Project Review Comments
- Project Name
- 2290 OLD RANCH RD CDR
- Description
- 3/4 acre disturbance occurred; disturbance in sensitive area Kettle creek; Floodplain/ PBJM on - site. SF residence requested to be constructed; see photos in additional docs in this file. This approval is for the Grading plan, & associated site plan -
- Location
- Parcels
- 6228005038 6228005038
- Applicant
-
LGA Studios
Larry Gilland ( larry@lgastudios.com )
(719) 635-0880 Larry Gilland ( larry@lgastudios.com )
(719) 635-0880 - File Number
- CDR2320
- Project Manager
- Kari Parsons
- Status
- Closed
- Created
- 10/16/2023 4:34:41 PM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Engineering Division
2/26/2024 4:32:35 PM |
Previous review comments have been resolved. Any approved documents will be uploaded by the project manager. Reviewed by: Carlos Hernandez carloshernandez@elpasoco.com |
2/26/2024 4:32:35 PM | |
PCD Project Manager
2/22/2024 8:09:48 AM |
Please contact engineering to discuss comments if there are questions. Carlos Hernandez 719-520-6314 & Glenn Reese 7196752654. | 2/22/2024 8:09:48 AM | |
PCD Engineering Division
2/22/2024 3:25:15 PM |
As discussed in the email sent to applicant and phone call with engineer please revise calculation formatting in the drainage report and resubmit with the owner's signature. Please note the drainage report should be signed by the owner/developer. Reviewed by: Carlos Hernandez carloshernandez@elpasoco.com |
2/22/2024 3:25:15 PM | |
EPC Stormwater Review
2/21/2024 4:40:57 PM |
Review 3: EPC DPW Stormwater comments have been resolved on the following documents: - GEC Plan EPC DPW Stormwater has no further comments. Planner: no re-review necessary. Reviewed by: Mikayla Hartford Stormwater Engineer I MikaylaHartford@elpasoco.com |
2/21/2024 4:40:57 PM | |
View |
PCD Engineering Division
2/7/2024 4:52:34 PM |
V2_GEC Plan Comments | 2/7/2024 4:52:34 PM |
View |
PCD Engineering Division
2/7/2024 4:52:11 PM |
V2_Drainage Report Comments | 2/7/2024 4:52:11 PM |
PCD Engineering Division
2/7/2024 4:51:40 PM |
Review 2: Review comments on the following documents: - Drainage Report Reviewed by: Carlos Hernandez carloshernandez@elpasoco.com |
2/7/2024 4:51:40 PM | |
Pikes Peak Regional Building Department
1/31/2024 6:39:33 AM |
No further comment. Amy Vanderbeek Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2930 E: Amy@pprbd.org |
1/31/2024 6:39:33 AM | |
EPC Stormwater Review
2/5/2024 2:54:12 PM |
Review 2: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - GEC Plan...............(to be uploaded with Development Services comments) EPC DPW Stormwater comments have been resolved on the following documents: - Drainage Report - ESQCP - FAE - GEC Checklist - PBMP - Site Plan - SWMP - SWMP Checklist Reviewed by: Mikayla Hartford Stormwater Engineer I MikaylaHartford@elpasoco.com |
2/5/2024 2:54:12 PM | |
View |
EPC Stormwater Review
12/7/2023 5:25:25 PM |
SWMP Checklist | 12/7/2023 5:25:25 PM |
View |
EPC Stormwater Review
12/7/2023 5:23:53 PM |
SWMP | 12/7/2023 5:23:53 PM |
View |
EPC Stormwater Review
12/7/2023 5:23:21 PM |
Site Plan | 12/7/2023 5:23:21 PM |
View |
EPC Stormwater Review
12/7/2023 5:23:01 PM |
PBMP | 12/7/2023 5:23:01 PM |
View |
EPC Stormwater Review
12/7/2023 5:22:44 PM |
GEC Checklist | 12/7/2023 5:22:44 PM |
View |
EPC Stormwater Review
12/7/2023 5:22:23 PM |
GEC Plan | 12/7/2023 5:22:23 PM |
View |
EPC Stormwater Review
12/7/2023 5:21:57 PM |
FAE | 12/7/2023 5:21:57 PM |
View |
EPC Stormwater Review
12/7/2023 5:21:38 PM |
ESQCP | 12/7/2023 5:21:38 PM |
