View: Project Documents
Agency | Comment | ||
---|---|---|---|
PCD Project Manager
6/9/2020 11:26:26 AM |
No further comments, see engineer comments for final signatures. Before land disturbance a pre-construction meeting is required to be scheduled with Brad Walters, bradwalters@elpasoco.com, inspection fees and any collateral is due at that meeting. Prior to issuance of a Certificate of Occupancy, all landscaping, parking stripping, and other improvements are required to be installed and completed. |
6/9/2020 11:26:26 AM | |
PCD Engineering Division
6/9/2020 9:42:10 AM |
Review 5: No additional comments. Submit the following documents with the appropriate signatures: - ESQCP - Pond Maintenance Agreement - Grading and Erosion Control Plan. (Make sure all sheets have the PE Stamp with signature and date of signature) Comments resolved on the following documents: - Traffic Memorandum - Deviation Request is no longer applicable. The driveway is relocated to meet sight distance criteria. Reviewed by: Gilbert LaForce, PE gilbertlaforce@elpasoco.com |
6/9/2020 9:42:10 AM | |
Colorado Springs Public Works
6/8/2020 10:17:21 AM |
Engineering Development Review has no comments on this item. Patrick V. Morris Civil Engineer II Public Works/Engineering Development Review City of Colorado Springs 30 S. Nevada Ave., Suite 401 Colorado Springs, CO 80903 tel: 719-385-5075 Main: 719-385-5979 patrick.morris@coloradosprings.gov |
6/8/2020 10:17:21 AM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
6/3/2020 3:59:14 PM |
Hey Gabe, All action items have been addressed, and approval is recommended. Let me know if you need anything else from me. Thanks, Ryne |
6/3/2020 3:59:14 PM | |
PCD Project Manager
5/12/2020 12:03:50 PM |
See engineer comments, if comments are not resolved on next submittal, a fee will be added to review again as we are now entering 6 submittals. | 5/12/2020 12:03:50 PM | |
View |
PCD Engineering Division
5/12/2020 9:17:41 AM |
Review 4 redlines: Deviation Request. | 5/12/2020 9:17:41 AM |
View |
PCD Engineering Division
5/12/2020 9:07:49 AM |
Review 4 redlines: Traffic Memo | 5/12/2020 9:07:49 AM |
PCD Engineering Division
5/12/2020 9:06:26 AM |
Review 4: Redline comments on the following documents are uploaded as separate comments: - Traffic Memorandum - Deviation Request Comments resolved on the following documents: - Financial Assurance Estimate Reviewed by: Gilbert LaForce, PE gilbertlaforce@elpasoco.com |
5/12/2020 9:06:26 AM | |
View |
EPC Health Department
4/23/2020 12:22:29 PM |
4/23/2020 12:22:29 PM | |
Colorado Department of Transportation - Pueblo Office
4/23/2020 9:43:23 AM |
This development is out of CDOT jurisdiction. Janitell Rd fall within EPC control and there appear to be no impacts to State Highway Facilities. No further comments are required. | 4/23/2020 9:43:23 AM | |
View |
PCD Project Manager
4/21/2020 2:32:50 PM |
Traffic Memo_V3, Engineer comments need to be addressed. This can affect the access point and ultimately a relocation of the driveway and new submittal for several other documents to show a new layout of not resolved. Contact the engineer if there are questions. A new submittal will not be accepted until the issues with the Traffic Memo are resolved with the engineer. | 4/21/2020 2:32:50 PM |
View |
PCD Project Manager
4/21/2020 11:30:37 AM |
Landscape Plan_V3, alternative may be accepted, however, see attached redlines an area of existing shrubs indicated that is not currently there. Director recommends proposing trees in this location. | 4/21/2020 11:30:37 AM |
View |
PCD Project Manager
4/21/2020 11:29:18 AM |
FAE_V3 | 4/21/2020 11:29:18 AM |
PCD Engineering Division
4/20/2020 5:41:12 PM |
