Project Name
Rolling Hills Ranch Filing #2
Description
Location
Parcels
4200000401 4200000401 4200000407 4200000407
Applicant
Meridian Ranch
Tom Kerby ( tom@meridianranch.com )
(719) 495-7444
Tom Kerby ( tom@meridianranch.com )
(719) 495-7444
File Number
SF2020
Project Manager
Ryan Howser
Status
Closed
Created
5/21/2020 1:54:36 PM

View: Project Documents



Review Comments (92)

Link Agency Comment
County Attorney - Development Review
2/8/2021 11:23:13 AM
No additional comments from County Attorney - Development Review at this time. 2/8/2021 11:23:13 AM
View PCD Project Manager
2/4/2021 5:01:10 PM
Please see redline comments for Adjacent owner Notification. 4 properties across Eastonville Road are not shown as being notified. Falcon School also did not receive notification. 2/4/2021 5:01:10 PM
PCD Engineering Division
2/4/2021 7:05:01 AM
The ECM administrator has approved the engineering documents on 2/4/2021. The project manager will upload approved documents onto EDARP.


reviewed by:
Daniel Torres
danieltorres@elpasoco.com
2/4/2021 7:05:01 AM
EPC Stormwater Review
2/2/2021 11:21:30 AM
Review 3. All Stormwater comments have been addressed.

Reviewed by:
Christina Furchak
Stormwater Engineer III
christinafurchak@elpasoco.com
2/2/2021 11:21:30 AM
Pikes Peak Regional Building Department
1/28/2021 11:45:33 AM
1. Two lots have the incorrect address, please change Lot 322 to 13279 and Lot 421 to 10832
2. $10.00 per lot & tract platting fee will be due at the time of the review of the mylar (2 addresses per lot & tract). If an address is not needed on a tract then no fee applies. Check should be made out to PIKES PEAK REGIONAL BUILDING DEPARTMENT or PPRBD. Paid directly to the Enumerations Department. It appears there are 244 lots and one tract, please confirm. If so the fee will be $254.00.
3. No further comments

Becky Allen
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-799-2707 W: pprbd.org E: beckya@pprbd.org
1/28/2021 11:45:33 AM
Mountain View Electric Association, Inc.
1/27/2021 8:29:03 AM
MVEA has no objection to updates of project. If there is any damage, removal, or relocation of facilities it will be at the expense of the applicant. 1/27/2021 8:29:03 AM
911 Authority - El Paso/Teller County
1/20/2021 9:18:04 AM
Street names previously approved.
No action for E911

Thank you
Justin
1/20/2021 9:18:04 AM
View EPC Health Department
1/10/2021 10:42:28 AM
1/10/2021 10:42:28 AM
View PCD Project Manager
12/23/2020 10:44:50 AM
Please see SWMP Checklist redlines 12/23/2020 10:44:50 AM
View PCD Project Manager
12/23/2020 10:44:11 AM
Please see SIA redlines per County Attorney's comments. 12/23/2020 10:44:11 AM
View PCD Project Manager
12/23/2020 10:43:18 AM
Please see SWMP redlines 12/23/2020 10:43:18 AM
View PCD Project Manager
12/23/2020 10:42:13 AM
Please see Mineral Rights redlines 12/23/2020 10:42:13 AM
View PCD Project Manager
12/23/2020 10:41:33 AM
Please see GEC Checklist redlines 12/23/2020 10:41:33 AM
View PCD Project Manager
12/23/2020 10:40:47 AM
Please see Final Plat Drawing redlines 12/23/2020 10:40:47 AM
View PCD Project Manager
12/23/2020 10:40:06 AM
Please see Funds Estimate redlines 12/23/2020 10:40:06 AM
View PCD Project Manager
12/23/2020 10:39:18 AM
Please see Final Drainage Report redlines 12/23/2020 10:39:18 AM
View PCD Project Manager
12/23/2020 10:38:31 AM
Please see Construction Drawing redlines 12/23/2020 10:38:31 AM
View PCD Project Manager
12/23/2020 10:37:25 AM
Please see Adjacent Notification redlines 12/23/2020 10:37:25 AM
View EPC Stormwater Review
12/21/2020 11:58:35 AM
SWMP_v2 12/21/2020 11:58:35 AM
View EPC Stormwater Review
12/21/2020 11:54:34 AM
SWMP Checklist_v2 12/21/2020 11:54:34 AM
View EPC Stormwater Review
12/21/2020 11:53:53 AM
GEC Checklist_v2 12/21/2020 11:53:53 AM
EPC Stormwater Review
12/21/2020 11:53:15 AM
Review 2: EPC Stormwater comments have been provided on the following uploaded documents:
- Construction Drawings (to be uploaded by PM with PCD comments)
- GEC Checklist
- SWMP Checklist
- SWMP

Reviewed by:
Christina Furchak
Stormwater Engineer III
christinafurchak@elpasoco.com
12/21/2020 11:53:15 AM
PCD Engineering Division
12/18/2020 12:15:34 PM
Review 2 comments on the following documents will be uploaded by the project manager:
-Final Drainage Report
-Traffic Study
-FAE
Please submit the deviation request for omitting the access ramp per our previous discussion.

