Project Review Comments
- Project Name
- Rockytop Campground Site Development Plan
- Description
- VA185 related file
- Location
- Parcels
- 8309200011 8309200011
- Applicant
-
G&D enterprises
Nina Ruiz ( nina.ruiz@vertexcos.com )
(719) 433-2018 Nina Ruiz ( nina.ruiz@vertexcos.com )
(719) 433-2018 - EA Number
- EA18250
- File Number
- PPR2140
- Project Manager
- Ashlyn Mathy
- Status
- Active
- Created
- 3/2/2021 6:49:04 PM
View: Project Documents
Agency | Comment | ||
---|---|---|---|
Colorado Department of Transportation - Pueblo Office
3/14/2023 9:20:29 AM |
CDOT Access: A CDOT Access Permit is required for this development. CDOT has been in communication with the developer over the years of this project and to date a CDOT Access Application has not been received for this development and the accesses, existing of proposed. Roadway safety improvements are going to be required of this development for continued safe access for the Rockytop Hotel/RV Camp Grounds use. The development is in use of a pioneered roadway and use will be reconfigured with future acceleration / deceleration lanes along SH24G. Access allowance to and from this pioneered roadway is not prohibited within CDOT Right of Way. CDOT Hydraulics: Plan Comments - Provide outlet protection for the 18” CMP outlet pipe and any other pipes discharging to CDOT ROW. Provide velocity calculations for those pipes and outlet protection. Report Comments - It appears that runoff discharges directly onto CDOT ROW. Is there any ponding onto CDOT ROW at the proposed outfalls? Spread calculations are not included and this is not discussed in the report text. How will spillway flows be captured? It appears that overtopping events will discharge directly onto CDOT ROW. If capacity in the ditch or culvert is provided for the overtopping events, it is not indicated in the report text CDOT Traffic: A Traffic Impact Memo is being requested for potential impacts to the surrounding roadways and WB access approach. Thank you, Arthur Gonzales - Access Manager |
3/14/2023 9:20:29 AM | |
PCD Project Manager
1/18/2023 8:12:19 PM |
No further comments on the following documents: - Letter of Intent - Site Development Plan - Lighting Plan - Sign Plan Please ensure that an up to date title commitment is provided prior to project approval. The title commitment is outdated. All remaining comments have been uploaded by PCD Engineering & Stormwater. |
1/18/2023 8:12:19 PM | |
View |
EPC Stormwater Review
1/18/2023 3:21:22 PM |
SWMP | 1/18/2023 3:21:22 PM |
View |
EPC Stormwater Review
1/18/2023 3:20:59 PM |
SWMP Checklist | 1/18/2023 3:20:59 PM |
View |
EPC Stormwater Review
1/18/2023 3:20:36 PM |
Private Detention Basin / Stormwater Quality BMP Maintenance Agreement | 1/18/2023 3:20:36 PM |
View |
EPC Stormwater Review
1/18/2023 3:19:34 PM |
PBMP Applicability Form | 1/18/2023 3:19:34 PM |
View |
EPC Stormwater Review
1/18/2023 3:19:10 PM |
GEC Checklist | 1/18/2023 3:19:10 PM |
View |
PCD Engineering Division
1/18/2023 5:30:15 PM |
FAE redlines | 1/18/2023 5:30:15 PM |
View |
PCD Engineering Division
1/18/2023 5:29:26 PM |
GEC Plan redlines | 1/18/2023 5:29:26 PM |
View |
PCD Engineering Division
1/18/2023 5:28:26 PM |
Drainage Report redlines | 1/18/2023 5:28:26 PM |
PCD Engineering Division
1/18/2023 5:31:13 PM |
Review 5 comments on the following documents will be uploaded: -Drainage Report -GEC plan -FAE Please see comments from the stormwater engineer and be sure to address CDOT's previous comments. reviewed by: Daniel Torres danieltorres@elpasoco.com |
1/18/2023 5:31:13 PM | |
County Attorney - Development Review
1/12/2023 5:21:44 PM |