Review 3: Redline comments on the following documents will be uploaded by the project manager: - Financial Assurance Estimate - Traffic Memorandum The attached file for the following documents are incorrect. - Swap files: Pond O&M Manual and SWMP. - Grading & Erosion Control checklist Comments resolved on the following documents: * SDI Worksheet * Pond Operations and Maintenance Manual * SWMP Checklist * SWMP * Drainage Report * Grading and Erosion Control Plan (Pond details not provided. Additional comments may be generated on the resubmittal) * GEC Checklist Reviewed by: Gilbert LaForce, PE gilbertlaforce@elpasoco.com |
4/20/2020 5:41:12 PM | |
Colorado Springs Public Works
4/14/2020 9:58:07 AM |
SWENT has no comments on this item. Jonathan Scherer by Chris Everhart |
4/14/2020 9:58:07 AM | |
County Attorney - Development Review
4/10/2020 4:34:06 PM |
This referral did not include the most recent draft of the Detention Maintenance Agreement. Upon review of the application on the public site, it appears that the Detention Maintenance Agreement uploaded on April 6 addressed all County Attorney's Office comments and is sufficient. | 4/10/2020 4:34:06 PM | |
Colorado Springs Public Works
4/3/2020 3:30:11 PM |
Traffic Engineering has no comments on this item. Zaker Alazzeh, P.E. Traffic Engineering Manager City of Colorado Springs (719) 385-5468 Zaker.Alazzeh@coloradosprings.gov |
4/3/2020 3:30:11 PM | |
Colorado Springs Public Works
4/2/2020 11:17:24 AM |
Engineering Development Review Division (EDRD) has no comments on this item. Patrick Morris Public Works/Engineering Development Review Division City of Colorado Springs 719-385-5075 Patrick.morris@coloradosprings.gov |
4/2/2020 11:17:24 AM | |
EPC Environmental Services
3/31/2020 12:26:40 PM |
El Paso County Environmental has no further comment | 3/31/2020 12:26:40 PM | |
View |
PCD Project Manager
3/5/2020 1:41:34 PM |
Traffic Memo_V2 | 3/5/2020 1:41:34 PM |
View |
PCD Project Manager
3/5/2020 1:41:11 PM |
SWMP_V2 | 3/5/2020 1:41:11 PM |
View |
PCD Project Manager
3/5/2020 1:40:49 PM |
SWMP Checklist_V2 | 3/5/2020 1:40:49 PM |
View |
PCD Project Manager
3/5/2020 1:40:29 PM |
SDI_V2 | 3/5/2020 1:40:29 PM |
View |
PCD Project Manager
3/5/2020 1:39:57 PM |
PDB-BMP Operations and Maintenance Manual_V2 | 3/5/2020 1:39:57 PM |
View |
PCD Project Manager
3/5/2020 1:39:16 PM |
GEC Plan_V2 | 3/5/2020 1:39:16 PM |
View |
PCD Project Manager
3/5/2020 1:38:55 PM |
GEC Checklist_V2 | 3/5/2020 1:38:55 PM |
View |
PCD Project Manager
3/5/2020 1:38:38 PM |
FAE_V2 | 3/5/2020 1:38:38 PM |
View |
PCD Project Manager
3/5/2020 1:38:00 PM |
Drainage Report_V2 | 3/5/2020 1:38:00 PM |
View |
PCD Project Manager
3/5/2020 1:37:38 PM |
LOI_V2 address landscape waiver, if no changes to the LOI please resubmit as is. | 3/5/2020 1:37:38 PM |
View |
PCD Project Manager
3/5/2020 1:36:50 PM |
See uploaded items for comments from engineering. Only outstanding comment from planning is the waiver request for landscaping in the Letter of Intent does is not included on the Landscape Plan. The entry feature should be on Landscape Plan. See attached Landscape Plan | 3/5/2020 1:36:50 PM |
PCD Engineering Division
3/5/2020 10:56:10 AM |
Review 2: Redline comments on the following documents will be uploaded by the project manager: * Pond Operations and Maintenance Manual * SDI Worksheet * Traffic Memorandum * Drainage Report * Grading and Erosion Control Plan (Pond details not provided. Additional comments may be generated on the resubmittal) * GEC Checklist * SWMP Checklist * SWMP * Financial Assurance Estimate Comments resolved on the following documents: - Letter of Intent - PBMP Applicability Form - EPC MS4 Post Construction Form - Copy of the State's Non-Jurisdictional Water Impoundment structure application form. Upload a copy of the notice to proceed letter once received. - Site Development Plan. FYI: Additional comments may be generated based on comments within the traffic study. - ESQCP Reviewed by: Gilbert LaForce, PE gilbertlaforce@elpasoco.com |
