2/29/2024 1:52:14 PM
|
Request for Review Comments email sent for Project Bent Grass Plaza - Site Development Plan for review by Rebecca Hardekopf on behalf of Woodmen Road Metro
|
2/29/2024 1:52:12 PM
|
Request for Review Comments email sent for Project Bent Grass Plaza - Site Development Plan for review by on behalf of Pikes Peak Regional Building Department
|
2/29/2024 1:52:10 PM
|
Request for Review Comments email sent for Project Bent Grass Plaza - Site Development Plan for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
2/29/2024 1:52:08 PM
|
Request for Review Comments email sent for Project Bent Grass Plaza - Site Development Plan for review by Glenn West on behalf of 911 Authority - El Paso/Teller County
|
2/29/2024 12:45:58 PM
|
Project Closed
|
2/29/2024 12:45:58 PM
|
Project Approved: 2/29/2024
|
2/29/2024 12:41:02 PM
|
Submission request canceled
|
2/29/2024 12:28:45 PM
|
Submission request sent to Applicant
|
1/2/2024 3:31:35 PM
|
Project Ready for Approval requests. Review Comment period is complete.
|
1/2/2024 3:30:58 PM
|
Request for Review Comments returned by PCD Project Manager
|
1/2/2024 2:00:54 PM
|
Request for Review Comments returned by PCD Engineering Division
|
12/19/2023 12:49:11 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
12/19/2023 8:34:49 AM
|
Request for Review Comments email sent for Project Bent Grass Plaza - Site Development Plan for review by Mikayla Hartford on behalf of EPC Stormwater Review
|
12/19/2023 8:34:47 AM
|
Request for Review Comments email sent for Project Bent Grass Plaza - Site Development Plan for review by Glenn Reese on behalf of EPC Stormwater Review
|
12/19/2023 8:34:45 AM
|
Request for Review Comments email sent for Project Bent Grass Plaza - Site Development Plan for review by Christina Prete on behalf of EPC Stormwater Review
|
12/19/2023 8:34:41 AM
|
Request for Review Comments email sent for Project Bent Grass Plaza - Site Development Plan for review by Lupe Packman on behalf of PCD Engineering Division
|
12/19/2023 8:34:39 AM
|
Request for Review Comments email sent for Project Bent Grass Plaza - Site Development Plan for review by Gilbert LaForce on behalf of PCD Engineering Division
|
12/19/2023 8:34:37 AM
|
Request for Review Comments email sent for Project Bent Grass Plaza - Site Development Plan for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
12/19/2023 8:34:35 AM
|
Request for Review Comments email sent for Project Bent Grass Plaza - Site Development Plan for review by Edward Schoenheit on behalf of PCD Engineering Division
|
12/19/2023 8:34:33 AM
|
Request for Review Comments email sent for Project Bent Grass Plaza - Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
|
12/19/2023 8:34:31 AM
|
Request for Review Comments email sent for Project Bent Grass Plaza - Site Development Plan for review by Charlene Durham on behalf of PCD Engineering Division
|
12/19/2023 8:34:29 AM
|
Request for Review Comments email sent for Project Bent Grass Plaza - Site Development Plan for review by Carlos Hernandez Martinez on behalf of PCD Engineering Division
|
12/19/2023 8:32:59 AM
|
Submission Triaged
|
12/11/2023 2:54:05 PM
|
Submission received from Applicant
|
12/6/2023 11:12:45 AM
|
Submission request sent to Applicant
|
12/6/2023 11:12:00 AM
|
Request for Review Comments returned by PCD Project Manager
|
12/4/2023 8:56:40 AM
|
Request for Review Comments returned by PCD Engineering Division
|
11/30/2023 8:48:30 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
11/21/2023 1:40:35 PM
|
Request for Review Comments sent for Project Bent Grass Plaza - Site Development Plan for review by Christina Prete on behalf of EPC Stormwater Review
|
11/21/2023 1:38:49 PM
|
Request for Review Comments sent for Project Bent Grass Plaza - Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
|
11/21/2023 1:35:38 PM
|
Submission request canceled
