PCD Engineering Division
9/3/2021 2:40:33 PM |
The engineering documents have been reviewed and are ready for approval by the ECM Administrator. You will be notified when the approved/accepted documents are uploaded to EDARP. -- Jeff Rice - 719-520-7877 |
9/3/2021 2:40:33 PM | |
County Attorney - Development Review
9/2/2021 1:08:55 PM |
No further comments. | 9/2/2021 1:08:55 PM | |
View |
Parks Advisory Board
9/1/2021 8:01:19 AM |
See final administrative Parks comments attached. This application was endorsed by the Park Advisory Board in Jan. 2021. Thanks, Greg |
9/1/2021 8:01:19 AM |
PCD Project Manager
8/25/2021 12:41:48 PM |
Please correct the minor comments on the plat and upload revised PDF for final view before printing Mylar. Staff will draft the Administrative resolution for the Directors approval this week. Please set up an appt w/ staff to record and the PUD and plat and the associated documents. Please note the CAO must sign off on all contracts , deeds prior to the plat recording date. | 8/25/2021 12:41:48 PM | |
View |
PCD Engineering Division
8/25/2021 12:31:49 PM |
(Plat redlines summary) | 8/25/2021 12:31:49 PM |
View |
PCD Engineering Division
8/25/2021 12:30:45 PM |
(Plat redlines) | 8/25/2021 12:30:45 PM |
View |
PCD Engineering Division
8/25/2021 12:30:06 PM |
See comment memo (click link at left) and redlines. A written response to all comments and redlines is required for review of the re-submittal. The following revised/signed documents need to be submitted: - Final Plat - Signed TIS - Final GEC Plan (if needed) - License agreement - ESQCP (2021 version) https://assets-publicworks.elpasoco.com/wp-content/uploads/Stormwater/2021/ESQCP-Permit.pdf -- Jeff Rice - 719-520-7877 |
8/25/2021 12:30:06 PM |
Cherokee Metro Dist
8/20/2021 9:46:30 AM |
All comments addressed in 6-23-21 review | 8/20/2021 9:46:30 AM | |
County Attorney - Development Review
8/10/2021 4:05:12 PM |
Comments from June 29 remain unaddressed. | 8/10/2021 4:05:12 PM | |
View |
PCD Engineering Division
7/13/2021 11:53:17 AM |
(Plat redlines summary) | 7/13/2021 11:53:17 AM |
View |
PCD Engineering Division
7/13/2021 11:52:54 AM |
(Plat redlines) | 7/13/2021 11:52:54 AM |
View |
PCD Engineering Division
7/13/2021 11:49:01 AM |
See comment memo (click link at left) and redlines. A written response to all comments and redlines is required for review of the re-submittal. A response to the previous comment memos was not found for this review or the previous review. The following revised/signed documents need to be submitted: - Final Plat - CDs (3 sets) - add standard County signature block to all 3 - GEC Plan - Final Grading Plan - provide standard Engineer's signature block - ESQCP -- Jeff Rice - 719-520-7877 |
7/13/2021 11:49:01 AM |
PCD Project Manager
7/1/2021 10:40:32 AM |
The FAE states "see attached" for the landscaping section, but nothing is attached.... Can you upload the FAE and the attachment? | 7/1/2021 10:40:32 AM | |
View |
PCD Project Manager
7/1/2021 10:38:08 AM |
Plat Comments- Please call 520-6306 if you have questions about the planning comments. Engineering comments will be forth coming. | 7/1/2021 10:38:08 AM |
PCD Project Manager
7/1/2021 9:57:46 AM |
Closure sheets should close each lot, plat boundary and each of the tracts. Please verify and update accordingly. | 7/1/2021 9:57:46 AM | |
PCD Project Manager
7/1/2021 9:52:35 AM |
Please prepare and submit the deeds with the exhibits for the tracts to be dedicated to the County for ROW dedication. | 7/1/2021 9:52:35 AM | |
View |
County Attorney - Development Review
6/29/2021 10:47:58 PM |
Proposed revisions to ROW License Agreement are attached. No further revisions to Detention Maintenance Agreement requested. |
6/29/2021 10:47:58 PM |
View |
County Attorney - Development Review
6/29/2021 10:00:45 PM |
Proposed revisions to SIA attached. | 6/29/2021 10:00:45 PM |
View |
Falcon Fire Protection District
6/28/2021 12:36:37 PM |
6/28/2021 12:36:37 PM | |
EPC Stormwater Review
