1/9/2025 1:33:04 PM
|
Project Ready for Approval requests. Review Comment period is complete.
|
1/9/2025 12:46:30 PM
|
Request for Review Comments returned by PCD Project Manager
|
1/8/2025 3:53:15 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Justin Kilgore on behalf of PCD Project Manager
|
1/3/2025 5:14:51 PM
|
Request for Review Comments returned by EPC Health Department
|
12/31/2024 9:50:01 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Mike McCarthy on behalf of EPC Health Department
|
12/31/2024 9:49:59 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Catherine McGarvy on behalf of EPC Health Department
|
12/31/2024 9:49:57 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by HEAEH LandUse on behalf of EPC Health Department
|
12/31/2024 9:47:05 AM
|
Submission Triaged
|
12/31/2024 9:31:06 AM
|
Submission received from Applicant
|
12/31/2024 9:26:16 AM
|
Submission request sent to Applicant
|
12/31/2024 9:23:03 AM
|
Submission request canceled
|
12/31/2024 9:12:53 AM
|
Submission request sent to Applicant
|
12/31/2024 9:12:18 AM
|
Submission Triaged
|
12/31/2024 9:01:21 AM
|
Submission received from Applicant
|
12/30/2024 3:46:09 PM
|
Submission request sent to Applicant
|
12/30/2024 2:09:36 PM
|
Submission request sent to Applicant
|
12/10/2024 11:10:12 AM
|
Request for Review Comments returned by County Attorney - Development Review
|
12/10/2024 9:30:17 AM
|
Submission Triaged
|
12/10/2024 9:07:04 AM
|
Submission received from Applicant
|
12/10/2024 8:58:49 AM
|
Submission request sent to Applicant
|
12/8/2024 4:26:29 PM
|
Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
|
12/8/2024 8:06:34 AM
|
Request for Review Comments returned by EPC Health Department
|
11/26/2024 10:35:51 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Lori Seago on behalf of County Attorney - Development Review
|
11/26/2024 10:35:49 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Erika Keech on behalf of County Attorney - Development Review
|
11/26/2024 10:35:47 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by April Willie on behalf of County Attorney - Development Review
|
11/26/2024 10:32:57 AM
|
Submission Triaged
|
11/25/2024 1:27:11 PM
|
Submission received from Applicant
|
11/22/2024 3:54:01 PM
|
Submission request sent to Applicant
|
11/22/2024 3:44:33 PM
|
Request for Review Comments returned by PCD Project Manager
|
11/21/2024 10:37:26 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
11/19/2024 12:18:19 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
11/8/2024 2:59:59 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
|
11/8/2024 2:59:57 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
|
11/8/2024 2:59:54 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
|
11/8/2024 2:59:52 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
11/8/2024 2:59:50 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Glenn Reese on behalf of EPC Stormwater Review
|
11/8/2024 2:59:49 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Christina Prete on behalf of EPC Stormwater Review
|
11/8/2024 2:59:47 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Mike McCarthy on behalf of EPC Health Department
|
11/8/2024 2:59:45 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Catherine McGarvy on behalf of EPC Health Department
|
11/8/2024 2:59:43 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by HEAEH LandUse on behalf of EPC Health Department
|
11/8/2024 2:59:41 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Lori Seago on behalf of County Attorney - Development Review
|
11/8/2024 2:59:39 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Erika Keech on behalf of County Attorney - Development Review
|
11/8/2024 2:59:37 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by April Willie on behalf of County Attorney - Development Review
|
11/8/2024 2:59:33 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Justin Kilgore on behalf of PCD Project Manager
|
11/8/2024 11:47:19 AM
|
Submission Triaged
|
11/6/2024 2:47:27 PM
|
Submission received from Applicant
|
11/6/2024 1:59:13 PM
|
Submission request sent to Applicant
|
11/6/2024 1:57:29 PM
|
Submission Triaged
|
11/4/2024 9:49:54 AM
|
Submission received from Applicant
|
10/15/2024 8:52:41 AM
|
Submission request sent to Applicant
|
10/14/2024 3:26:08 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
10/11/2024 11:45:00 AM
|
Request for Review Comments returned by PCD Project Manager
|
10/10/2024 6:02:16 PM
|
Request for Review Comments returned by PCD Engineering Division
|
10/10/2024 10:58:08 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
10/8/2024 10:03:08 AM
|
Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
|
10/7/2024 9:06:50 AM
|
Request for Review Comments email resent for Project UDON RV Storage for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
|
10/6/2024 8:58:18 PM
|
Request for Review Comments returned by EPC Health Department
|
10/3/2024 7:19:14 AM
|
Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
|
10/2/2024 3:35:53 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