|
11/21/2023 1:26:28 PM
|
Submission request sent to Applicant
|
11/21/2023 1:25:28 PM
|
Submission Triaged
|
11/18/2023 9:22:52 PM
|
Submission received from Applicant
|
11/14/2023 9:36:32 AM
|
Request for Review Comments returned by El Paso County Conservation Dist
|
11/8/2023 3:51:08 PM
|
Submission request sent to Applicant
|
11/8/2023 2:19:08 PM
|
Request for Review Comments returned by Upper Black Squirrel Creek GWMD
|
11/7/2023 1:27:28 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
11/3/2023 4:52:07 PM
|
Request for Review Comments returned by PCD Project Manager
|
11/2/2023 5:42:02 PM
|
Request for Review Comments returned by PCD Engineering Division
|
11/2/2023 3:25:32 PM
|
Request for Review Comments returned by Falcon School District 49
|
11/2/2023 7:54:56 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
10/30/2023 12:32:35 PM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
10/26/2023 2:21:22 PM
|
Request for Review Comments returned by Bent Grass Metro
|
10/25/2023 9:06:22 AM
|
Request for Review Comments returned by Falcon Fire Protection District
|
10/18/2023 11:00:31 AM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
10/17/2023 8:36:18 AM
|
Request for Review Comments email sent for Project Bent Grass Plaza - Site Development Plan for review by General Email on behalf of Mountain View Electric Association, Inc.
|
10/17/2023 8:36:16 AM
|
Request for Review Comments email sent for Project Bent Grass Plaza - Site Development Plan for review by Evelyn galanephillips on behalf of Falcon School District 49
|
10/17/2023 8:36:14 AM
|
Request for Review Comments email sent for Project Bent Grass Plaza - Site Development Plan for review by Fire Chief Trent Harwig on behalf of Falcon Fire Protection District
|
10/17/2023 8:36:12 AM
|
Request for Review Comments email sent for Project Bent Grass Plaza - Site Development Plan for review by District Manager Mariah Hudson on behalf of El Paso County Conservation Dist
|
10/17/2023 8:36:09 AM
|
Request for Review Comments email sent for Project Bent Grass Plaza - Site Development Plan for review by UDS Admin Staff on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
10/17/2023 8:36:06 AM
|
Request for Review Comments email sent for Project Bent Grass Plaza - Site Development Plan for review by Rebecca Hardekopf on behalf of Bent Grass Metro
|
10/17/2023 8:36:04 AM
|
Request for Review Comments email sent for Project Bent Grass Plaza - Site Development Plan for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
|
10/17/2023 8:36:02 AM
|
Request for Review Comments email sent for Project Bent Grass Plaza - Site Development Plan for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
10/17/2023 8:36:00 AM
|
Request for Review Comments email sent for Project Bent Grass Plaza - Site Development Plan for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
10/17/2023 8:35:52 AM
|
Request for Review Comments email sent for Project Bent Grass Plaza - Site Development Plan for review by Catherine McGarvy on behalf of EPC Health Department
|
10/17/2023 8:35:46 AM
|
Request for Review Comments email sent for Project Bent Grass Plaza - Site Development Plan for review by Christian Haas on behalf of PCD Project Manager
|
10/17/2023 8:35:44 AM
|
Request for Review Comments email sent for Project Bent Grass Plaza - Site Development Plan for review by Engineering Manager on behalf of PCD Engineering Division
|
10/13/2023 2:52:34 PM
|
Fees paid: 10/13/2023 (Receipt: 1008427)
|
10/10/2023 3:58:38 PM
|
Payment Request sent: 10/10/2023
|
10/10/2023 3:58:38 PM
|
File # Assigned: PPR2342
|
10/10/2023 3:58:31 PM
|
Submission Triaged
|
10/10/2023 3:38:25 PM
|
Submission received from Applicant
|
8/14/2023 4:32:50 PM
|
Submission request sent to Applicant
|
8/14/2023 4:29:18 PM
|
Project Manager Assigned: Christian Haas
|
8/14/2023 4:29:18 PM
|
Project Created
|