PCD Engineering comments on the following documents have been resolved:
-Letter of intent
-Final Plat
-Construction Drawings
-PBMP Applicability form: Provide PCD file No. for this application.

Signed engineering documents may be submitted for approval by the ECM Administrator.

Reviewed by:
Daniel Torres
danieltorres@elpasoco.com
12/18/2020 12:15:34 PM
PCD Project Manager
12/17/2020 5:35:24 PM
Comments will be returned once PCD Engineering has completed their review. 12/17/2020 5:35:24 PM
View Northern EPC Coalition of Community Organizations, Inc. (NEPCO)(to also include the TLLU areas)
12/15/2020 2:46:22 PM
It appears that all our comments from the attached Oct 2020 review are still current and relevant. Please refer to it for NEPCO's input. Thank you. 12/15/2020 2:46:22 PM
Pikes Peak Regional Building Department
12/15/2020 9:23:22 AM
1. Overlook Bluff Lane was an approved street name not DRIVE. Please verify with El Paso/Teller 9-1-1 Authority that this is acceptable.
2. Addressing will be completed and sent back to you be December 23rd, 2020. Addresses to be on the plat.
3.. Previous standard comments still apply. $10.00 per lot & tract platting fee will be due at the time of the review of the mylar (2 addresses per lot & tract). If an address is not needed on a tract then no fee applies. Check should be made out to PIKES PEAK REGIONAL BUILDING DEPARTMENT or PPRBD. Paid directly to the Enumerations Department.
No further comments.


