9/22/2021 8:18:50 AM
|
Project Closed
|
9/22/2021 8:18:50 AM
|
Project Approved: 9/22/2021
|
9/22/2021 8:17:53 AM
|
Submission Triaged
|
9/22/2021 8:16:29 AM
|
Submission received from Applicant
|
9/3/2021 2:40:52 PM
|
Request for Review Comments returned by PCD Engineering Division
|
9/2/2021 1:09:05 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
9/1/2021 8:01:47 AM
|
Request for Review Comments returned by Parks Advisory Board
|
8/26/2021 3:55:17 PM
|
Submission request sent to Applicant
|
8/26/2021 11:50:02 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
8/26/2021 11:46:41 AM
|
Submission Triaged
|
8/26/2021 11:37:51 AM
|
Submission received from Applicant
|
8/25/2021 4:34:21 PM
|
Submission request sent to Applicant
|
8/25/2021 4:33:54 PM
|
Request for Review Comments returned by PCD Project Manager
|
8/25/2021 4:33:26 PM
|
Request for Review Comments email resent for Project Urban Collection at Palmer Village for review by Kari Parsons on behalf of PCD Project Manager
|
8/25/2021 1:39:06 PM
|
Submission request sent to Applicant
|
8/25/2021 1:36:51 PM
|
Submission request sent to Applicant
|
8/25/2021 1:29:15 PM
|
Request for Review Comments returned by PCD Project Manager
|
8/25/2021 1:08:43 PM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by on behalf of Parks Advisory Board
|
8/25/2021 12:31:59 PM
|
Request for Review Comments returned by PCD Engineering Division
|
8/20/2021 9:46:40 AM
|
Request for Review Comments returned by Cherokee Metro Dist
|
8/19/2021 9:44:58 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Lori Seago on behalf of County Attorney - Development Review
|
8/19/2021 9:44:01 AM
|
Submission Triaged
|
8/19/2021 9:30:04 AM
|
Submission received from Applicant
|
8/19/2021 9:25:53 AM
|
Submission request sent to Applicant
|
8/10/2021 4:05:23 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
7/28/2021 4:58:36 PM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Jeff Munger on behalf of Cherokee Metro Dist
|
7/28/2021 4:49:03 PM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Lori Seago on behalf of County Attorney - Development Review
|
7/28/2021 4:48:08 PM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Lori Seago on behalf of County Attorney - Development Review
|
7/28/2021 4:48:06 PM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Kari Parsons on behalf of PCD Project Manager
|
7/28/2021 4:48:00 PM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
7/28/2021 4:46:30 PM
|
Submission Triaged
|
7/28/2021 4:38:00 PM
|
Submission received from Applicant
|
7/15/2021 8:45:18 AM
|
Submission request sent to Applicant
|
7/13/2021 12:04:13 PM
|
Submission request sent to Applicant
|
7/13/2021 11:53:32 AM
|
Request for Review Comments returned by PCD Engineering Division
|
7/1/2021 12:10:11 PM
|
Request for Review Comments returned by PCD Project Manager
|
6/30/2021 6:46:20 AM
|
Submission request sent to Applicant
|
6/29/2021 10:48:09 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
6/28/2021 12:36:51 PM
|
Request for Review Comments returned by Falcon Fire Protection District
|
6/23/2021 2:59:40 PM
|
Request for Review Comments returned by Cherokee Metro Dist
|
6/17/2021 8:57:43 AM
|
Request for Review Comments returned by Colorado Springs Planning & Community Development
|
6/8/2021 9:11:11 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by deric clemons on behalf of Natural Resources Conservation Service (Federal Agency)
|
6/8/2021 9:11:08 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Roger Austin on behalf of Mountain Metro Transit (City of COS)
|
6/8/2021 9:11:06 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Melissa Andrews on behalf of Falcon School District 49
|
6/8/2021 9:11:04 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Fire Chief Trent Harwig on behalf of Falcon Fire Protection District
|
6/8/2021 9:11:02 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Peter Susemilh on behalf of Constitution Heights Metro
|
6/8/2021 9:11:00 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Terry Johns on behalf of Colorado Springs SD 11
|
6/8/2021 9:10:58 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Meggan Herington on behalf of Colorado Springs Planning & Community Development
|
6/8/2021 9:10:44 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Jeff Munger on behalf of Cherokee Metro Dist
|
6/8/2021 9:10:42 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Commander John Padgett on behalf of EPC Sheriff's Department
|
6/7/2021 9:57:56 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
