Project Review Comments
- Project Name
- UDON RV Storage
- Description
- RV Storage site development plan on CS zoned property over 35 acres
- Location
- Parcels
- 4400000237 4400000237
- Applicant
-
Kimley-Horn
Kevin Kofford ( kevin.kofford@kimley-horn.com )
(719) 352-9194 Kevin Kofford ( kevin.kofford@kimley-horn.com )
(719) 352-9194 - EA Number
- EA2417
- File Number
- PPR2422
- Project Manager
- Lisa Elgin
- Status
- Active
- Created
- 2/21/2024 10:00:50 AM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Project Manager
11/22/2024 3:29:32 PM |
No further comments. | 11/22/2024 3:29:32 PM | |
View |
County Attorney - Development Review
11/19/2024 12:18:10 PM |
Please see edits to attached DMA. Reviewed by: Erika Keech, Senior County Attorney, erikakeech2@elpasoco.com, 719-520-7013 |
11/19/2024 12:18:10 PM |
EPC Stormwater Review
11/21/2024 10:21:21 AM |
Review 4: EPC DPW Stormwater has no further comments. Provide signed Detention Basin / Stormwater Quality BMP Maintenance Agreement once County Attorney comments are addressed. Reviewed by: Mikayla Hartford Stormwater Engineer I 719.339.5053 MikaylaHartford@elpasoco.com |
11/21/2024 10:21:21 AM | |
County Attorney - Development Review
10/14/2024 3:25:58 PM |
Please submit a word version of the DMA. Reviewed by: Erika Keech, Senior County Attorney, erikakeech2@elpasoco.com, 719-520-7013 |
10/14/2024 3:25:58 PM | |
View |
PCD Project Manager
10/11/2024 11:44:46 AM |
See comments on Landscape Plan. | 10/11/2024 11:44:46 AM |
View |
PCD Project Manager
10/11/2024 11:43:50 AM |
See comments on Site Development Plan. | 10/11/2024 11:43:50 AM |
PCD Engineering Division
10/10/2024 6:01:31 PM |
Engineering Review Ver.3 No further engineering comments Please schedule PRECON EPC Road Impact fees applicable for Mini Warehouse $725/1,000 sf Assessed for 248Ksqft per site plan Edward Schoenheit, Engineer E.P.C. Dept. of Public Works 2880 International Circle Colorado Springs, CO. 80910 Office: 719.520.6813 Cell: 719.502.9659 https://planningdevelopment.elpasoco.com/ |
10/10/2024 6:01:31 PM | |
EPC Stormwater Review
10/10/2024 10:56:19 AM |
Review 3: Please provide the following documents upon resubmittal: - SDI Form or MHFD_Detention Calcs (Planner to send the upload request) - Detention Maintenance Agreement with Exhibits (MS WORD Version required) Reviewed by: Christina Prete, P.E. Stormwater Manager ChristinaPrete@elpasoco.com |
10/10/2024 10:56:19 AM | |
View |
Colorado Department of Transportation - Pueblo Office
10/8/2024 10:02:42 AM |
10/8/2024 10:02:42 AM | |
View |
EPC Health Department
10/6/2024 8:57:44 PM |
10/6/2024 8:57:44 PM | |
View |
Colorado Department of Transportation - Pueblo Office
10/3/2024 7:19:00 AM |
10/3/2024 7:19:00 AM | |
Pikes Peak Regional Building Department
10/2/2024 3:35:44 PM |
When submitting plans for permit each structure will be assigned a letter A-P. Contact Enumerations for this layout prior to submitting plans to RBD. No further comment. Amy Vanderbeek Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2930 E: Amy@pprbd.org |
10/2/2024 3:35:44 PM | |
View |
PCD Project Manager
9/19/2024 1:54:22 PM |
See comments on Landscape Plan. | 9/19/2024 1:54:22 PM |
View |
PCD Project Manager
9/19/2024 1:53:37 PM |
See comments on Site Development Plan. | 9/19/2024 1:53:37 PM |
View |
PCD Engineering Division
9/18/2024 8:30:49 AM |
GEC_V2 | 9/18/2024 8:30:49 AM |
View |
PCD Engineering Division
9/18/2024 8:30:20 AM |
SDP_V2 | 9/18/2024 8:30:20 AM |
View |
PCD Engineering Division