3/5/2020 10:56:10 AM | |
View |
El Paso County Conservation Dist
3/2/2020 9:02:05 AM |
3/2/2020 9:02:05 AM | |
Pikes Peak Regional Building Department
2/24/2020 9:49:18 AM |
Standard final plat comments apply. | 2/24/2020 9:49:18 AM | |
View |
Colorado Department of Public Health and Environment
2/21/2020 1:01:19 PM |
2/21/2020 1:01:19 PM | |
View |
EPC Environmental Services
2/19/2020 2:26:25 PM |
2/19/2020 2:26:25 PM | |
County Attorney - Development Review
2/14/2020 11:00:12 AM |
Same comments as Dec. 27. | 2/14/2020 11:00:12 AM | |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
2/14/2020 9:19:09 AM |
Hey Gabe, All action items have been addressed, and approval is recommended. Let me know if you need anything else from me. Thanks, Ryne |
2/14/2020 9:19:09 AM | |
RBD Floodplain
2/10/2020 3:47:35 PM |
this project has been approved by floodplain, permit number 19093 | 2/10/2020 3:47:35 PM | |
View |
EPC Health Department
2/9/2020 4:51:23 PM |
2/9/2020 4:51:23 PM | |
Colorado Department of Public Health and Environment
1/27/2020 10:31:09 AM |
Thank you for submitting this referral to the Colorado Department of Public Health and Environment (CDPHE). Please note that the following requirements and recommendations are not intended to be an exhaustive list and it is ultimately the responsibility of the applicant to comply with all applicable rules and regulations. Please also note that CDPHE’s failure to respond to any referrals should not be construed as a favorable response. Hazardous and Solid Waste The facility as proposed must register as an industrial recycling facility and would be regulated under Section 8 of the Colorado solid waste regulations. The facility must notify the Hazardous Materials and Waste Management Division prior to beginning operations at the site. The industrial recycling registeration form can be found on the Department website at https://www.colorado.gov/pacific/cdphe/sw-recycling-forms-apps. Contact for industrial recycling information is Emily Kaps at (303) 692-3343 or emily.kaps@state.co.us for additional information and requirements. |
1/27/2020 10:31:09 AM | |
View |
PCD Project Manager
1/14/2020 7:38:11 AM |
Traffic Memo_V1 | 1/14/2020 7:38:11 AM |
View |
PCD Project Manager
1/14/2020 7:37:55 AM |
SWMP Checklist_V1 | 1/14/2020 7:37:55 AM |
View |
PCD Project Manager
1/14/2020 7:37:36 AM |
SDP_V1 | 1/14/2020 7:37:36 AM |
View |
PCD Project Manager
1/14/2020 7:37:16 AM |
PBMP Applicability_V1 | 1/14/2020 7:37:16 AM |
View |
PCD Project Manager
1/14/2020 7:36:51 AM |
Operations Plan_V1 | 1/14/2020 7:36:51 AM |
View |
PCD Project Manager
1/14/2020 7:36:32 AM |
LOI_V1 | 1/14/2020 7:36:32 AM |
View |
PCD Project Manager
1/14/2020 7:36:15 AM |
Lighting Plan_V1 | 1/14/2020 7:36:15 AM |
View |
PCD Project Manager
1/14/2020 7:35:51 AM |
Landscape Plan_V1 | 1/14/2020 7:35:51 AM |
View |
PCD Project Manager
1/14/2020 7:35:34 AM |
GEC Plan_V1 | 1/14/2020 7:35:34 AM |
View |
PCD Project Manager
1/14/2020 7:35:01 AM |
GEC Checklist_V1 | 1/14/2020 7:35:01 AM |
View |
PCD Project Manager
1/14/2020 7:34:43 AM |
FAE_V1 | 1/14/2020 7:34:43 AM |
View |
PCD Project Manager
1/14/2020 7:34:26 AM |
ESQCP_V1 | 1/14/2020 7:34:26 AM |
View |
PCD Project Manager
1/14/2020 7:34:09 AM |
Drainage Report_V1 | 1/14/2020 7:34:09 AM |
View |
PCD Project Manager
1/14/2020 7:33:48 AM |
Closure Plan_V1 | 1/14/2020 7:33:48 AM |
View |
PCD Engineering Division
1/11/2020 1:00:07 PM |
Review 1 redline comments to the stormwater management plan (SWMP) is attached. | 1/11/2020 1:00:07 PM |