Comments from 12/8/22 have not yet been addressed. | 1/12/2023 5:21:44 PM | |
EPC Stormwater Review
1/18/2023 3:17:36 PM |
Review 5: EPC DPW Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - Drainage Report....(to be uploaded by PM with PCD comments - FAE........................(to be uploaded by PM with PCD comments) - GEC Plan...............(to be uploaded by PM with PCD comments) - GEC Checklist - PBMP Applicability Form - Private Detention Basin / Stormwater Quality BMP Maintenance Agreement - SWMP Checklist - SWMP Unresolved comment from Review #4: Please provide the following documents upon resubmittal now that it is clear that an ESQCP is required since it was recently documented in the drainage report that the limits of disturbance will exceed 1ac. You will have to ask the planner to send an upload request. - ESQCP, which can be downloaded here: https://publicworks.elpasoco.com/stormwater/ EPC DPW Stormwater comments have been resolved on the following documents: - MS4 Post Construction Form Reviewed by: Glenn Reese, P.E. Stormwater Engineer III glennreese@elpasoco.com |
1/18/2023 3:17:36 PM | |
View |
PCD Project Manager
12/12/2022 11:23:02 AM |
Drainage Report - Final_V3 redlines | 12/12/2022 11:23:02 AM |
View |
PCD Project Manager
12/12/2022 11:22:36 AM |
Grading & Erosion Control Plan_V3 redlines | 12/12/2022 11:22:36 AM |
View |
PCD Project Manager
12/12/2022 11:22:04 AM |
Site Development Plan_V3 redlnes | 12/12/2022 11:22:04 AM |
View |
Colorado Parks and Wildlife
12/10/2022 1:45:00 PM |
12/10/2022 1:45:00 PM | |
PCD Engineering Division
12/8/2022 4:34:10 PM |
Review 4 comments on the following documents will be uploaded by the project manager: -Drainage Report Please see comments from the stormwater engineer and be sure to address CDOT's previous comments. Due to the amount of unresolved comments, staff recommends that a response document be provided by the applicant/consultant showing where/how they have addressed the review comments. reviewed by: Daniel Torres danieltorres@elpasoco.com |
12/8/2022 4:34:10 PM | |
View |
County Attorney - Development Review
12/8/2022 12:45:41 PM |
Proposed edits to Detention Maintenance Agreement attached. | 12/8/2022 12:45:41 PM |
Pikes Peak Regional Building Department
12/8/2022 9:39:13 AM |
No further comment. Becky Allen Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org |
12/8/2022 9:39:13 AM | |
View |
EPC Stormwater Review
12/6/2022 4:49:57 PM |
PBMP Applicability Form_v4 | 12/6/2022 4:49:57 PM |
View |
EPC Stormwater Review
12/6/2022 4:49:39 PM |
MS4 Post Construction Form | 12/6/2022 4:49:39 PM |
View |
EPC Stormwater Review
12/6/2022 4:49:06 PM |
GEC Checklist | 12/6/2022 4:49:06 PM |
EPC Stormwater Review
12/6/2022 4:50:29 PM |
Review 4: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - Drainage Report....(to be uploaded by PM with PCD comments - GEC Plan...............(to be uploaded by PM with PCD comments) - GEC Checklist - MS4 Post Construction Form - PBMP Applicability Form Please provide the following documents upon resubmittal now that it is clear that an ESQCP is required since it was recently documented in the drainage report that the limits of disturbance will exceed 1ac. You will have to ask the planner to send an upload request. - ESQCP - SWMP Checklist - SWMP Download the first two documents here: https://publicworks.elpasoco.com/stormwater/ Reviewed by: Glenn Reese, P.E. Stormwater Engineer II glennreese@elpasoco.com |
12/6/2022 4:50:29 PM | |
911 Authority - El Paso/Teller County
11/23/2022 8:19:24 AM |
No action for E911 on this submittal. Thank you. Justin |
11/23/2022 8:19:24 AM | |
Mountain View Electric Association, Inc.