9/18/2024 8:30:00 AM |
ESQCP_V2 | 9/18/2024 8:30:00 AM |
View |
PCD Engineering Division
9/18/2024 8:29:43 AM |
DMA_V2 | 9/18/2024 8:29:43 AM |
PCD Engineering Division
9/18/2024 8:32:57 AM |
Engineering Review Ver.2 Please see engineering review comments on the following documents: Detention Maintenance Agreement_V2 Exhibit A is the property legal description Exhibit B is the FAE. Please update paragraphs for entry information. Legal review still required and may had additional comments. ESQCP_V2 Please use the comments and form from V1 to correct. The V2 ESQCP signatory page was invertedly replaced with the FDR signature page so the ESQCP form pages are mismatched. SDP_V2 PCD Comments GEC Plan_V2 Edward Schoenheit, Engineer E.P.C. Dept. of Public Works 2880 International Circle Colorado Springs, CO. 80910 Office: 719.520.6813 Cell: 719.502.9659 https://planningdevelopment.elpasoco.com/ |
9/18/2024 8:32:57 AM | |
View |
EPC Stormwater Review
9/17/2024 2:10:46 PM |
GEC Checklist | 9/17/2024 2:10:46 PM |
EPC Stormwater Review
9/17/2024 3:52:26 PM |
Review 2: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - GEC Plan.............(to be uploaded by Development Services Engineering) - GEC Checklist Please provide the following documents upon resubmittal (the planner will send an upload request): - SDI Form or MHFD_Detention Calcs Provide signed Detention Basin / Stormwater Quality BMP Maintenance Agreement once County Attorney comments are addressed. EPC DPW Stormwater comments have been resolved on the following documents: - Construction Drawings - Drainage Report - FAE - Notice of Intent to Construct a Non-Jurisdictional Water Impoundment Structure (proof of submittal only) - O&M Manual - PBMP Applicability Form - Private Detention Basin / Stormwater Quality BMP Maintenance Agreement - SWMP - SWMP Checklist Reviewed by: Mikayla Hartford Stormwater Engineer I 719.339.5053 MikaylaHartford@elpasoco.com |
9/17/2024 3:52:26 PM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
9/13/2024 9:53:03 AM |
All Springs Utilities comments have been addressed for PPR2422. | 9/13/2024 9:53:03 AM | |
Pikes Peak Regional Building Department
9/10/2024 10:17:32 AM |
1. Contact Enumerations for the layout prior to plan submittal with RBD. 2. In the title block of the first page of the developments plan the title block & below legal description of the parcel should read; The northeast quarter of the NORTHEAST quarter, not northwest. 3. On the El Paso County Assessor’s website there are still 3 buildings listed that you are not showing on site. Add these to the site plan or contact the Assessor’s get these structures removed (STORAGE WAREHOUSE, UTILITY BLDG & EQUIPMENT BLDG). Clarify which will be done. 4. How tall is the 2 proposed gates and fencing? If the fencing and gates exceeds 7’ , a separate address will need to be assigned along with a separate permit. Please clarify. Amy Vanderbeek Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2930 E: Amy@pprbd.org |
9/10/2024 10:17:32 AM | |
Pikes Peak Regional Building Department
9/5/2024 3:26:30 PM |