6/7/2021 9:57:32 AM |
Per previous comment: EPC Stormwater has no further comments at this time. Thanks. | 6/7/2021 9:57:32 AM | |
View |
Cherokee Metro Dist
4/22/2021 8:22:41 AM |
Wastewater Plan Comments attached. The only comment was on sheet 7 | 4/22/2021 8:22:41 AM |
View |
Cherokee Metro Dist
4/21/2021 4:18:19 PM |
Water Constr. Plan Comments | 4/21/2021 4:18:19 PM |
View |
Cherokee Metro Dist
4/21/2021 4:17:38 PM |
Utility Plan Comments | 4/21/2021 4:17:38 PM |
PCD Administrative Notice
4/21/2021 12:45:15 PM |
Adjacent property notifications have been mailed indicating the anticipated decision date and how to provide comment. | 4/21/2021 12:45:15 PM | |
View |
PCD Engineering Division
4/19/2021 4:31:25 PM |
(2020 Drainage Fees sheet) | 4/19/2021 4:31:25 PM |
View |
PCD Engineering Division
4/19/2021 4:27:00 PM |
(Pond B MS4-SDI redlines) | 4/19/2021 4:27:00 PM |
View |
PCD Engineering Division
4/19/2021 4:26:35 PM |
(Pond A MS4-SDI redlines) | 4/19/2021 4:26:35 PM |
View |
PCD Engineering Division
4/19/2021 4:25:30 PM |
(FAE redlines) | 4/19/2021 4:25:30 PM |
View |
PCD Engineering Division
4/19/2021 4:24:54 PM |
(CDs redlines summary) | 4/19/2021 4:24:54 PM |
View |
PCD Engineering Division
4/19/2021 4:24:01 PM |
(CDs redlines) | 4/19/2021 4:24:01 PM |
View |
PCD Engineering Division
4/19/2021 4:23:15 PM |
(FGP redlines summary) | 4/19/2021 4:23:15 PM |
View |
PCD Engineering Division
4/19/2021 4:22:41 PM |
(GEC redlines summary) | 4/19/2021 4:22:41 PM |
View |
PCD Engineering Division
4/19/2021 4:21:53 PM |
(FDR redlines summary) | 4/19/2021 4:21:53 PM |
View |
PCD Engineering Division
4/19/2021 4:20:42 PM |
(plat redlines summary) | 4/19/2021 4:20:42 PM |
View |
PCD Engineering Division
4/19/2021 4:19:26 PM |
(plat redlines) | 4/19/2021 4:19:26 PM |
PCD Engineering Division
4/19/2021 4:18:29 PM |
The following revised/signed documents need to be submitted: - Final Plat - Final Drainage Report - Traffic escrow memo - CDs (3 sets) - add standard County signature block to all 3 - GEC Plan - Final Grading Plan - FAE - SDI workbooks (2) - MS4 forms(2) - ESQCP - SWMP - O&M Manual (not submitted yet) |
4/19/2021 4:18:29 PM | |
View |
PCD Engineering Division
4/19/2021 3:55:40 PM |
See comment memo and redlines. A written response to all comments and redlines is required for review of the re-submittal. A response to the previous comment memo was not found for this review. -- Jeff Rice - 719-520-7877 |
4/19/2021 3:55:40 PM |
View |
PCD Project Manager
4/15/2021 8:00:44 AM |
Plat Comments Review 2 Planning Redlines Only- Engineering comments are forthcoming (next week). If these are addressed prior to engineers review, I can swap the plat out. | 4/15/2021 8:00:44 AM |
PCD Project Manager
4/15/2021 7:58:44 AM |
Please provide the HOA docs. The applicant is proposing the HOA maintain the drainage, and private roads. The Agreements (Pond Maintenance and License) are proposed to be between the HOA and the County. We will verify the HOA has been created and CCRS are recorded by County Staff with the plat recordation or by applicant prior to Plat recording (reception number written on plat ) so the entity can sign the contracts with the County which are then recorded before the plat and their reception numbers written on the plat. If you choose to record the HOA docs please verify the provisions for maintenance and ownership of roads, tracts, detention, etc are included and provide the recorded copy. | 4/15/2021 7:58:44 AM | |
View |
County Attorney - Development Review
4/14/2021 10:13:08 PM |
Comments on Detention Maintenance Agreement attached. | 4/14/2021 10:13:08 PM |
View |
County Attorney - Development Review
4/14/2021 9:37:58 PM |
Proposed changes to SIA are attached. | 4/14/2021 9:37:58 PM |
PCD Project Manager
4/14/2021 1:14:23 PM |
Applicant did not address comment regarding the traffic fee program in LOI; verify no PID inclusion is requested with the plat. The application must be completed and sent to CAO 60 days prior to plat recording. | 4/14/2021 1:14:23 PM | |