10/1/2024 2:50:58 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Lori Seago on behalf of County Attorney - Development Review
|
10/1/2024 2:50:56 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Erika Keech on behalf of County Attorney - Development Review
|
10/1/2024 2:50:55 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by April Willie on behalf of County Attorney - Development Review
|
9/27/2024 1:31:22 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by on behalf of Pikes Peak Regional Building Department
|
9/27/2024 1:31:20 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
9/27/2024 1:31:18 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Glenn Reese on behalf of EPC Stormwater Review
|
9/27/2024 1:31:17 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Christina Prete on behalf of EPC Stormwater Review
|
9/27/2024 1:31:13 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Kari Parsons on behalf of PCD Project Manager
|
9/27/2024 1:31:09 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Gilbert LaForce on behalf of PCD Engineering Division
|
9/27/2024 1:31:05 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Engineering Manager on behalf of PCD Engineering Division
|
9/27/2024 1:24:26 PM
|
Submission Triaged
|
9/26/2024 11:00:29 AM
|
Submission received from Applicant
|
9/23/2024 8:49:36 AM
|
Request for Review Comments email resent for Project UDON RV Storage for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
|
9/23/2024 8:33:33 AM
|
Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
|
9/19/2024 2:14:41 PM
|
Submission request sent to Applicant
|
9/19/2024 1:55:05 PM
|
Request for Review Comments returned by PCD Project Manager
|
9/19/2024 1:52:17 PM
|
Request for Review Comments email resent for Project UDON RV Storage for review by Kari Parsons on behalf of PCD Project Manager
|
9/18/2024 8:33:06 AM
|
Request for Review Comments returned by PCD Engineering Division
|
9/17/2024 3:53:06 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
9/17/2024 1:37:39 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
9/16/2024 2:07:26 PM
|
Request for Review Comments email resent for Project UDON RV Storage for review by on behalf of Pikes Peak Regional Building Department
|
9/13/2024 9:53:21 AM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
9/10/2024 10:18:48 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
9/9/2024 2:14:23 PM
|
Request for Review Comments returned by PCD Project Manager
|
9/9/2024 8:33:33 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by on behalf of Pikes Peak Regional Building Department
|
9/5/2024 3:26:40 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
9/3/2024 2:41:58 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by on behalf of Pikes Peak Regional Building Department
|
9/3/2024 2:41:56 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
|
9/3/2024 2:41:55 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
|
9/3/2024 2:41:53 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Arthur Gonzales on behalf of Colorado Department of Transportation - Pueblo Office
|
9/3/2024 2:41:51 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
|
9/3/2024 2:41:49 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by LBS Review on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
9/3/2024 2:41:47 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
9/3/2024 2:41:45 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
9/3/2024 2:41:43 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Glenn Reese on behalf of EPC Stormwater Review
|
9/3/2024 2:41:41 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Christina Prete on behalf of EPC Stormwater Review
|
9/3/2024 2:41:39 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Mike McCarthy on behalf of EPC Health Department
|
9/3/2024 2:41:37 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Catherine McGarvy on behalf of EPC Health Department
|
9/3/2024 2:41:35 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by HEAEH LandUse on behalf of EPC Health Department
|
9/3/2024 2:41:32 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Kari Parsons on behalf of PCD Project Manager
|
9/3/2024 2:41:28 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Gilbert LaForce on behalf of PCD Engineering Division
|
9/3/2024 2:41:24 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Engineering Manager on behalf of PCD Engineering Division
|
9/3/2024 2:03:48 PM
|
Submission Triaged
|
8/29/2024 2:57:59 PM
|
Submission received from Applicant
|
8/13/2024 5:56:20 PM
|
Request for Review Comments returned by Ellicott Fire Protection District
|
8/13/2024 2:37:27 PM
|
Submission request sent to Applicant
|
7/30/2024 7:56:52 PM
|
Request for Review Comments returned by EPC Health Department
|
7/25/2024 2:35:54 PM
|
Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
|
7/25/2024 2:15:29 PM
|
Request for Review Comments email resent for Project UDON RV Storage for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
|
7/25/2024 10:03:17 AM
|
Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
|