1. Plans and Permits for each RV storage carport will be required with Regional Building Department (RBD). 2. When submitting plans for permit each structure will be assigned a letter A-P. Contact Enumerations for this layout prior to submitting plans to RBD. 3. In the title block of the first page of the developments plan the title block & below legal description of the parcel should read The northeast quarter of the NORTHEAST quarter, not northwest. 4. On the El Paso County Assessor’s website there are still 3 buildings listed that you are not showing on site. Add these to the site plan or contact the Assessor’s get these structures removed (STORAGE WAREHOUSE, UTILITY BLDG & EQUIPMENT BLDG). Clarify which will be done. 5. How tall is the 2 proposed gates and fencing? If the fencing and gates exceeds 7’ , a separate address will need to be assigned along with a separate permit. Please clarify. Please disregard prior comments. These comments apply to another project. Sorry for the confusion. Amy Vanderbeek Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2930 E: Amy@pprbd.org |
9/5/2024 3:26:30 PM | |
Ellicott Fire Protection District
8/13/2024 5:55:09 PM |
Ellicott Fire Department has no objections to this site as described. | 8/13/2024 5:55:09 PM | |
View |
EPC Health Department
7/30/2024 7:56:28 PM |
7/30/2024 7:56:28 PM | |
View |
Colorado Department of Transportation - Pueblo Office
7/25/2024 2:35:29 PM |
7/25/2024 2:35:29 PM | |
View |
EPC Stormwater Review
7/17/2024 12:37:27 PM |
ESQCP | 7/17/2024 12:37:27 PM |
View |
EPC Stormwater Review
7/17/2024 12:37:11 PM |
SWMP Checklist | 7/17/2024 12:37:11 PM |
View |
EPC Stormwater Review
7/17/2024 12:36:54 PM |
SWMP | 7/17/2024 12:36:54 PM |
View |
EPC Stormwater Review
7/17/2024 12:36:01 PM |
Site Development Plan | 7/17/2024 12:36:01 PM |
View |
EPC Stormwater Review
7/17/2024 12:35:34 PM |
PBMP Applicability Form | 7/17/2024 12:35:34 PM |
View |
EPC Stormwater Review
7/17/2024 12:38:35 PM |
Detention Maintenance Agreement | 7/17/2024 12:38:35 PM |
View |
EPC Stormwater Review
7/17/2024 12:34:51 PM |
GEC Checklist | 7/17/2024 12:34:51 PM |
View |
EPC Stormwater Review
7/17/2024 12:33:15 PM |
GEC Plan | 7/17/2024 12:33:15 PM |
View |
EPC Stormwater Review
7/17/2024 12:32:47 PM |
FAE | 7/17/2024 12:32:47 PM |
View |
EPC Stormwater Review
7/17/2024 12:38:48 PM |
O&M | 7/17/2024 12:38:48 PM |
View |
EPC Stormwater Review
7/17/2024 12:31:28 PM |
Drainage Report | 7/17/2024 12:31:28 PM |
View |
PCD Project Manager
7/16/2024 4:02:51 PM |
Landscape Admin Relief | 7/16/2024 4:02:51 PM |
View |
PCD Project Manager
7/16/2024 4:02:19 PM |
Letter of Intent corrections | 7/16/2024 4:02:19 PM |
EPC Stormwater Review
7/17/2024 10:34:24 AM |
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - Drainage Report - FAE - GEC Plan - GEC Checklist - O&M Manual - Private Detention Basin / Stormwater Quality BMP Maintenance Agreement - PBMP Applicability Form - Site Development Plan - SWMP - SWMP Checklist Please provide the following documents upon resubmittal (the planner will send an upload request): - Notice of Intent to Construct a Non-Jurisdictional Water Impoundment Structure (proof of submittal only) - SDI Form or MHFD_Detention Calcs Reviewed by: Mikayla Hartford Stormwater Engineer I 719.339.5053 MikaylaHartford@elpasoco.com |
7/17/2024 10:34:24 AM | |
View |
PCD Engineering Division
7/15/2024 4:54:45 PM |
TIS_V1 | 7/15/2024 4:54:45 PM |
View |
PCD Engineering Division
7/15/2024 4:32:25 PM |
CDOT Comments | 7/15/2024 4:32:25 PM |
View |
PCD Engineering Division
7/15/2024 5:00:30 PM |