6/4/2021 7:14:48 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
6/4/2021 7:14:44 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Lori Seago on behalf of County Attorney - Development Review
|
6/4/2021 7:14:42 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Kari Parsons on behalf of PCD Project Manager
|
6/4/2021 7:14:38 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
6/4/2021 7:11:30 AM
|
Submission Triaged
|
6/3/2021 4:33:58 PM
|
Submission received from Applicant
|
4/22/2021 8:24:11 AM
|
Request for Review Comments returned by Cherokee Metro Dist
|
4/22/2021 7:27:27 AM
|
Request for Review Comments email resent for Project Urban Collection at Palmer Village for review by Jeff Munger on behalf of Cherokee Metro Dist
|
4/21/2021 4:19:07 PM
|
Request for Review Comments returned by Cherokee Metro Dist
|
4/21/2021 1:06:34 PM
|
Request for Review Comments returned by PCD Administrative Notice
|
4/21/2021 12:59:35 PM
|
Request for Review Comments email resent for Project Urban Collection at Palmer Village for review by Elena Krebs on behalf of PCD Administrative Notice
|
4/21/2021 12:45:26 PM
|
Request for Review Comments returned by PCD Administrative Notice
|
4/20/2021 7:42:07 AM
|
Submission request sent to Applicant
|
4/19/2021 4:31:54 PM
|
Request for Review Comments returned by PCD Engineering Division
|
4/15/2021 12:13:38 PM
|
Submission request sent to Applicant
|
4/15/2021 8:00:58 AM
|
Request for Review Comments returned by PCD Project Manager
|
4/14/2021 10:24:04 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
4/14/2021 12:38:39 PM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Elena Krebs on behalf of PCD Administrative Notice
|
4/14/2021 12:33:33 PM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Jeff Munger on behalf of Cherokee Metro Dist
|
4/13/2021 1:15:30 PM
|
Request for Review Comments returned by EPC Stormwater Review
|
3/17/2021 7:05:38 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
3/17/2021 7:05:34 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Lori Seago on behalf of County Attorney - Development Review
|
3/17/2021 7:05:32 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Kari Parsons on behalf of PCD Project Manager
|
3/17/2021 7:05:28 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
3/17/2021 7:01:45 AM
|
Submission Triaged
|
3/16/2021 9:14:56 PM
|
Submission received from Applicant
|
1/5/2021 1:13:26 PM
|
Submission request sent to Applicant
|
1/5/2021 1:12:02 PM
|
Submission request sent to Applicant
|
1/5/2021 1:07:33 PM
|
Request for Review Comments returned by PCD Project Manager
|
12/31/2020 9:06:15 AM
|
Request for Review Comments returned by Colorado Springs Public Works
|
12/30/2020 3:13:34 PM
|
Request for Review Comments returned by PCD Engineering Division
|
12/28/2020 3:20:17 PM
|
Request for Review Comments returned by Colorado Division of Water Resources
|
12/17/2020 4:34:35 PM
|
Request for Review Comments returned by EPC Health Department
|
12/17/2020 9:22:10 AM
|
Request for Review Comments returned by Colorado Springs Airport Advisory Commission
|
12/16/2020 8:44:57 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Kari Parsons on behalf of PCD Project Manager
|
12/16/2020 8:44:53 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
12/16/2020 8:23:40 AM
|
Request for Review Comments returned by EPC Stormwater Review
|
12/15/2020 10:19:04 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
12/12/2020 10:01:06 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
12/11/2020 4:55:53 PM
|
Request for Review Comments returned by Cherokee Metro Dist
|
12/9/2020 8:55:50 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
12/7/2020 12:52:55 PM
|
Request for Review Comments returned by EPC Parks Department
|
12/4/2020 4:16:25 PM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
12/3/2020 8:44:00 AM
|
Project Manager Assigned: Kari Parsons
|
12/2/2020 2:32:52 PM
|
Request for Review Comments returned by EPC Environmental Services
|
12/1/2020 2:04:17 PM
|
Request for Review Comments returned by Upper Black Squirrel Creek GWMD
|
12/1/2020 10:51:51 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
11/30/2020 7:31:55 AM
|
Request for Review Comments returned by RBD Floodplain
|
11/25/2020 11:53:39 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by deric clemons on behalf of Natural Resources Conservation Service (Federal Agency)
|
11/25/2020 11:53:36 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Administrative Assistant Cathy Hansen-Lee on behalf of Mountain View Electric Association, Inc.