PCD Project Manager
4/14/2021 12:20:55 PM |
When does the applicant anticipate recording the PUDSP? Please note: The PUD site specific zoning was in place at the time the BOCC resolution was recorded. | 4/14/2021 12:20:55 PM | |
EPC Stormwater Review
4/5/2021 3:36:21 PM |
Review 2: EPC Stormwater comments have been resolved on the following documents: - CD's - Drainage Report - ESQCP - FAE - GEC Plan - GEC Checklist - PBMP Applicability Form - SWMP - SWMP Checklist EPC Stormwater has no further comments at this time. Thanks. Reviewed by: Glenn Reese, P.E. Stormwater Engineer I glennreese@elpasoco.com |
4/5/2021 3:36:21 PM | |
PCD Project Manager
1/5/2021 1:07:10 PM |
This is proposed to be an administrative plat. All documents including, easements, license agreements, maintenance agreements sia, etc.. should be signed by PCD Executive Director not BoCC Chairman. | 1/5/2021 1:07:10 PM | |
View |
PCD Project Manager
1/5/2021 1:02:12 PM |
PUDSP Plan for plat preparers reference. | 1/5/2021 1:02:12 PM |
View |
PCD Project Manager
1/5/2021 1:01:26 PM |
Letter of Intent Planning Comments | 1/5/2021 1:01:26 PM |
View |
PCD Project Manager
1/5/2021 1:01:01 PM |
SIA Comments- Please get back to staff with proposed solution. | 1/5/2021 1:01:01 PM |
View |
PCD Project Manager
1/5/2021 1:00:23 PM |
FAE Planning Comments | 1/5/2021 1:00:23 PM |
View |
PCD Project Manager
1/5/2021 12:59:58 PM |
Final Plat Redlines combined. Many of the comments related to missing notes and lack of clarity on line work. | 1/5/2021 12:59:58 PM |
Colorado Springs Public Works
12/30/2020 5:24:01 PM |
The letter of intent says drainage improvements were addressed in the drainage report and a GECP was prepared by the engineer. The drainage report and GECP documents were not included in the review. City Stormwater Enterprise has no comments at this time. Joel Metzker Stormwater Enterprise City of Colorado Springs 30 S. Nevada Ave., Suite 401 Colorado Springs, CO 80903 Office: (719) 385-7719 joel.metzker@coloradosprings.gov |
12/30/2020 5:24:01 PM | |
View |
PCD Engineering Division
12/30/2020 3:12:12 PM |
(License Agreement template for private improvements and landscaping in the ROW) | 12/30/2020 3:12:12 PM |
View |
PCD Engineering Division
12/30/2020 3:11:01 PM |
(NEPE Easement Template for offsite drainage and access easements - change County to HOA) (This can also be used for public sidewalks outside the ROW.) | 12/30/2020 3:11:01 PM |
View |
PCD Engineering Division
12/30/2020 3:08:17 PM |
(Example plat notes) | 12/30/2020 3:08:17 PM |
View |
PCD Engineering Division
12/30/2020 3:07:34 PM |
(PBMP-App-Form redlines) | 12/30/2020 3:07:34 PM |
View |
PCD Engineering Division
12/30/2020 3:06:49 PM |
(ESQCP redlines) | 12/30/2020 3:06:49 PM |
View |
PCD Engineering Division
12/30/2020 3:05:46 PM |
(FAE redlines) | 12/30/2020 3:05:46 PM |
View |
PCD Engineering Division
12/30/2020 3:05:11 PM |
(Utility CDs redlines combined) | 12/30/2020 3:05:11 PM |
View |
PCD Engineering Division
12/30/2020 3:02:10 PM |
(CDs redlines summary) | 12/30/2020 3:02:10 PM |
View |
PCD Engineering Division
12/30/2020 3:01:20 PM |
(CDs redlines) | 12/30/2020 3:01:20 PM |
View |
PCD Engineering Division
12/30/2020 3:00:17 PM |
(GEC redlines summary) | 12/30/2020 3:00:17 PM |
View |
PCD Engineering Division
12/30/2020 2:59:27 PM |
(GEC redlines) | 12/30/2020 2:59:27 PM |
View |
PCD Engineering Division
12/30/2020 2:58:42 PM |
(FGP redlines summary) | 12/30/2020 2:58:42 PM |
View |
PCD Engineering Division
12/30/2020 2:58:01 PM |
(FGP redlines) | 12/30/2020 2:58:01 PM |
View |
PCD Engineering Division
12/30/2020 2:56:55 PM |
(FDR redlines summary) | 12/30/2020 2:56:55 PM |
View |
PCD Engineering Division
12/30/2020 2:56:19 PM |
(FDR redlines) | 12/30/2020 2:56:19 PM |
View |
PCD Engineering Division
12/30/2020 1:40:35 PM |
See comment letter and redlines. | 12/30/2020 1:40:35 PM |
View |
Colorado Division of Water Resources
12/28/2020 3:19:52 PM |
12/28/2020 3:19:52 PM | |
View |