Amy Vanderbeek
Enumerations Plans Examiner
Pikes Peak Regional Building Department
O: 719-327-2930
12/15/2020 9:23:22 AM
Falcon Fire Protection District
12/15/2020 9:03:02 AM
Falcon Fire has no additional comments from those submitted on 10/1/2020. 12/15/2020 9:03:02 AM
View Colorado Division of Water Resources
12/14/2020 5:50:01 PM
1-23-2020 letter 12/14/2020 5:50:01 PM
View Colorado Division of Water Resources
12/14/2020 5:49:40 PM
It does not appear there are any changes to the water supply plan for Rolling Hills Ranch Filing 2. Please see our comments on the attached letter dated 10-22-2020. 12/14/2020 5:49:40 PM
County Attorney - Development Review
12/12/2020 9:15:38 PM
Same comment regarding SIA as Oct. 6. 12/12/2020 9:15:38 PM
View Parks Advisory Board
12/7/2020 8:24:51 AM
El Paso County Community Services / Parks Final Comments, Review #2 - Please See Attached Documents for New Additional Comments (PAB Endorsed 10/14/2020) 12/7/2020 8:24:51 AM
View EPC Parks Department
12/7/2020 8:23:05 AM
El Paso County Community Services / Parks Final Comments, Review #2 - Please See Attached Documents for New Additional Comments (PAB Endorsed 10/14/2020) 12/7/2020 8:23:05 AM
911 Authority - El Paso/Teller County
12/7/2020 7:59:59 AM
Street names previously reserved.
No action for E911.
Thank you.
Justin
12/7/2020 7:59:59 AM
County Attorney - Water
12/2/2020 3:30:33 PM
County Attorney's Office provided water sufficiency under the Preliminary Plan File No. PUDSP-19-9. Please advise if further review is necessary re: water sufficiency or whether what is on file is sufficient for this filing. Thanks so much. 12/2/2020 3:30:33 PM
View EPC Environmental Services
12/2/2020 1:15:10 PM
12/2/2020 1:15:10 PM
Mountain View Electric Association, Inc.
12/2/2020 8:01:55 AM
Thank you for the opportunity to review this project. No additional comments at this time.
Cathy
Mountain View Electric Association, Inc.
12/2/2020 8:01:55 AM
Upper Black Squirrel Creek GWMD
12/1/2020 2:23:47 PM
The Upper Black Squirrel Creek GWMD does not have any comments at this time but reserves the right to comment in the future. 12/1/2020 2:23:47 PM
View El Paso County Conservation Dist
12/1/2020 10:16:00 AM
12/1/2020 10:16:00 AM
View El Paso County Conservation Dist
12/1/2020 10:15:24 AM
12/1/2020 10:15:24 AM
View EPC Environmental Services
11/20/2020 9:38:19 AM
11/20/2020 9:38:19 AM
View EPC Health Department
11/15/2020 12:49:55 PM
11/15/2020 12:49:55 PM
View EPC Health Department
11/15/2020 12:47:09 PM
11/15/2020 12:47:09 PM
Upper Black Squirrel Creek GWMD
11/4/2020 2:36:01 PM
The Upper Black Squirrel Creek GWMD does not have any comments at this time but reserves the right to comment in the future. 11/4/2020 2:36:01 PM
Upper Black Squirrel Creek GWMD
11/4/2020 2:35:08 PM
The Upper Black Squirrel Creek GWMD does not have any comments at this time but reserves the right to comment in the future. 11/4/2020 2:35:08 PM
View PCD Project Manager
10/26/2020 2:58:21 PM
Please see attached redline comments 10/26/2020 2:58:21 PM
View PCD Project Manager
10/26/2020 11:46:23 AM
Please see redline comments 10/26/2020 11:46:23 AM
View PCD Project Manager
10/26/2020 11:45:39 AM
Please see redline comments 10/26/2020 11:45:39 AM
View PCD Project Manager
10/26/2020 11:45:03 AM
Please see redline comments 10/26/2020 11:45:03 AM
View PCD Project Manager
10/26/2020 11:43:56 AM
Please see redline comments 10/26/2020 11:43:56 AM
View PCD Project Manager
10/26/2020 11:43:13 AM
Please see redline comments 10/26/2020 11:43:13 AM
View PCD Project Manager
10/26/2020 11:42:36 AM
Please see redline comments 10/26/2020 11:42:36 AM
View PCD Project Manager
10/26/2020 11:42:01 AM
Please see redline comments 10/26/2020 11:42:01 AM
View PCD Project Manager
10/26/2020 11:41:19 AM
Please see redline comments 10/26/2020 11:41:19 AM
View PCD Project Manager
10/26/2020 11:40:44 AM
Please see redline comments 10/26/2020 11:40:44 AM
View PCD Project Manager
10/26/2020 11:40:13 AM
Please see redline comments 10/26/2020 11:40:13 AM
View PCD Project Manager
10/26/2020 11:39:10 AM
Please see redline comments 10/26/2020 11:39:10 AM
View PCD Project Manager
10/26/2020 11:38:13 AM
Please see redline comments 10/26/2020 11:38:13 AM
View PCD Project Manager
10/26/2020 11:37:26 AM
Please see redline comments 10/26/2020 11:37:26 AM
View Colorado Division of Water Resources
10/26/2020 9:01:07 AM
January 23, 2020 letter 10/26/2020 9:01:07 AM
View Colorado Division of Water Resources
10/26/2020 9:00:29 AM
10/26/2020 9:00:29 AM
View Colorado Division of Water Resources
10/26/2020 8:59:39 AM
January 23, 2020 letter 10/26/2020 8:59:39 AM
View Colorado Division of Water Resources
10/26/2020 8:58:41 AM
10/26/2020 8:58:41 AM
PCD Engineering Division
10/26/2020 10:22:21 AM
Review 1 comments on the following documents will be uploaded by the project manager:
-Letter of intent
-Final Drainage Report
-Traffic Study
-FAE
-Final Plat
-Construction Drawings
-PBMP Applicability form: Provide PCD file No. for this application.

Reviewed by:
Daniel Torres
danieltorres@elpasoco.com
10/26/2020 10:22:21 AM
View Parks Advisory Board
10/21/2020 9:52:24 AM
El Paso County Community Services / Parks Final Comments - Please See Attached Documents (PAB Endorsed 10/14/2020) 10/21/2020 9:52:24 AM
View Parks Advisory Board
10/21/2020 9:50:26 AM
El Paso County Community Services / Parks Final Comments - Please See Attached Documents (PAB Endorsed 10/14/2020) 10/21/2020 9:50:26 AM
View EPC Stormwater Review
10/14/2020 1:37:41 PM
SWMP Checklist_V1 10/14/2020 1:37:41 PM
View EPC Stormwater Review
10/14/2020 1:31:29 PM
SWMP_V1 10/14/2020 1:31:29 PM
View EPC Stormwater Review
10/14/2020 1:33:05 PM
GEC Checklist_V1 10/14/2020 1:33:05 PM
EPC Stormwater Review
10/14/2020 1:28:03 PM
Review 1: EPC Stormwater comments have been provided on the following uploaded documents:
- Construction Drawings (to be uploaded by PM with PCD comments)
- GEC Checklist
- SWMP
- SWMP Checklist