7/17/2024 5:10:48 PM
|
Submission request sent to Applicant
|
7/17/2024 12:39:41 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
7/16/2024 4:03:07 PM
|
Request for Review Comments returned by PCD Project Manager
|
7/15/2024 5:01:23 PM
|
Request for Review Comments returned by PCD Engineering Division
|
7/11/2024 7:48:59 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
|
7/11/2024 7:48:57 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
|
7/11/2024 7:48:55 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Arthur Gonzales on behalf of Colorado Department of Transportation - Pueblo Office
|
7/11/2024 7:48:53 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
|
7/10/2024 1:04:10 PM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
7/9/2024 9:27:08 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
7/5/2024 4:05:57 PM
|
Request for Review Comments returned by Colorado Springs Planning & Community Development
|
7/1/2024 3:12:18 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
7/1/2024 3:12:16 PM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Glenn West on behalf of 911 Authority - El Paso/Teller County
|
7/1/2024 1:48:31 PM
|
Request for Review Comments returned by Schriever AFB
|
7/1/2024 12:23:44 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
7/1/2024 12:03:24 PM
|
Request for Review Comments returned by RBD Floodplain
|
7/1/2024 11:57:31 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Darren Horstmeier on behalf of Schriever AFB
|
7/1/2024 11:57:29 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Elizabeth Dukes on behalf of Peterson AFB
|
7/1/2024 11:57:27 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Peggy Current on behalf of Ellicott Metro
|
7/1/2024 11:57:25 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Mark Stanwood on behalf of Ellicott Fire Protection District
|
7/1/2024 11:57:23 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Michael Henley on behalf of Ellicott Fire Protection District
|
7/1/2024 11:57:21 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Gabe Sevigny on behalf of Colorado Springs Planning & Community Development
|
7/1/2024 11:57:19 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Keith Curtis on behalf of RBD Floodplain
|
7/1/2024 11:57:17 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by on behalf of Pikes Peak Regional Building Department
|
7/1/2024 11:57:15 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by george san miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
7/1/2024 11:57:13 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
7/1/2024 11:57:11 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Chris Smith on behalf of Ellicott SD 22
|
7/1/2024 11:57:09 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by LBS Review on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
7/1/2024 11:57:07 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
7/1/2024 11:57:05 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Shannon Mustoe on behalf of EPC Stormwater Review
|
7/1/2024 11:57:03 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
7/1/2024 11:57:01 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Glenn Reese on behalf of EPC Stormwater Review
|
7/1/2024 11:56:59 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Christina Prete on behalf of EPC Stormwater Review
|
7/1/2024 11:56:57 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by on behalf of EPC Public Works, County Engineer
|
7/1/2024 11:56:55 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by on behalf of EPC Public Works, County Engineer
|
7/1/2024 11:56:53 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Mike McCarthy on behalf of EPC Health Department
|
7/1/2024 11:56:51 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Catherine McGarvy on behalf of EPC Health Department
|
7/1/2024 11:56:49 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by HEAEH LandUse on behalf of EPC Health Department
|
7/1/2024 11:56:45 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Kari Parsons on behalf of PCD Project Manager
|
7/1/2024 11:56:43 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Gilbert LaForce on behalf of PCD Engineering Division
|
7/1/2024 11:56:42 AM
|
Request for Review Comments email sent for Project UDON RV Storage for review by Engineering Manager on behalf of PCD Engineering Division
|
6/27/2024 8:58:13 AM
|
Fees paid: 6/27/2024 (Receipt: 1009285)
|
6/26/2024 5:15:41 PM
|
Project Manager Assigned: Lisa Elgin
|
6/26/2024 2:24:02 PM
|
Payment Request sent: 6/26/2024
|
6/26/2024 2:24:02 PM
|
File # Assigned: PPR2422
|
6/26/2024 2:23:48 PM
|
Submission Triaged
|
6/26/2024 1:13:41 PM
|
Submission received from Applicant
|
6/26/2024 1:02:32 PM
|
Submission request sent to Applicant
|
6/26/2024 1:02:07 PM
|
Submission Triaged
|
6/26/2024 12:24:54 PM
|
Submission received from Applicant
|
2/27/2024 8:12:09 AM
|
Submission request sent to Applicant
|
2/21/2024 10:00:57 AM
|
Project Manager Assigned: Ryan Howser
|
2/21/2024 10:00:57 AM
|
EA Assigned: EA2417
|
2/21/2024 10:00:57 AM
|
Project Created
|