7/11/2023 4:47:25 PM
|
Submission request sent to Applicant
|
1/5/2023 10:58:02 AM
|
Project Closed
|
1/5/2023 10:58:02 AM
|
Project Approved: 1/5/2023
|
1/4/2023 4:23:31 PM
|
Request for Review Comments returned by PCD Engineering Division
|
1/3/2023 7:27:17 AM
|
Request for Review Comments returned by PCD Project Manager
|
12/19/2022 7:17:30 AM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Kari Parsons on behalf of PCD Project Manager
|
12/19/2022 7:17:28 AM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
12/19/2022 7:16:48 AM
|
Submission Triaged
|
12/15/2022 10:29:33 AM
|
Submission received from Applicant
|
12/14/2022 5:24:27 PM
|
Request for Review Comments returned by PCD Project Manager
|
12/14/2022 5:06:59 PM
|
Request for Review Comments returned by PCD Engineering Division
|
12/14/2022 3:52:26 PM
|
Request for Review Comments returned by Traffic Review Consultant
|
12/13/2022 4:51:03 PM
|
Submission request sent to Applicant
|
11/30/2022 2:39:31 PM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Paul Brown on behalf of Traffic Review Consultant
|
11/30/2022 11:22:18 AM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Kari Parsons on behalf of PCD Project Manager
|
11/30/2022 11:22:16 AM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
11/30/2022 11:21:53 AM
|
Submission Triaged
|
11/29/2022 12:21:24 PM
|
Submission received from Applicant
|
11/15/2022 10:17:22 AM
|
Submission request sent to Applicant
|
11/15/2022 10:15:53 AM
|
Request for Review Comments returned by PCD Project Manager
|
11/15/2022 9:34:32 AM
|
Request for Review Comments returned by PCD Engineering Division
|
11/9/2022 2:45:30 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
11/3/2022 12:00:27 PM
|
Submission Triaged
|
11/3/2022 11:52:55 AM
|
Submission received from Applicant
|
11/2/2022 3:51:34 PM
|
Submission request sent to Applicant
|
10/25/2022 7:07:12 AM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
10/25/2022 7:07:08 AM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Kari Parsons on behalf of PCD Project Manager
|
10/25/2022 7:07:06 AM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
10/24/2022 4:45:21 PM
|
Submission Triaged
|
10/24/2022 3:42:56 PM
|
Submission received from Applicant
|
9/7/2022 1:43:39 PM
|
Submission request sent to Applicant
|
9/7/2022 12:09:24 PM
|
Request for Review Comments returned by PCD Engineering Division
|
9/6/2022 5:33:25 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
9/6/2022 11:33:16 AM
|
Request for Review Comments returned by PCD Project Manager
|
8/31/2022 8:22:10 AM
|
Request for Review Comments returned by Colorado Springs Public Works
|
8/30/2022 4:20:56 PM
|
Request for Review Comments returned by Traffic Review Consultant
|
8/22/2022 10:25:16 AM
|
Fees paid: 8/22/2022 (Receipt: 1006824)
|
8/15/2022 8:26:21 AM
|
Payment Request sent: 8/15/2022
|
8/11/2022 4:19:38 PM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
8/10/2022 2:15:50 PM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
8/10/2022 10:57:44 AM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by General Email on behalf of Mountain View Electric Association, Inc.