Reviewed by:
Christina Furchak
Stormwater Engineer III
christinafurchak@elpasoco.com
10/14/2020 1:28:03 PM
Northern EPC Coalition of Community Organizations, Inc. (NEPCO)(to also include the TLLU areas)
10/13/2020 2:39:01 PM
The TLLUC is no longer reviewing land use issues. If it did, it would mirror NEPCO's comments. 10/13/2020 2:39:01 PM
View Northern EPC Coalition of Community Organizations, Inc. (NEPCO)(to also include the TLLU areas)
10/13/2020 2:30:03 PM
10/13/2020 2:30:03 PM
Pikes Peak Regional Building Department
10/12/2020 2:06:09 PM
1. Please provide a large scale copy of the project all on one sheet of paper for addressing purposes.
2. Once received the addresses need to be on the plat.
3. Standard final plat comments still apply, but with RBD being closed, there are a few new changes to Enumerations review of the Mylar. Please, send a pdf of the final plat document (intended plat of record) to the Enumerations reviewer that reviewed the project. We will then check the mylar for the normal things we look at on a plat, address, street names, title block and floodplain statement. Then we will stamp off on that document with an RBD check stamp, if all is accurate. This will be our copy of record that we plan to see once the document is recorded, minus a few signatures on the main sheet. Please contact your reviewer in Enumerations for instruction on payment.
10/12/2020 2:06:09 PM
View EPC Parks Department
10/9/2020 11:53:28 AM
El Paso County Community Services / Parks Preliminary Comments - Please See Attached Documents (To be presented to the Park Advisory Board on 10/14/2020) 10/9/2020 11:53:28 AM
View EPC Parks Department
10/9/2020 11:52:20 AM
El Paso County Community Services / Parks Preliminary Comments - Please See Attached Documents (To be presented to the Park Advisory Board on 10/14/2020) 10/9/2020 11:52:20 AM
County Attorney - Development Review
10/6/2020 10:07:11 PM
Owner listed in SIA does not match owner identified in Assessor's records. Please correct if needed. 10/6/2020 10:07:11 PM
County Attorney - Development Review
10/6/2020 10:01:58 PM
This appears to be a duplicate referral to County Attorney's Office - Development Review. I have a second referral for the same application in my queue. 10/6/2020 10:01:58 PM
911 Authority - El Paso/Teller County
10/5/2020 8:32:28 AM
Street names previously approved.
No other comment for E911

Thank you
Justin
10/5/2020 8:32:28 AM
911 Authority - El Paso/Teller County
10/5/2020 8:31:43 AM
Street names previously approved.
No other comment for E911

Thank you
Justin
10/5/2020 8:31:43 AM
View Falcon Fire Protection District
10/1/2020 1:36:49 PM
10/1/2020 1:36:49 PM
View Falcon Fire Protection District
10/1/2020 1:36:21 PM
10/1/2020 1:36:21 PM
Colorado State Forest Service
9/29/2020 12:11:00 PM
The primary wildland fuel type for this proposal is grassland with scattered trees having a low wildfire hazard potential. No special fire mitigation plans or other actions are necessary for final approval by the Colorado State Forest Service. 9/29/2020 12:11:00 PM
Colorado State Forest Service
9/29/2020 12:09:44 PM
The primary wildland fuel type for this proposal is grassland with scattered trees having a low wildfire hazard potential. No special fire mitigation plans or other actions are necessary for final approval by the Colorado State Forest Service. 9/29/2020 12:09:44 PM
Falcon Fire Protection District
9/29/2020 10:01:37 AM
duplicate comment sheet for SF2020. See other sheet for comments. 9/29/2020 10:01:37 AM
View El Paso County Conservation Dist
9/29/2020 8:33:58 AM
9/29/2020 8:33:58 AM
View El Paso County Conservation Dist
9/29/2020 8:31:16 AM
9/29/2020 8:31:16 AM
View El Paso County Conservation Dist
9/29/2020 8:23:05 AM
9/29/2020 8:23:05 AM
View El Paso County Conservation Dist
9/29/2020 8:18:27 AM
9/29/2020 8:18:27 AM
View EPC Environmental Services
9/24/2020 2:04:58 PM
9/24/2020 2:04:58 PM
View Mountain View Electric Association, Inc.
9/23/2020 2:59:40 PM
9/23/2020 2:59:40 PM
View Mountain View Electric Association, Inc.
9/23/2020 2:58:48 PM
9/23/2020 2:58:48 PM
County Attorney - Water
9/23/2020 9:12:02 AM
This appears to be a duplicate submittal. 9/23/2020 9:12:02 AM
County Attorney - Water
9/23/2020 9:11:07 AM
County Attorney's Office provided water sufficiency under File No. PUDSP-19-9. Planner - Please advise if further review is necessary re: water sufficiency or whether what is on file is sufficient for this filing. Thanks so much. 9/23/2020 9:11:07 AM