|
11/25/2020 11:53:34 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Roger Austin on behalf of Mountain Metro Transit (City of COS)
|
11/25/2020 11:53:32 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Melissa Andrews on behalf of Falcon School District 49
|
11/25/2020 11:53:30 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Fire Chief Trent Harwig on behalf of Falcon Fire Protection District
|
11/25/2020 11:53:28 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Peter Susemilh on behalf of Constitution Heights Metro
|
11/25/2020 11:53:26 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by UDS Admin Staff on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
11/25/2020 11:53:24 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Terry Johns on behalf of Colorado Springs SD 11
|
11/25/2020 11:53:22 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Shirley Applegate on behalf of Colorado Springs Public Works
|
11/25/2020 11:53:19 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Meggan Herington on behalf of Colorado Springs Planning & Community Development
|
11/25/2020 11:53:05 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Kristine Andrews on behalf of Colorado Springs Airport Advisory Commission
|
11/25/2020 11:53:03 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Jeff Munger on behalf of Cherokee Metro Dist
|
11/25/2020 11:53:01 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Office Mgr Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
|
11/25/2020 11:52:59 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Keith Curtis on behalf of RBD Floodplain
|
11/25/2020 11:52:57 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by RBD Enumerations on behalf of Pikes Peak Regional Building Department
|
11/25/2020 11:52:55 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by GIS Technician Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
11/25/2020 11:52:53 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Joanna Williams on behalf of Colorado Division of Water Resources
|
11/25/2020 11:52:51 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Stormwater Manager Steve Jacobsen on behalf of EPC Stormwater Review
|
11/25/2020 11:52:45 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Commander John Padgett on behalf of EPC Sheriff's Department
|
11/25/2020 11:52:42 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by on behalf of EPC Parks Department
|
11/25/2020 11:52:40 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Catherine McGarvy on behalf of EPC Health Department
|
11/25/2020 11:52:33 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Kathy Andrew on behalf of EPC Environmental Services
|
11/25/2020 11:52:31 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Lori Seago on behalf of County Attorney - Development Review
|
11/25/2020 11:52:28 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Rad Dickson on behalf of PCD Project Manager
|
11/25/2020 11:52:26 AM
|
Request for Review Comments email sent for Project Urban Collection at Palmer Village for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
|
11/25/2020 10:01:27 AM
|
Fees paid: 11/25/2020 (Receipt: 1003603)
|
11/20/2020 8:23:18 AM
|
Payment Request sent: 11/20/2020
|
11/20/2020 8:23:09 AM
|
Submission Triaged
|
11/20/2020 8:21:26 AM
|
Submission received from Applicant
|
11/20/2020 7:47:39 AM
|
File # Assigned: SF2028
|
11/20/2020 7:47:18 AM
|
Submission request sent to Applicant
|
11/20/2020 7:40:59 AM
|
Submission Triaged
|
11/18/2020 6:03:45 PM
|
Submission received from Applicant
|
11/10/2020 7:54:05 AM
|
Submission request sent to Applicant
|
10/2/2020 10:58:30 AM
|
Submission request sent to Applicant
|
10/2/2020 10:12:35 AM
|
Submission request sent to Applicant
|
10/1/2020 10:56:14 AM
|
Project Manager Assigned: Rad Dickson
|
10/1/2020 10:56:14 AM
|
Project Created
|