Project Review Comments
- Project Name
- Bent Grass Plaza - Site Development Plan
- Description
- 1 story commercial development of two buildings on three lots totaling 1.86 acres Woodmen Road Fees due at the Building Permit. Bent Grass Metro District fees to District due to District,
- Location
- Parcels
- 5301101063 5301101063 5301101064 5301101064 5301101065 5301101065
- Applicant
-
Bucher Design Studio
Nick Sallecchia ( nick@bucherdesign.com )
(719) 484-0480 Nick Sallecchia ( nick@bucherdesign.com )
(719) 484-0480 - File Number
- PPR2342
- Project Manager
- Christian Haas
- Status
- Closed
- Created
- 8/14/2023 4:29:04 PM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Project Manager
1/2/2024 3:24:46 PM |
All Planning, Engineering and Stormwater comments have been resolved. Awaiting approval and recordation of VR2320. | 1/2/2024 3:24:46 PM | |
PCD Engineering Division
1/2/2024 2:00:31 PM |
Review 3: Submit signed ESQCP; all other engineering documents are ready for approval/acceptance. Reviewed by: Jeff Rice jeffrice@elpasoco.com |
1/2/2024 2:00:31 PM | |
EPC Stormwater Review
12/19/2023 12:49:04 PM |
Review 3: EPC DPW Stormwater comments have been resolved on the following documents: - GEC Plan - GEC Checklist - PBMP Applicability Form - SWMP - SWMP Checklist Please sign and resubmit the following document: - ESQCP EPC DPW Stormwater has no further comments. Planner: no re-review necessary. Reviewed by: Glenn Reese, P.E. Stormwater Engineer III GlennReese@elpasoco.com |
12/19/2023 12:49:04 PM | |
PCD Project Manager
12/6/2023 11:11:48 AM |
All Planning Comments have been resolved. | 12/6/2023 11:11:48 AM | |
View |
PCD Engineering Division
12/4/2023 8:50:14 AM |
FAE | 12/4/2023 8:50:14 AM |
PCD Engineering Division
12/4/2023 8:56:10 AM |
Comments have been resolved on the following documents: -Traffic memo See attached comments for the following: -FAE Revise site plan to include "Utility and Site Plan" within it and not as a standalone document. Submit signed/stamped engineering documents in the next submittal. Reviewed By: Lupe Packman Lupepackman@elpasoco.com |
12/4/2023 8:56:10 AM | |
View |
EPC Stormwater Review
11/30/2023 8:48:15 AM |
SWMP | 11/30/2023 8:48:15 AM |
View |
EPC Stormwater Review
11/30/2023 8:47:59 AM |
GEC Plan | 11/30/2023 8:47:59 AM |
EPC Stormwater Review
11/21/2023 2:51:40 PM |
Review 2: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - GEC Plan - SWMP Please see my previous V1 comments on the following documents. Revised versions were not uploaded with this submittal. - GEC Checklist - PBMP Applicability Form - SWMP Checklist Please provide the following document upon resubmittal (the planner will send an upload request). This was requested with Review 1 and not provided. - ESQCP EPC DPW Stormwater comments have been resolved on the following documents: - Drainage Letter Reviewed by: Glenn Reese, P.E. Stormwater Engineer III GlennReese@elpasoco.com |
11/21/2023 2:51:40 PM | |
View |
El Paso County Conservation Dist
11/14/2023 9:36:24 AM |
11/14/2023 9:36:24 AM | |
Upper Black Squirrel Creek GWMD
11/8/2023 2:18:50 PM |
The Upper Black Squirrel Creek GWMD does not have any comments at this time but respectfully reserves the right to comment on any future submittals. Thank you. | 11/8/2023 2:18:50 PM | |
View |
Mountain View Electric Association, Inc.