Engineering Review Ver.1 Please see engineering review comments on the following documents: Detention Maintenance Agreement_V1 Please use attached form and load into Detention Maintenance Agreement slot within EDARP. FDR_V1 (to be uploaded by SW) ESQCP_V1 (to be uploaded by SW) FAE_V1 (to be uploaded by SW) TIS_V1 see attached SDP_V1 (to be uploaded by PCD) GEC Plan_V1 (to be uploaded by SW) LOI_V1 (to be uploaded by PCD) Please combine all GEC plan sheets into one set as the GEC Plan set. Please coordinate with CDOT for review comments on the TIS. A CDOT Access permit will be required from CDOT. See CDOT comments Edward Schoenheit, Engineer I E.P.C. Dept. of Public Works 2880 International Circle Colorado Springs, CO. 80910 Office: 719.520.6813 Cell: 719.502.9659 https://planningdevelopment.elpasoco.com/ |
7/15/2024 5:00:30 PM |
View |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
7/10/2024 1:03:59 PM |
Good afternoon Lisa, Please see the attached CSU 1st review of PPR2422. One (!) comment is requested. Best, Matthew Alcuran, MPA| Engineering Support Specialist Sr. Utilities Development Services | Colorado Springs Utilities 1521 South Hancock Expressway| MC 1812 | Colorado Springs, CO 80903 O: 719-668-8261 |malcuran@csu.org |
7/10/2024 1:03:59 PM |
911 Authority - El Paso/Teller County
7/9/2024 9:27:00 AM |
No action for E911 on this submittal. Thank you. Justin |
7/9/2024 9:27:00 AM | |
Schriever AFB
7/1/2024 1:48:18 PM |
No comments. | 7/1/2024 1:48:18 PM | |
Pikes Peak Regional Building Department
7/1/2024 12:23:34 PM |
1. The existing plat shows the street name as Silverado Hill LOOP not view. Change the suffix in the street name. El Paso-tell E-9-1-1 should be included in this review to clarify the correct spelling of this street name. 2. The configuration has changed from the original layout. Before the area can be assigned addressing, Enumerations will need to see the overall layout. Please email to Amy Vanderbeek Amy@pprbd.org 3. Standard Final Plat comments: a. Enumerations will review the pre-plat (mylar) prior to plat for address placement, street names, and title block. b. A $10.00 per lot and tract platting fee will be due at the time of the review of the pre-plat, (two addresses per lot and tract). If an address is not needed on a tract then no fee applies. Check should be made out to PIKES PEAK REGIONAL BUILDING DEPARTMENT or PPRBD. Paid directly to the Enumerations Department. As of December 5th 2023, the fee for all credit/debit cards has changed from the flat 2.95% fee to the following: Over the phone Credit/Debit Card payments will be 2.3% and In-Person Debit Card payments will be 1.5% (in-person only). c. A copy of the final recorded plat is required prior to plan submittal for RESIDENTIAL. A copy of the final recorded plat is required prior to approval in the Enumerations department on any COMMERCIAL plan submittal. Please email the Enumerations staff member that reviewed your project. Amy@pprbd.org; Brent@pprbd.org; or BeckyA@pprbd.org d. Pre-plat reviews can be reviewed via “pdf” or in-person. The pre-plat will be stamped by Enumerations for accuracy and returned to the applicant and the planner. All payments to be mailed to RBD via a check or credit card payment over the phone. Plats should not be recorded prior to Enumerations stamping the pre-plat and receiving payment of plat fees. If any pre-plat changes occur, even if changes do not apply to Enumerations, we still need to re-stamp the pre-plat. The Enumerations stamped pre-plat copy should match the recorded document minus a few signatures. If you would like an in-person review, please make an appointment on our website, https://www.pprbd.org/Home/BookAppt |
7/1/2024 12:23:34 PM | |
RBD Floodplain
7/1/2024 12:03:13 PM |
site not in the SFHA, no comment | 7/1/2024 12:03:13 PM |