of PCD Engineering Division
|
6/10/2024 4:00:46 PM
|
Submission request sent to Applicant
|
6/6/2024 5:22:27 PM
|
Fees paid: 6/6/2024 (Receipt: 1009215)
|
6/4/2024 2:20:43 PM
|
Payment Request sent: 6/4/2024
|
6/4/2024 2:20:43 PM
|
File # Assigned: CDR246
|
6/4/2024 2:20:33 PM
|
Submission Triaged
|
6/4/2024 10:58:48 AM
|
Submission received from Applicant
|
5/15/2024 1:49:35 PM
|
Submission request sent to Applicant
|
5/15/2024 1:47:10 PM
|
Project Manager Assigned: Scott Weeks
|
5/15/2024 1:43:54 PM
|
Set Applicant to Kimley-Horn Associates
|
5/15/2024 1:43:10 PM
|
Set Applicant to Kimley Horn & Associates
|
5/15/2024 1:31:21 PM
|
Project Manager Assigned: Kari Parsons
|
5/15/2024 1:31:21 PM
|
EA Assigned: EA2343
|
5/15/2024 1:31:21 PM
|
Project Created
|