11/7/2023 1:27:02 PM |
See attached comments | 11/7/2023 1:27:02 PM |
PCD Project Manager
11/3/2023 4:51:52 PM |
Building Height on Elevations sheet appears to list height as 123ft when I'm pretty sure you meant 23ft. Please update and resubmit. Site Plan, Lighting Plan, and Landscaping Plan are all good to go. | 11/3/2023 4:51:52 PM | |
View |
PCD Engineering Division
11/2/2023 5:41:50 PM |
Traffic memo | 11/2/2023 5:41:50 PM |
View |
PCD Engineering Division
11/2/2023 5:41:06 PM |
FAE | 11/2/2023 5:41:06 PM |
View |
PCD Engineering Division
11/2/2023 5:40:34 PM |
GEC plan | 11/2/2023 5:40:34 PM |
View |
PCD Engineering Division
11/2/2023 5:40:09 PM |
Drainage letter | 11/2/2023 5:40:09 PM |
PCD Engineering Division
11/2/2023 5:39:26 PM |
Review 1 comments are attached for the following: -Traffic memo -Gec plan -Drainage letter -FAE Reviewed By: Lupe Packman lupepackman@elpasoco.com |
11/2/2023 5:39:26 PM | |
Falcon School District 49
11/2/2023 3:25:22 PM |
District 49 has no comment at this time. We respectfully request the opportunity to comment on any future alterations. | 11/2/2023 3:25:22 PM | |
View |
EPC Stormwater Review
10/31/2023 8:54:38 AM |
SWMP Checklist | 10/31/2023 8:54:38 AM |
View |
EPC Stormwater Review
10/31/2023 8:52:36 AM |
SWMP | 10/31/2023 8:52:36 AM |
View |
EPC Stormwater Review
10/31/2023 8:51:46 AM |
PBMP Applicability Form | 10/31/2023 8:51:46 AM |
View |
EPC Stormwater Review
10/31/2023 8:51:27 AM |
GEC Checklist | 10/31/2023 8:51:27 AM |
Pikes Peak Regional Building Department
10/30/2023 11:36:25 AM |
1. Enumerations will require the final recorded document vacating the lot lines prior to signing off any plan submitted to Regional Building Department for permit issuance. 2. Once the lot line is vacated please use 11694 Bent Grass Market View for the larger of the two buildings. 3. If the trash enclosure exceeds 7’ therefore, a separate address will need to be assigned along with a separate permit. Amy Vanderbeek Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2930 E: Amy@pprbd.org |
10/30/2023 11:36:25 AM | |
EPC Stormwater Review
10/31/2023 8:55:30 AM |
Review 1: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - Drainage Letter...(to be uploaded with Development Services comments) - GEC Plan............(to be uploaded with Development Services comments) - GEC Checklist - PBMP Applicability Form - SWMP - SWMP Checklist Please provide the following document upon resubmittal (the planner will send an upload request): - ESQCP Reviewed by: Glenn Reese, P.E. Stormwater Engineer III GlennReese@elpasoco.com |
10/31/2023 8:55:30 AM | |
Bent Grass Metro
10/26/2023 2:21:13 PM |
This proposed project is located within the Bent Grass Metropolitan District boundaries. The District assess’ platting and building permit fees for new development within the District Boundaries, the District also assess’ a mill levy on property within the District Boundaries. The fees for this year are as follows: Traffic Signal Fee: Commercial - $10,000/ACRE Residential - $1,000/ACRE Platting Fees: Commercial- $5500/ACRE Residential- $5500/ACRE Building Permit Fees: Commercial- Commercial/Industrial/Other non-residential- $1.00/SQUARE FOOT |
10/26/2023 2:21:13 PM | |
View |
Falcon Fire Protection District
10/25/2023 9:05:48 AM |
10/25/2023 9:05:48 AM | |
View |
Falcon Fire Protection District
10/25/2023 9:05:11 AM |
10/25/2023 9:05:11 AM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
10/18/2023 11:00:22 AM |
Coordinate with CSU Field Engineering for any gas service connections or designs 719-668-4985 | 10/18/2023 11:00:22 AM |