11/23/2022 8:12:10 AM |
This is not within the MVEA service territory | 11/23/2022 8:12:10 AM | |
View |
PCD Project Manager
6/22/2022 4:38:46 PM |
Site Development Plan_V2 REDLINES | 6/22/2022 4:38:46 PM |
View |
PCD Project Manager
6/22/2022 4:38:26 PM |
PPR2140- Site Development Plan LOI Checklist MARKUP | 6/22/2022 4:38:26 PM |
View |
PCD Project Manager
6/22/2022 4:38:01 PM |
PPR2140- Site Development Plan Checklist MARKUPS | 6/22/2022 4:38:01 PM |
View |
PCD Project Manager
6/22/2022 4:37:30 PM |
Lighting Plan_V2 REDLINES | 6/22/2022 4:37:30 PM |
View |
PCD Project Manager
6/22/2022 4:37:09 PM |
Letter of Intent_V1 REDLINES | 6/22/2022 4:37:09 PM |
View |
PCD Project Manager
6/22/2022 4:36:44 PM |
Grading and Erosion Control Plan_V1 REDLINES | 6/22/2022 4:36:44 PM |
View |
PCD Project Manager
6/22/2022 4:36:03 PM |
Financial Assurance Forms_V1 REDLINES | 6/22/2022 4:36:03 PM |
View |
PCD Project Manager
6/22/2022 4:35:40 PM |
Drainage Report Final_V1 REDLINES | 6/22/2022 4:35:40 PM |
PCD Engineering Division
6/22/2022 9:51:31 AM |
Review 3 comments on the following documents will be uploaded by the project manager: -GEC Plan -Drainage Report -FAE: Please revise the FAE form to include the proposed sand filter basins. Please submit a maintenance agreement and O&M for the proposed sand filter basins. reviewed by: Daniel Torres danieltorres@elpasoco.com |
6/22/2022 9:51:31 AM | |
View |
EPC Stormwater Review
6/21/2022 11:22:16 AM |
PBMP Applicability Form | 6/21/2022 11:22:16 AM |
EPC Stormwater Review
6/21/2022 11:21:45 AM |
Review 3: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - Drainage Report....(to be uploaded by PM with PCD comments - GEC Plan...............(to be uploaded by PM with PCD comments) - PBMP Applicability Form Please provide the following documents upon resubmittal for the Sand Filter Basins: - MS4 Post Construction Form - O&M Manual - Private Detention Basin / Stormwater Quality BMP Maintenance Agreement Reviewed by: Glenn Reese, P.E. Stormwater Engineer II glennreese@elpasoco.com |
6/21/2022 11:21:45 AM | |
View |
PCD Project Manager
2/23/2022 5:27:54 PM |
Please see redline comments on Landscape Plan | 2/23/2022 5:27:54 PM |
View |
PCD Project Manager
2/23/2022 5:27:31 PM |
Please see redline comments on LOI | 2/23/2022 5:27:31 PM |
View |
PCD Project Manager
2/23/2022 5:26:44 PM |
Please see redline comments on SDP | 2/23/2022 5:26:44 PM |
View |
PCD Project Manager
2/23/2022 5:26:20 PM |
Please see redline comments on PBMP Form | 2/23/2022 5:26:20 PM |
View |
PCD Project Manager
2/23/2022 5:25:59 PM |
Please see redline comments on GEC Plan | 2/23/2022 5:25:59 PM |
View |
PCD Project Manager
2/23/2022 5:25:36 PM |
Please see redline comments on Drainage Report | 2/23/2022 5:25:36 PM |
PCD Project Manager
2/17/2022 7:11:59 AM |
Comments to be uploaded once PCD Engineering has completed their review. | 2/17/2022 7:11:59 AM | |
View |
EPC Stormwater Review
2/18/2022 9:55:30 AM |
PBMP Applicability Form | 2/18/2022 9:55:30 AM |
PCD Engineering Division
2/16/2022 10:21:50 PM |
Review 2 comments on the following documents will be uploaded by the project manager: -Site Development Plan -GEC Plan -Drainage Report -PBMP Applicability Form No additional comments on the following documents: -Letter of intent -FAE reviewed by: Daniel Torres danieltorres@elpasoco.com |
2/16/2022 10:21:50 PM | |
County Attorney - Development Review
2/8/2022 12:03:10 PM |
No further comments from County Attorney's Office at this time. | 2/8/2022 12:03:10 PM | |
EPC Stormwater Review
2/18/2022 9:54:58 AM |
Review 2: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - Drainage Report....(to be uploaded by PM with PCD comments - GEC Plan...............(to be uploaded by PM with PCD comments) - PBMP Applicability Form EPC Stormwater comments have been resolved on the following documents: - FAE Reviewed by: Glenn Reese, P.E. Stormwater Engineer II glennreese@elpasoco.com |