|
8/10/2022 10:57:40 AM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by UDS Admin Staff on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
8/10/2022 10:57:36 AM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Rae Carlson on behalf of Colorado Springs Public Works
|
8/10/2022 10:57:28 AM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Meggan Herington on behalf of Colorado Springs Planning & Community Development
|
8/10/2022 10:57:22 AM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Clara Lucero on behalf of CIG Colorado Interstate Gas
|
8/10/2022 10:57:21 AM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
8/10/2022 10:57:20 AM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Paul Brown on behalf of Traffic Review Consultant
|
8/10/2022 10:57:19 AM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
8/10/2022 10:57:18 AM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Joseph Martinez on behalf of US Army Corps of Engineers-Pueblo
|
8/10/2022 10:57:16 AM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
8/10/2022 10:57:13 AM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Joshua Palmer on behalf of EPC Public Works, County Engineer
|
8/10/2022 10:57:12 AM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Kari Parsons on behalf of PCD Project Manager
|
8/10/2022 10:57:10 AM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
8/10/2022 10:55:53 AM
|
Submission Triaged
|
8/10/2022 8:54:56 AM
|
Submission received from Applicant
|
6/13/2022 9:40:58 AM
|
Submission request sent to Applicant
|
6/13/2022 9:36:52 AM
|
Request for Review Comments returned by PCD Project Manager
|
6/13/2022 8:55:02 AM
|
Request for Review Comments returned by PCD Engineering Division
|
6/9/2022 9:44:15 AM
|
Request for Review Comments returned by Traffic Review Consultant
|
6/8/2022 10:35:48 AM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Paul Brown on behalf of Traffic Review Consultant
|
6/8/2022 10:35:47 AM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Kari Parsons on behalf of PCD Project Manager
|
6/8/2022 10:35:45 AM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
6/8/2022 10:34:27 AM
|
Submission Triaged
|
6/8/2022 10:07:34 AM
|
Submission received from Applicant
|
6/7/2022 6:05:53 PM
|
Request for Review Comments returned by PCD Engineering Division
|
6/3/2022 3:50:41 PM
|
Request for Review Comments returned by Colorado Springs Public Works
|
6/2/2022 1:30:08 PM
|
Request for Review Comments returned by PCD Project Manager
|
6/1/2022 4:43:28 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
6/1/2022 2:53:51 PM
|
Request for Review Comments returned by Traffic Review Consultant
|
5/28/2022 12:17:25 PM
|
Submission request sent to Applicant
|
5/23/2022 9:25:06 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
5/19/2022 12:08:40 PM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
5/19/2022 12:07:32 PM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Paul Brown on behalf of Traffic Review Consultant
|
5/18/2022 4:56:15 PM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Paul Brown on behalf of Traffic Review Consultant
|
5/18/2022 4:08:43 PM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
5/16/2022 8:42:50 AM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Paul Brown on behalf of Traffic Review Consultant
|
5/10/2022 3:33:40 PM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by General Email on behalf of Mountain View Electric Association, Inc.
|
5/10/2022 3:33:36 PM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by UDS Admin Staff on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
5/10/2022 3:33:35 PM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Rae Carlson on behalf of Colorado Springs Public Works
|
5/10/2022 3:33:21 PM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Meggan Herington on behalf of Colorado Springs Planning & Community Development
|
5/10/2022 3:33:13 PM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Clara Lucero on behalf of CIG Colorado Interstate Gas
|
5/10/2022 3:33:12 PM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Joe Valdez on behalf of Black Hills Energy-Aquila
|
5/10/2022 3:33:08 PM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
5/10/2022 3:33:07 PM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Joseph Martinez on behalf of US Army Corps of Engineers-Pueblo
|
5/10/2022 3:33:05 PM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
5/10/2022 3:33:03 PM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Jennifer Irvine on behalf of EPC Public Works, County Engineer
|
5/10/2022 3:33:02 PM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Kari Parsons on behalf of PCD Project Manager
|
5/10/2022 3:33:01 PM
|
Request for Review Comments email sent for Project CDR Sterling Ranch Road bridge Sandcreek Channel for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
5/10/2022 11:56:02 AM
|
Fees paid: 5/10/2022 (Receipt: 1006292)
|
5/9/2022 7:52:48 AM
|
Payment Request sent: 5/9/2022
|
5/9/2022 7:52:39 AM
|
File # Assigned: CDR226
|
5/9/2022 7:52:13 AM
|
Submission Triaged
|
5/6/2022 11:16:16 AM
|
Submission received from Applicant
|
4/21/2022 3:59:08 PM
|
Submission request sent to Applicant
|
4/21/2022 3:58:57 PM
|
Set Applicant to Classic Consulting Engineers & Surveyors, LLC
|
4/5/2022 4:15:38 PM
|
Submission request sent to Applicant
|
12/15/2021 8:20:00 AM
|
Submission request sent to Applicant
|
12/6/2021 8:59:05 PM
|
Submission request sent to Applicant
|
12/6/2021 8:58:45 PM
|
Submission Triaged
|
12/6/2021 5:32:17 PM
|
Submission received from Applicant
|
3/19/2021 12:47:06 PM
|
Submission request sent to Applicant
|
3/19/2021 12:44:31 PM
|
Project Manager Assigned: Kari Parsons
|
3/19/2021 12:44:31 PM
|
Project Created
|