Project Review Comments
- Project Name
- Marksheffel & Brushtop CDR
- Description
- West of Vollmer, Eastern Portion of Marksheffel Rd, and Brushtop and the Detention Pond
- Location
- Parcels
- 5200000575 5200000575 5200000577 5200000577
- Applicant
-
NES Inc
Andrea Barlow ( abarlow@nescolorado.com )
(719) 471-0073 Andrea Barlow ( abarlow@nescolorado.com )
(719) 471-0073 - File Number
- CDR2413
- Project Manager
- Bret Dilts
- Status
- Active
- Created
- 4/2/2024 2:44:41 PM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
County Attorney - Development Review
2/7/2025 1:19:01 PM |
The Detention Maintenance Agreement is proposing maintenance by a metropolitan district that does not yet exist. Who will be responsible for maintenance in the meantime? Please think through maintenance of the pond, select the correct DMA template, and complete all necessary information. Lori Seago Sr. County Attorney loriseago@elpasoco.com |
2/7/2025 1:19:01 PM | |
View |
EPC Stormwater Review
2/6/2025 10:50:50 AM |
Drainage Report | 2/6/2025 10:50:50 AM |
View |
EPC Stormwater Review
2/6/2025 10:48:19 AM |
Utility CDs | 2/6/2025 10:48:19 AM |
View |
EPC Stormwater Review
2/6/2025 10:47:10 AM |
SWMP Checklist | 2/6/2025 10:47:10 AM |
View |
EPC Stormwater Review
2/6/2025 10:46:30 AM |
SWMP | 2/6/2025 10:46:30 AM |
View |
EPC Stormwater Review
2/6/2025 10:26:25 AM |
SDI Form | 2/6/2025 10:26:25 AM |
View |
EPC Stormwater Review
2/6/2025 9:18:11 AM |
PBMP Applicability Form | 2/6/2025 9:18:11 AM |
View |
EPC Stormwater Review
2/6/2025 9:11:36 AM |
Private Detention Basin / Stormwater Quality BMP Maintenance Agreement | 2/6/2025 9:11:36 AM |
View |
EPC Stormwater Review
2/6/2025 9:11:07 AM |
O&M | 2/6/2025 9:11:07 AM |
View |
EPC Stormwater Review
2/6/2025 9:10:47 AM |
GEC Checklist | 2/6/2025 9:10:47 AM |
View |
EPC Stormwater Review
2/6/2025 9:09:59 AM |
GEC Plan | 2/6/2025 9:09:59 AM |
View |
EPC Stormwater Review
2/6/2025 9:07:33 AM |
FAE | 2/6/2025 9:07:33 AM |
View |
EPC Stormwater Review
2/6/2025 9:07:05 AM |
CDs | 2/6/2025 9:07:05 AM |
View |
EPC Stormwater Review
2/4/2025 4:49:05 PM |
ESQCP | 2/4/2025 4:49:05 PM |
PCD Project Manager
2/4/2025 4:20:20 PM |
See DPW Engineering comments. | 2/4/2025 4:20:20 PM | |
View |
PCD Engineering Division
2/4/2025 4:12:36 PM |
Letter of Intent | 2/4/2025 4:12:36 PM |
PCD Engineering Division
2/4/2025 4:13:21 PM |
DPW Engineering Review 1 has comments on the following documents: - Construction Drawings (to be uploaded by Stormwater) - Utility CDs (to be uploaded by Stormwater) - FAE (to be uploaded by Stormwater) - Drainage Report (to be uploaded by Stormwater) - Letter of Intent Review by Bret Dilts, PE bretdilts@elpasoco.com 719-520-6864 |
2/4/2025 4:13:21 PM | |
EPC Stormwater Review
2/6/2025 10:44:04 AM |
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded document(s): - CDs - Drainage Report - ESQCP - FAE - GEC Plan - GEC Checklist - O&M Manual - Private Detention Basin / Stormwater Quality BMP Maintenance Agreement - PBMP Applicability Form - SDI Form or MHFD_Detention Calcs - SWMP - SWMP Checklist - Utility CDs Please provide the following document(s) upon resubmittal (the planner will need to send an upload request): - Notice of Intent to Construct a Non-Jurisdictional Water Impoundment Structure (proof of submittal only) Note: The Soils Report and Landscape Plans will be reviewed once submitted. Reviewed by: Mikayla Hartford Stormwater Engineer I 719.339.5053 MikaylaHartford@elpasoco.com |
2/6/2025 10:44:04 AM | |
Mountain View Electric Association, Inc.
2/3/2025 11:21:25 AM |
MVEA has existing facilities near and within this parcel of land. MVEA will work with the developer on the design of the electric service and to acquire any utility easements. MVEA also requests the platting of MVEA’s existing facilities with easements on the plat, if applicable. If there is any damage, removal or relocation of facilities it will be at the expense of the applicant. | 2/3/2025 11:21:25 AM | |
Colorado Springs Public Works
1/30/2025 4:00:18 PM |
Construction plans for Marksheffel Rd. must be submitted to the City of Colorado Springs and approved prior to construction. Tract B will ultimately have to be dedicated to the City as right-of-way. Please submit the construction plans in Project Dox. Thank you. Joel Dagnillo, P.E. Engineering Development Review City of Colorado Springs (719)385-5412 Joel.dagnillo@coloradosprings.gov |
1/30/2025 4:00:18 PM | |
View |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
1/28/2025 1:34:45 PM |
See attached with comment. Best, Matthew Alcuran, MPA| Engineering Support Specialist Sr. Colorado Springs Utilities | Utilities Development Services 1521 South Hancock Expressway| MC 1812 | Colorado Springs, CO 80903 O: 719-668-8261 |malcuran@csu.org |
1/28/2025 1:34:45 PM |
Colorado Springs Public Works
1/15/2025 12:47:58 PM |
The developer is required to remit the amount of $100,000 for the future anticipated traffic signal at the intersection of Marksheffel Road with Vollmer Road. Zaker Alazzeh, P.E. Traffic Engineering Manager/Deputy City Traffic Engineer City of Colorado Springs (719) 385-5468 Zaker.Alazzeh@coloradosprings.gov |
1/15/2025 12:47:58 PM |