PCD Engineering Division
1/4/2023 4:23:04 PM |
See previous comment letter for reference. All engineering documents have been forwarded for ECM Administrator's approval/acceptance and will be uploaded to EDARP when approved/accepted. Bridge material design life certifications will be required prior to acceptance. -- Jeff Rice - 719-520-7877 |
1/4/2023 4:23:04 PM | |
View |
PCD Engineering Division
12/14/2022 5:06:18 PM |
(Contech CDs redlines) | 12/14/2022 5:06:18 PM |
View |
Traffic Review Consultant
12/14/2022 3:52:00 PM |
Attached are a few comments on the drainage letter regarding riprap and scour. We agree that all other previous comments have been incorporated. We have no further comments on the bridge design or bridge construction drawings. We would like to see responses to our few comments, but do not require a full resubmittal based on these comments. | 12/14/2022 3:52:00 PM |
View |
PCD Engineering Division
12/14/2022 5:05:50 PM |
See comment letter (link at left) for reference. The following items need to be revised and resubmitted - Contech CDs Bridge material design life certifications will be required prior to acceptance. -- Jeff Rice - 719-520-7877 |
12/14/2022 5:05:50 PM |
View |
PCD Engineering Division
11/15/2022 9:34:05 AM |
(FAE redlines) | 11/15/2022 9:34:05 AM |
View |
PCD Engineering Division
11/15/2022 9:33:29 AM |
(Guardrail CDs redlines) | 11/15/2022 9:33:29 AM |
View |
PCD Engineering Division
11/15/2022 9:32:51 AM |
(Contech CDs redlines) | 11/15/2022 9:32:51 AM |
View |
PCD Engineering Division
11/15/2022 9:32:09 AM |
(GEC redlines) | 11/15/2022 9:32:09 AM |
View |
PCD Engineering Division
11/15/2022 9:29:27 AM |
(Drainage Letter redlines) | 11/15/2022 9:29:27 AM |
View |
PCD Engineering Division
11/15/2022 9:28:11 AM |
See comment letter (link at left) for reference. The following items need to be revised and resubmitted - Drainage report - CDs - Guardrail - CDs - Contech - GEC Plan - FAE Bridge material design life certifications will be required prior to acceptance. -- Jeff Rice - 719-520-7877 |
11/15/2022 9:28:11 AM |
View |
EPC Stormwater Review
11/6/2022 7:43:55 AM |
SWMP | 11/6/2022 7:43:55 AM |
EPC Stormwater Review
11/6/2022 7:43:05 AM |
Review 3: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - SWMP EPC Stormwater comments have been resolved on the following documents: - GEC Plan Reviewed by: Glenn Reese, P.E. Stormwater Engineer II glennreese@elpasoco.com |
11/6/2022 7:43:05 AM | |
View |
PCD Engineering Division
9/7/2022 12:08:52 PM |
(ESQCP redlines) | 9/7/2022 12:08:52 PM |
View |
PCD Engineering Division
9/7/2022 12:08:29 PM |
(PBMP Applicability Form redlines) | 9/7/2022 12:08:29 PM |
View |
PCD Engineering Division
9/7/2022 12:07:47 PM |
(FAE redlines) | 9/7/2022 12:07:47 PM |
View |
PCD Engineering Division
9/7/2022 12:07:21 PM |
(GEC redlines) | 9/7/2022 12:07:21 PM |
View |
PCD Engineering Division
9/7/2022 12:06:42 PM |
(Drainage Letter redlines) | 9/7/2022 12:06:42 PM |
View |
PCD Engineering Division
9/7/2022 12:00:21 PM |
(Bridge Design Report redlines) | 9/7/2022 12:00:21 PM |
View |
PCD Engineering Division
9/7/2022 11:59:22 AM |
(LOI redlines) | 9/7/2022 11:59:22 AM |
EPC Stormwater Review
9/6/2022 5:26:42 PM |
Review 2: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - GEC Plan...(to be uploaded by PCD) Unresolved comment: please provide the following documents on resubmittal: - SWMP - SWMP Checklist EPC Stormwater comments have been resolved on the following documents: - Drainage Letter - FAE - GEC Checklist Sign/stamp and resubmit the following document: - PBMP Applicability Form Reviewed by: Glenn Reese, P.E. Stormwater Engineer II glennreese@elpasoco.com |
9/6/2022 5:26:42 PM | |
PCD Project Manager
9/6/2022 11:33:08 AM |
Engineering will upload their comments shortly. | 9/6/2022 11:33:08 AM | |
View |
PCD Engineering Division
9/7/2022 11:56:36 AM |
See comment letter (link at left) for reference. A comment matrix spreadsheet for on-call consultant comments will be emailed separately. The following items need to be revised and resubmitted - Letter of Intent - Bridge design report - Drainage report - CDs (guardrails, railings, etc.) - GEC Plan - FAE - PBMP Applicability Form - Comment matrix response - Comment memo response The following items are required prior to approval of this project: - Project Specifications (including site/channel work and Conspan) Bridge material design life certifications will be required prior to acceptance. -- Jeff Rice - 719-520-7877 |
9/7/2022 11:56:36 AM |
View |
Traffic Review Consultant
8/30/2022 4:20:39 PM |
Most comments were addressed but this submittal is still missing the geotech report or addendum that provides the bearing pressure referenced in both the plans and bridge design report. Also missing are scour analysis and outlet protection design analysis. Please provide these items with the next submittal. | 8/30/2022 4:20:39 PM |
Colorado Springs Public Works
8/24/2022 9:04:42 AM |
Engineering Development Review has no comments on this item. Joel Dagnillo, P.E. Engineering Development Review City of Colorado Springs (719)385-5412 Joel.dagnillo@coloradosprings.gov |
8/24/2022 9:04:42 AM | |
Colorado Springs Public Works
8/15/2022 11:14:22 AM |
Traffic Engineering has no comments on this item. Zaker Alazzeh, P.E. Traffic Engineering Manager/Deputy City Traffic Engineer City of Colorado Springs (719) 385-5468 Zaker.Alazzeh@coloradosprings.gov |
8/15/2022 11:14:22 AM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
8/11/2022 4:19:01 PM |
Colorado Springs Utilities does not object to the application. If there is any conflict with our infrastructure during the consecution please call us. Corey Masoumi, cmasoumi@csu.org |
8/11/2022 4:19:01 PM | |
Mountain View Electric Association, Inc.