PCD Engineering Division
1/11/2020 1:23:52 PM |
Review 1: Due to the nature of the comment in the drainage report and traffic letter, resubmittal will be treated as a first review. Additional comments are likely to be generated on the resubmittal. Redline comments on the following documents will be uploaded by the project manager: - Letter of Intent - PBMP Applicability Form - Site Development Plan - Traffic Letter - GEC Checklist - SWMP Checklist - ESQCP - Grading and Erosion Control Plan - Financial Assurance Estimate - Drainage Report - Contact the department of public works (John Clack) regarding potential road degradation fee. Submit the following documents: - Pond Operations and Maintenance Manual - SDI Worksheet - EPC MS4 Post Construction Form - Copy of the State's Non-Jurisdictional Water Impoundment structure application form. Upload a copy of the notice to proceed letter once received. Reviewed by: Gilbert LaForce, PE gilbertlaforce@elpasoco.com |
1/11/2020 1:23:52 PM | |
View |
EPC Environmental Services
1/2/2020 4:07:42 PM |
1/2/2020 4:07:42 PM | |
View |
EPC Environmental Services
1/2/2020 4:07:27 PM |
1/2/2020 4:07:27 PM | |
RBD Floodplain
12/31/2019 8:22:38 AM |
looks good, drainage pond updated | 12/31/2019 8:22:38 AM | |
Pikes Peak Regional Building Department
12/30/2019 11:55:17 AM |
Address assign for this project is 2210 Jantell Road. 2104 Janitell Road should not be used. Does the 48 x 90 building still exist on this tract? A permit is required to set the trailer. |
12/30/2019 11:55:17 AM | |
View |
County Attorney - Development Review
12/27/2019 12:38:05 PM |
Proposed changes to Detention Maintenance Agreement are attached. Please review carefully. If changes are acceptable, please accept them in the document, fill out the number of detention basin/BMPs in the highlighted areas, complete the signature blocks, and return a final draft for review. Because applicant is leasing the property, the property owners must also sign the agreement. The Tract 6 owner must sign to grant the County an easement to access the property in order to reach the detention pond. The Tract 10 owners must sign to grant the County an easement for access and to perform work in the event the County must repair the pond. The Tract 10 owners must also agree to maintain and repair the pond in the event the applicant fails to do so or no longer occupies the property. |
12/27/2019 12:38:05 PM |
View |
El Paso County Conservation Dist
12/20/2019 8:18:52 AM |
12/20/2019 8:18:52 AM | |
View |
El Paso County Conservation Dist
12/20/2019 8:18:21 AM |
12/20/2019 8:18:21 AM | |
View |
Colorado Springs Utilities, Dev, Svc.(includes water resources)
12/18/2019 9:52:31 AM |
Hey Gabe, Attached is the review memo for the subject application. There is one action item, and let me know if you need anything else from me. Thanks, Ryne |
12/18/2019 9:52:31 AM |
RBD Floodplain
12/17/2019 8:10:49 AM |
“Proposed conditions drainage map” shown at the back of the Final Drainage Reports still shows the old detention pond configuration , please update. | 12/17/2019 8:10:49 AM | |
Stratmoor HIlls Fire Department
12/12/2019 3:18:20 PM |
The shed has no objections to the site development plan as described | 12/12/2019 3:18:20 PM | |
RBD Floodplain
12/12/2019 2:51:57 PM |
Disapprove: The site development and grading and erosion control plan in this submittal are data 11-12-19 and show encroachment into the floodway. The plans that were approved and permitted through the floodplain office are dated 12/9/19 and do not show encroachment into the floodway. The plans in this file need to be replaced with the updated 12-9-19 version. Keith Curtis 719-327-2898 |
12/12/2019 2:51:57 PM |