EPC Health Department
12/17/2020 4:34:18 PM |
12/17/2020 4:34:18 PM | |
View |
Colorado Springs Airport Advisory Commission
12/17/2020 9:21:51 AM |
The attached land use summary with comments was reviewed and accepted at the Airport Advisory Commission meeting held on December 16, 2020. | 12/17/2020 9:21:51 AM |
Colorado Springs Public Works
12/15/2020 1:57:05 PM |
Traffic Engineering has no comments on this item. Zaker Alazzeh, P.E. Traffic Engineering Manager City of Colorado Springs (719) 385-5468 Zaker.Alazzeh@coloradosprings.gov |
12/15/2020 1:57:05 PM | |
Pikes Peak Regional Building Department
12/15/2020 10:18:30 AM |
1. The spelling of the street name Foerster Grass View was changed to Forester Grass View. Foerster Grass, come to find out is t type of grass. Is this the spelling you want? Please clarity. 2. The unique addressing that was sent to you on the last submittal needs to be on the plat as a plat note; Lots 1-24 addressed from Vanhoutte View, 25-40 addressed from Serviceberry Grove, 41-44 addressed from Fountain Grass Grove, 65-74 addressed from Fountain Grass Grove 75-88 addressed from Purple Fountain Point , 95-100 addressed from Foerster Grass View-with addresses placed on the front & rear of the home. LOTS 45-64 will be addressed from Hannah Ridge Drive, 89-94 will be addressed from Foerster Grass View-with addressed placed on the front only. 3. For assignment of addressing for lots and tracts, place addressing marker (xxx) where they are intended to be utilized. Lot marker placement to be front door. Please clarify. Standard final plat comments: 1. $10.00 per lot & tract platting fee will be due at the time of the review of the mylar (2 addresses per lot & tract). If an address is not needed on a tract then no fee applies. Check should be made out to PIKES PEAK REGIONAL BUILDING DEPARTMENT or PPRBD. Paid directly to the Enumerations Department. Mark the tract locations so that we know how much to change for each tract, please. 2. A copy of the final recorded plat is required prior to plan submittal for RESIDENTIAL. Amy@pprbd.org 3. Standard final plat comments still apply, but with RBD being closed, there are a few new changes to Enumerations review of the Mylar. Please, send a pdf of the final plat document (intended plat of record) to the Enumerations reviewer that reviewed the project. We will then check the mylar for the normal things we look at on a plat, address, street names, title block and floodplain statement. Then we will stamp off on that document with an RBD check stamp, if all is accurate. This will be our copy of record that we plan to see once the document is recorded, minus a few signatures on the main sheet. Please contact your reviewer in Enumerations for instruction on payment. Amy Vanderbeek Enumerations Plans Examiner Pikes Peak Regional Building Department O: 719-327-2930 |
12/15/2020 10:18:30 AM | |
View |
County Attorney - Development Review
12/12/2020 9:57:01 PM |
If the developer wishes to include the subdivision in Public Improvement District No. 2, please complete the attached petition in full and submit to the County Attorney's Office, along with a legal description of the subdivision in Word. (If the developer wishes to join PID No. 3, please contact the EPC Planner for the correct petition.) State law requires that legal notice of the BoCC hearing to include the property in the PID be published for three weeks. Developer is responsible for reimbursing the County Attorney's Office for the cost of publication. The inclusion hearing must be held before the plat is recorded and requires 3 weeks of published notice. The County Attorney's Office makes every attempt to schedule the inclusion hearing on the date of BoCC or administrative approval of the plat, or as close thereto as possible. The developer and County Planning are responsible to keep the County Attorney's Office informed of the anticipated plat approval date. |
12/12/2020 9:57:01 PM |
View |
County Attorney - Development Review