8/10/2022 2:15:41 PM |
Mountain View Electric Association has existing facilities near this parcel of land. If there is any damage, removal or relocation of facilities it will be at the expense of the applicant. | 8/10/2022 2:15:41 PM | |
PCD Engineering Division
6/13/2022 8:54:51 AM |
No comment on the geotechnical addendum - see previous comments. -- Jeff Rice - 719-520-7877 |
6/13/2022 8:54:51 AM | |
Traffic Review Consultant
6/9/2022 9:44:07 AM |
We do not have any comments on the provided Addendum to Geotech Report. Previous comments on the bridge report, drainage letter, and construction plans will require resubmittal. | 6/9/2022 9:44:07 AM | |
View |
PCD Engineering Division
6/7/2022 6:05:36 PM |
(FAE redlines) | 6/7/2022 6:05:36 PM |
View |
PCD Engineering Division
6/7/2022 6:05:10 PM |
(GEC redlines) | 6/7/2022 6:05:10 PM |
View |
PCD Engineering Division
6/7/2022 6:04:21 PM |
(CANDE redlines) | 6/7/2022 6:04:21 PM |
View |
PCD Engineering Division
6/7/2022 6:03:49 PM |
(CD redlines summary) | 6/7/2022 6:03:49 PM |
View |
PCD Engineering Division
6/7/2022 6:03:10 PM |
(CD redlines) | 6/7/2022 6:03:10 PM |
View |
PCD Engineering Division
6/7/2022 6:02:07 PM |
(Drainage Letter redlines) | 6/7/2022 6:02:07 PM |
View |
PCD Engineering Division
6/7/2022 6:00:04 PM |
(LOI redlines) | 6/7/2022 6:00:04 PM |
View |
PCD Engineering Division
6/7/2022 5:59:10 PM |
See comment letter (link at left) for reference. A comment matrix spreadsheet for on-call consultant comments will be emailed separately. The following items need to be revised and resubmitted - Letter of Intent - Bridge design report - Drainage report - CDs - GEC Plan - FAE - PBMP Applicability Form - Comment matrix response - Comment memo response The following items are required prior to approval of this project: - Project Specifications (including site/channel work and Conspan) Bridge material design life certifications will be required prior to acceptance. -- Jeff Rice - 719-520-7877 |
6/7/2022 5:59:10 PM |
Colorado Springs Public Works
6/2/2022 2:49:29 PM |
Engineering Development Review has no comments on this item. Joel Dagnillo, P.E. Engineering Development Review City of Colorado Springs (719)385-5412 Joel.dagnillo@coloradosprings.gov |
6/2/2022 2:49:29 PM | |
View |
EPC Stormwater Review
6/1/2022 4:23:34 PM |
GEC Checklist | 6/1/2022 4:23:34 PM |
Colorado Springs Public Works
6/1/2022 4:11:23 PM |
Traffic Engineering has no comments on this item. Zaker Alazzeh, P.E. Traffic Engineering Manager/Deputy City Traffic Engineer City of Colorado Springs (719) 385-5468 Zaker.Alazzeh@coloradosprings.gov |
6/1/2022 4:11:23 PM | |
View |
Traffic Review Consultant
6/1/2022 2:48:32 PM |
See attached PDF for comments on Bridge Design Report from FHU. | 6/1/2022 2:48:32 PM |
View |
Traffic Review Consultant
6/1/2022 2:45:43 PM |
See attached for comments on Construction Drawings from FHU | 6/1/2022 2:45:43 PM |
View |
Traffic Review Consultant
6/1/2022 2:43:49 PM |
See attached comment form for structural and hydraulic comments from FHU. | 6/1/2022 2:43:49 PM |
EPC Stormwater Review
6/1/2022 4:22:59 PM |
Review 1: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - Drainage Letter......(to be uploaded by PM with PCD comments) - FAE........................(to be uploaded by PM with PCD comments) - GEC Plan...............(to be uploaded by PM with PCD comments) - GEC Checklist Please provide the following documents on resubmittal: - ESQCP - PBMP Applicability Form (check "Yes" for exclusion H and explain in the Notes on pg 3 how much acreage and what percentage of the site that the exclusion applies to). - SWMP - SWMP Checklist Reviewed by: Glenn Reese, P.E. Stormwater Engineer II glennreese@elpasoco.com |
6/1/2022 4:22:59 PM | |
Mountain View Electric Association, Inc.
5/23/2022 9:24:38 AM |
Mountain View Electric Association has existing facilities near this parcel of land. If there is any damage, removal or relocation of facilities it will be at the expense of the applicant. | 5/23/2022 9:24:38 AM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
5/18/2022 4:08:21 PM |
No action item is required. Any conflict with Springs Utilities infrastructures must be reported to us. Approval can be recommended. ____________________________________________________ Corey Masoumi | Engineering Support Coordinator Utilities Development Services | Colorado Springs Utilities 1521 S Hancock Expy Colorado Springs, CO 80903 O: 719-668-1856 | Main: 719-668-8259 cmasoumi@csu.org | www.csu.org |
5/18/2022 4:08:21 PM |