2/18/2022 9:54:58 AM | |
View |
PCD Project Manager
10/1/2021 10:31:08 AM |
Please see redline comments for Title Commitment | 10/1/2021 10:31:08 AM |
View |
PCD Project Manager
10/1/2021 10:30:29 AM |
Please see redline comments for Site Development Plan | 10/1/2021 10:30:29 AM |
View |
PCD Project Manager
10/1/2021 10:29:59 AM |
Please see redline comments for Sign Plan | 10/1/2021 10:29:59 AM |
View |
PCD Project Manager
10/1/2021 10:29:05 AM |
Please see redline comments for PBMP Form | 10/1/2021 10:29:05 AM |
View |
PCD Project Manager
10/1/2021 10:28:36 AM |
Please see redline comments for LOI | 10/1/2021 10:28:36 AM |
View |
PCD Project Manager
10/1/2021 10:28:11 AM |
Please see redline comments for Landscape Plan | 10/1/2021 10:28:11 AM |
View |
PCD Project Manager
10/1/2021 10:27:36 AM |
Please see redline comments for GEC Plan | 10/1/2021 10:27:36 AM |
View |
PCD Project Manager
10/1/2021 10:27:10 AM |
Please see redline comments for FAE | 10/1/2021 10:27:10 AM |
View |
PCD Project Manager
10/1/2021 10:26:42 AM |
Please see redline comments for Drainage Report | 10/1/2021 10:26:42 AM |
View |
PCD Project Manager
10/1/2021 10:26:10 AM |
Please see redline comments for DMA | 10/1/2021 10:26:10 AM |
View |
EPC Stormwater Review
9/30/2021 7:33:14 AM |
PBMP Applicability Form_v1 | 9/30/2021 7:33:14 AM |
EPC Stormwater Review
9/30/2021 7:30:48 AM |
Review 1: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - Drainage Report...(to be uploaded by PM with PCD comments) - FAE.......................(to be uploaded by PM with PCD comments) - GEC Plan...............(to be uploaded by PM with PCD comments) - PBMP Applicability Form Reviewed by: Glenn Reese, P.E. Stormwater Engineer II glennreese@elpasoco.com |
9/30/2021 7:30:48 AM | |
PCD Project Manager
9/30/2021 7:24:42 AM |
Comments to be uploaded once PCD Engineering has completed their review | 9/30/2021 7:24:42 AM | |
PCD Engineering Division
9/29/2021 5:09:52 PM |
Review 1 comments on the following documents will be uploaded by the project manager: -Site Development Plan -Letter of Intent -GEC Plan -Drainage Report -Detention Maintenance agreement -FAE -PBMP Applicability Form Due to nature and quantity of comments provided, additional comments may be provided with the resubmittal. reviewed by: Daniel Torres danieltorres@elpasoco.com |
9/29/2021 5:09:52 PM | |
View |
Colorado Department of Transportation - Pueblo Office
9/28/2021 4:36:39 PM |
9/28/2021 4:36:39 PM | |
County Attorney - Development Review
9/20/2021 11:39:37 AM |
Please confirm with the EPC Planner whether a Detention Maintenance Agreement is required. | 9/20/2021 11:39:37 AM | |
Pikes Peak Regional Building Department
9/15/2021 2:32:17 PM |
1. Addresses assigned for the two new buildings are as follows: greenhouse 7133 Lucky 4 Road and the new laundry/restroom building will be 7145 Lucky 4 Road. Please submit plans for these buildings under these addresses. 2. If the retaining wall is over 4’ in height an address will need to be assigned and a permit pulled for the retaining wall. When the retaining wall is proposed to be added to the site, please contact us regarding an address if over 4’. 3. No further comments. Becky Allen Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org |
9/15/2021 2:32:17 PM | |
911 Authority - El Paso/Teller County
9/7/2021 8:52:43 AM |
No new street names requested on this submittal. No action for E911. Thank you. Justin. |
9/7/2021 8:52:43 AM | |
View |
Colorado Parks and Wildlife
9/3/2021 10:49:23 AM |
9/3/2021 10:49:23 AM | |
Mountain View Electric Association, Inc.
9/1/2021 11:25:41 AM |
This is not within the MVEA service territory | 9/1/2021 11:25:41 AM |