12/12/2020 9:54:27 PM |
Comments on and proposed changes to Detention Maintenance Agreement attached. Pursuant to paragraph 8 of the agreement, please amend the Declaration to add a provision specifically referring to the Agreement and stating that the Agreement is incorporated into the covenants and touches and concerns each and every lot in the subdivision. Also note that the name of the HOA needs to be updated in the bylaws and Declaration. |
12/12/2020 9:54:27 PM |
View |
County Attorney - Development Review
12/12/2020 9:51:48 PM |
Comments on and proposed changes to SIA attached. | 12/12/2020 9:51:48 PM |
View |
Cherokee Metro Dist
12/11/2020 4:55:24 PM |
12/11/2020 4:55:24 PM | |
View |
Cherokee Metro Dist
12/11/2020 4:55:02 PM |
12/11/2020 4:55:02 PM | |
View |
Cherokee Metro Dist
12/11/2020 4:54:15 PM |
12/11/2020 4:54:15 PM | |
View |
Cherokee Metro Dist
12/11/2020 4:53:32 PM |
12/11/2020 4:53:32 PM | |
View |
Cherokee Metro Dist
12/11/2020 4:52:58 PM |
12/11/2020 4:52:58 PM | |
View |
Cherokee Metro Dist
12/11/2020 4:51:28 PM |
12/11/2020 4:51:28 PM | |
View |
Cherokee Metro Dist
12/11/2020 4:50:47 PM |
12/11/2020 4:50:47 PM | |
Cherokee Metro Dist
12/11/2020 4:43:07 PM |
Review comments are on the uploaded set of drawings (3 sets). Comments need to be addressed before Cherokee approves this development. The Urban Collections at Palmer Village is included in Cherokee Metro District's service area and Cherokee has adequate water and wastewater treatment capacity to serve this customer. |
12/11/2020 4:43:07 PM | |
View |
EPC Stormwater Review
12/10/2020 1:24:20 PM |
SWMP Checklist_v1 | 12/10/2020 1:24:20 PM |
View |
EPC Stormwater Review
12/10/2020 1:23:11 PM |
SWMP_v1 | 12/10/2020 1:23:11 PM |
View |
EPC Stormwater Review
12/10/2020 1:22:18 PM |
PBMP Form_v1 | 12/10/2020 1:22:18 PM |
View |
EPC Stormwater Review
12/10/2020 1:21:58 PM |
GEC Checklist_v1 | 12/10/2020 1:21:58 PM |
EPC Stormwater Review
12/10/2020 1:21:15 PM |
Review 1: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents: - CD's.......................(to be uploaded by PM with PCD comments) - Drainage Report....(to be uploaded by PM with PCD comments) - ESQCP...................(to be uploaded by PM with PCD comments) - FAE........................(to be uploaded by PM with PCD comments) - GEC Plan...............(to be uploaded by PM with PCD comments) - GEC Checklist - PBMP Applicability Form - SWMP - SWMP Checklist Reviewed by: Glenn Reese, P.E. Stormwater Engineer I glennreese@elpasoco.com |
12/10/2020 1:21:15 PM | |
Colorado Springs Public Works
12/10/2020 11:05:12 AM |
Engineering Development Review Division has no comments. Patrick V. Morris Civil Engineer II Public Works/Engineering Development Review City of Colorado Springs 30 S. Nevada Ave., Suite 401 Colorado Springs, CO 80903 tel: 719-385-5075 Main: 719-385-5979 patrick.morris@coloradosprings.gov |
12/10/2020 11:05:12 AM | |
911 Authority - El Paso/Teller County
12/9/2020 8:55:40 AM |
All street names previously approved and reserved. No other action for E911. Thank you Justin |
12/9/2020 8:55:40 AM | |
View |
EPC Parks Department
12/7/2020 12:52:43 PM |
See preliminary Parks comments attached. | 12/7/2020 12:52:43 PM |
View |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
12/4/2020 4:16:17 PM |
Hey Kari, Attached is the review memo for the subject application. Let me know if you need anything further from me. Thanks, Ryne Solberg, rsolberg@csu.org |
12/4/2020 4:16:17 PM |
View |
EPC Environmental Services
12/2/2020 2:32:22 PM |
12/2/2020 2:32:22 PM | |
Upper Black Squirrel Creek GWMD
12/1/2020 2:04:07 PM |
The Upper Black Squirrel Creek GWMD does not have any comments at this time but respectfully reserves the right to comment in the future. | 12/1/2020 2:04:07 PM | |
View |
Mountain View Electric Association, Inc.
12/1/2020 10:51:42 AM |
12/1/2020 10:51:42 AM | |
RBD Floodplain
11/30/2020 7:31:33 AM |
note 4 : DFIRM suffix is G not F, and date is Dec 7 2018 not 1997 | 11/30/2020 7:31:33 AM |