2/28/2024 5:17:43 PM
|
Project Closed
|
2/28/2024 5:17:43 PM
|
Project Approved: 2/28/2024
|
2/26/2024 4:32:42 PM
|
Request for Review Comments returned by PCD Engineering Division
|
2/26/2024 3:39:39 PM
|
Project reopened for Approval requests
|
2/26/2024 3:39:30 PM
|
Project Closed
|
2/26/2024 3:39:30 PM
|
Project Approved: 2/26/2024
|
2/26/2024 3:39:13 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Gilbert LaForce on behalf of PCD Engineering Division
|
2/26/2024 3:39:11 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Engineering Manager on behalf of PCD Engineering Division
|
2/26/2024 3:38:31 PM
|
Submission Triaged
|
2/26/2024 3:36:40 PM
|
Submission received from Applicant
|
2/26/2024 1:37:26 PM
|
Submission request sent to Applicant
|
2/22/2024 5:03:01 PM
|
Request for Review Comments returned by PCD Engineering Division
|
2/22/2024 8:12:28 AM
|
Submission request sent to Applicant
|
2/22/2024 8:09:56 AM
|
Request for Review Comments returned by PCD Project Manager
|
2/21/2024 4:49:23 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
2/15/2024 2:14:53 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
2/15/2024 2:14:51 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Glenn Reese on behalf of EPC Stormwater Review
|
2/15/2024 2:14:49 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Christina Prete on behalf of EPC Stormwater Review
|
2/15/2024 2:14:45 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Gilbert LaForce on behalf of PCD Engineering Division
|
2/15/2024 2:14:43 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Engineering Manager on behalf of PCD Engineering Division
|
2/15/2024 2:13:32 PM
|
Submission Triaged
|
2/15/2024 11:33:14 AM
|
Submission received from Applicant
|
2/8/2024 7:18:31 AM
|
Submission request sent to Applicant
|
2/7/2024 4:53:13 PM
|
Request for Review Comments returned by PCD Engineering Division
|
2/6/2024 10:34:20 AM
|
Request for Review Comments returned by PCD Project Manager
|
2/6/2024 10:14:31 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
1/31/2024 6:39:42 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
1/22/2024 7:10:40 AM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by on behalf of Pikes Peak Regional Building Department
|
1/22/2024 7:10:38 AM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
1/22/2024 7:10:36 AM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Glenn Reese on behalf of EPC Stormwater Review
|
1/22/2024 7:10:34 AM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Christina Prete on behalf of EPC Stormwater Review
|
1/22/2024 7:10:30 AM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Gilbert LaForce on behalf of PCD Engineering Division
|
1/22/2024 7:10:28 AM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Engineering Manager on behalf of PCD Engineering Division
|
1/22/2024 7:08:56 AM
|
Submission Triaged
|
1/20/2024 6:22:57 PM
|
Submission received from Applicant
|
12/11/2023 7:21:31 AM
|
Submission request sent to Applicant
|
12/7/2023 5:27:23 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
12/7/2023 3:35:31 PM
|
Request for Review Comments returned by RBD Floodplain
|
12/7/2023 3:25:10 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Keith Curtis on behalf of RBD Floodplain
|
12/7/2023 10:24:27 AM
|
Request for Review Comments returned by Colorado Parks and Wildlife
|
12/6/2023 5:31:43 PM
|
Request for Review Comments returned by PCD Engineering Division
|
12/6/2023 5:24:24 PM
|
Request for Review Comments email resent for Project 2290 OLD RANCH RD CDR for review by Engineering Manager on behalf of PCD Engineering Division
|
12/6/2023 4:56:13 PM
|
Request for Review Comments returned by PCD Engineering Division
|
12/6/2023 2:57:46 PM
|
Request for Review Comments returned by RBD Floodplain
|
12/6/2023 10:47:39 AM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Lupe Packman on behalf of PCD Engineering Division
|
12/6/2023 10:47:36 AM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Gilbert LaForce on behalf of PCD Engineering Division
|
12/6/2023 10:47:34 AM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
12/6/2023 10:47:32 AM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Edward Schoenheit on behalf of PCD Engineering Division
|
12/6/2023 10:47:30 AM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Engineering Manager on behalf of PCD Engineering Division
|
12/6/2023 10:47:28 AM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Charlene Durham on behalf of PCD Engineering Division
|
12/6/2023 10:47:26 AM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Carlos Hernandez Martinez on behalf of PCD Engineering Division
|
12/6/2023 10:41:44 AM
|
Request for Review Comments email resent for Project 2290 OLD RANCH RD CDR for review by Keith Curtis on behalf of RBD Floodplain
|
12/6/2023 10:27:37 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
12/6/2023 10:24:23 AM
|
Request for Review Comments returned by PCD Project Manager
|
12/6/2023 10:13:18 AM
|
Request for Review Comments email resent for Project 2290 OLD RANCH RD CDR for review by Engineering Manager on behalf of PCD Engineering Division
|
12/6/2023 7:59:12 AM
|
Request for Review Comments returned by PCD Engineering Division
|
11/30/2023 11:11:04 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
11/19/2023 7:26:03 AM
|
Request for Review Comments returned by RBD Floodplain
|
11/16/2023 3:13:58 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by General Email on behalf of Mountain View Electric Association, Inc.