View |
EPC Stormwater Review
12/7/2023 5:18:50 PM |
Drainage Report | 12/7/2023 5:18:50 PM |
RBD Floodplain
12/7/2023 3:34:40 PM |
I visited the site today 12/7/23, and found that the berm shown on the GECP was installed as drawn outside the floodplain. Also the erosion control mat which protruded slightly into the mapped floodplain at grade was installed. The bank had been disturbed under the erosion control matting by the owner who was removing concrete rubble as I understand it. No appreciable fill was noted in the floodplain and the banks appeared to be stabilized as if work was complete in that area. Any future fill plans along the creek bank should be coordinated with the Regional Floodplain office: Keith Curtis, PE Floodplain Administrator Pikes Peak Regional Building Department 2880 International Circle Colorado Springs CO, 80910 O: 719-327-2898 E: keith@pprbd.org W: pprbd.org No further comments on this plan , and no further requirements from the floodplain office for this project. |
12/7/2023 3:34:40 PM | |
View |
Colorado Parks and Wildlife
12/7/2023 10:23:51 AM |
12/7/2023 10:23:51 AM | |
View |
PCD Engineering Division
12/6/2023 5:31:01 PM |
V1_LOI Comments | 12/6/2023 5:31:01 PM |
PCD Engineering Division
12/6/2023 5:28:43 PM |
Review 1: Review comments on the following documents: - Letter of Intent (uploaded) - Drainage Report (to be uploaded by stormwater engineer) - GEC Plan (to be uploaded by stormwater engineer) Reviewed by: Carlos Hernandez Review Engineer carloshernandez@elpasoco.com |
12/6/2023 5:28:43 PM | |
EPC Stormwater Review
12/7/2023 5:16:22 PM |
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - Drainage Report...(uploaded with Development Services comments) - ESQCP - FAE - GEC Plan...............(uploaded with Development Services comments) - GEC Checklist - PBMP - Site Plan - SWMP - SWMP Checklist Reviewed by: Mikayla Hartford Stormwater Engineer I MikaylaHartford@elpasoco.com |
12/7/2023 5:16:22 PM | |
RBD Floodplain
12/6/2023 2:57:37 PM |
No fill allowed in the floodway, please provide a site plan prepared by a licensed surveyor showing the extents of fill placed on site as well as the extents of the floodway including elevation data at the top and tow of fill areas. If fill has been placed in the floodway a no rise certification will need to be prepared by Colorado licensed engineer certifying that the fill has caused no rise in floodplain elevations, or the fill will need to be removed from the floodplain. |
12/6/2023 2:57:37 PM | |
Mountain View Electric Association, Inc.
12/6/2023 10:27:29 AM |
MVEA has an overhead electric line running east to west through the property. This must be shown on the plat/plan. No permanent structures are allowed within the 20 feet width of the easement/electric line. | 12/6/2023 10:27:29 AM | |
PCD Project Manager
12/6/2023 10:24:16 AM |
The planning staff does not review this type of CDR project and relies on the DPW staff expertise. | 12/6/2023 10:24:16 AM | |
Pikes Peak Regional Building Department
11/30/2023 11:10:53 AM |
1. Permit for the garage conversion to workshop (N23945), with Regional Building is in A statis, which means the inspections exceeded 180 days without an inspection. This permit needs to be reopened, receive inspections and closed out. No further comment. Amy Vanderbeek Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2930 E: Amy@pprbd.org |
11/30/2023 11:10:53 AM | |
RBD Floodplain
11/19/2023 7:25:44 AM |
no work shown in the floodplain, no further comment | 11/19/2023 7:25:44 AM |