|
11/16/2023 3:13:56 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Keith Curtis on behalf of RBD Floodplain
|
11/16/2023 3:13:54 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by on behalf of Pikes Peak Regional Building Department
|
11/16/2023 3:13:52 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by george san miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
11/16/2023 3:13:50 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
11/16/2023 3:13:48 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Joseph Martinez on behalf of US Army Corps of Engineers-Pueblo
|
11/16/2023 3:13:46 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Tyson Floersheim on behalf of Colorado Parks and Wildlife
|
11/16/2023 3:13:44 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Travis Sauder on behalf of Colorado Parks and Wildlife
|
11/16/2023 3:13:42 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Tim Kroening on behalf of Colorado Parks and Wildlife
|
11/16/2023 3:13:40 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Sarah Watson on behalf of Colorado Parks and Wildlife
|
11/16/2023 3:13:38 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Philip Gurule on behalf of Colorado Parks and Wildlife
|
11/16/2023 3:13:36 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Karen Voltura on behalf of Colorado Parks and Wildlife
|
11/16/2023 3:13:34 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Corey Adler on behalf of Colorado Parks and Wildlife
|
11/16/2023 3:13:32 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Cassidy English on behalf of Colorado Parks and Wildlife
|
11/16/2023 3:13:30 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Drew Vrbenec on behalf of Colorado Parks and Wildlife
|
11/16/2023 3:13:28 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Aaron Berscheid on behalf of Colorado Parks and Wildlife
|
11/16/2023 3:13:26 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
11/16/2023 3:13:24 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Glenn Reese on behalf of EPC Stormwater Review
|
11/16/2023 3:13:22 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Christina Prete on behalf of EPC Stormwater Review
|
11/16/2023 3:13:18 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Lupe Packman on behalf of PCD Engineering Division
|
11/16/2023 3:13:16 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Gilbert LaForce on behalf of PCD Engineering Division
|
11/16/2023 3:13:14 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
11/16/2023 3:13:12 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Edward Schoenheit on behalf of PCD Engineering Division
|
11/16/2023 3:13:08 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Engineering Manager on behalf of PCD Engineering Division
|
11/16/2023 3:13:06 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Charlene Durham on behalf of PCD Engineering Division
|
11/16/2023 3:13:04 PM
|
Request for Review Comments email sent for Project 2290 OLD RANCH RD CDR for review by Carlos Hernandez Martinez on behalf of PCD Engineering Division
|
11/16/2023 3:11:26 PM
|
Submission Triaged
|
11/16/2023 3:00:40 PM
|
Submission received from Applicant
|
11/16/2023 12:15:23 PM
|
Submission request sent to Applicant
|
11/13/2023 7:33:08 PM
|
Fees paid: 11/13/2023 (Receipt: 1008515)
|
11/13/2023 4:08:14 PM
|
Submission request sent to Applicant
|
11/13/2023 4:03:36 PM
|
Submission request sent to Applicant
|
11/13/2023 2:27:16 PM
|
Payment Request sent: 11/13/2023
|
11/13/2023 2:27:15 PM
|
File # Assigned: CDR2320
|
11/13/2023 2:27:01 PM
|
Submission Triaged
|
11/13/2023 2:25:11 PM
|
Submission received from Applicant
|
10/16/2023 4:40:43 PM
|
Submission request sent to Applicant
|
10/16/2023 4:34:51 PM
|
Project Manager Assigned: Kari Parsons
|
10/16/2023 4:34:51 PM
|
Project Created
|