Project Review Comments

Back to List


Project Name
PRAIRIE RIDGE (Reconsideration)
Description
A request for a reconsideration for an expired final plat SF07016
Location
North of Walker, Eastside of Brown Road
Parcels
6100000483 6100000483
Applicant
SONSHIP PROPERTIES LLC
David Gorman ( daveg@mvecivil.com )
(719) 635-5736
David Gorman ( daveg@mvecivil.com )
(719) 635-5736
EA Number
EA18264
File Number
SF2010
Project Manager
Ryan Howser
Status
Closed
Created
8/28/2018 3:42:01 PM

View: Project Documents



Review Comments (70)

Link Agency Comment
EPC County Attorney's Office
12/15/2022 10:25:00 AM
All comments from 11/8/22 have been resolved. 12/15/2022 10:25:00 AM
County Attorney - Development Review
11/8/2022 1:40:17 PM
With regard to the requirements in the County Attorney's water review, please complete the following prior to final plat recording:
1. The property owner has changed. The sample deeds and the declaration of covenants must be amended to reflect the new owner and uploaded into eDARP.
2. The court decree and augmentation plan must be recorded.
3. Please upload into eDARP the deed from Sonship to Clovis conveying the water rights.
4. Please include in the sample deed to lot owners the total amounts of water in each aquifer being conveyed.
11/8/2022 1:40:17 PM
View County Attorney - Development Review
11/8/2022 1:11:36 PM
Signature to SIA attached. 11/8/2022 1:11:36 PM
View County Attorney - Development Review
11/8/2022 1:08:07 PM
Signature to escrow agreement attached. 11/8/2022 1:08:07 PM
View County Attorney - Development Review
10/20/2022 11:55:14 AM
Proposed edits to escrow agreement attached. 10/20/2022 11:55:14 AM
View County Attorney - Development Review
8/25/2022 12:12:13 PM
Attached is a template escrow agreement. The one submitted is not used by the County. 8/25/2022 12:12:13 PM
PCD Project Manager
8/18/2022 8:49:19 AM
Please update Note 22 to remove the language "Public Improvement Contribution Fund." The note can simply read "...will be paid to El Paso County to be deposited for off-site improvements to Brown Road (El Paso County Public Records, Reception No. ________). These funds..." 8/18/2022 8:49:19 AM
PCD Project Manager
8/3/2022 11:28:44 AM
Planning Division has no comments. 8/3/2022 11:28:44 AM
County Attorney - Development Review
8/1/2022 3:27:16 PM
No further comments from County Attorney - Development Review. 8/1/2022 3:27:16 PM
PCD Engineering Division
8/2/2022 4:38:02 PM
Engineering documents have been approved by the ECM administrator. Approved documents will be uploaded by the project manager.

reviewed by:
Daniel Torres
danieltorres@elpasoco.com
8/2/2022 4:38:02 PM
View EPC Environmental Services
7/15/2022 12:31:45 PM
7/15/2022 12:31:45 PM
View County Attorney - Development Review
12/3/2021 1:30:46 PM
1. No further comments to SIA.
2. If the developer wishes to include the subdivision in Public Improvement District No. 2, please complete the attached petition in full and submit to the County Attorney's Office, along with a legal description of the subdivision in Word.

State law requires that legal notice of the BoCC hearing to include the property in the PID be published for three weeks. Developer is responsible for reimbursing the County Attorney's Office for the cost of publication.

The inclusion hearing must be held before the plat is recorded and requires 3 weeks of published notice. The County Attorney's Office makes every attempt to schedule the inclusion hearing on the date of BoCC or administrative approval of the plat, or as close thereto as possible. The developer and County Planning are responsible to keep the County Attorney's Office informed of the anticipated plat approval date.
12/3/2021 1:30:46 PM
View PCD Engineering Division
11/24/2021 2:48:16 PM
Review 4 comments on the following documents will be uploaded:
-FAE (minor comment)

Please submit signed engineering documents for approval by the ECM administrator.

Ryan: a 7 day turnaround is sufficient in regards to engineering items

reviewed by:
Daniel Torres
danieltorres@elpasoco.com
11/24/2021 2:48:16 PM
EPC Stormwater Review
11/24/2021 1:33:36 PM
All Stormwater comments have been addressed. 11/24/2021 1:33:36 PM
PCD Project Manager
11/23/2021 9:45:12 AM
Planning Division has no further comments at this time. Please note project is still pending comments from the County Attorney. 11/23/2021 9:45:12 AM
View EPC Health Department
11/18/2021 9:03:07 PM
11/18/2021 9:03:07 PM
View EPC Health Department
11/17/2021 8:45:25 PM
11/17/2021 8:45:25 PM
PCD Project Manager
7/16/2021 11:30:38 AM
Please change name on face of plat to "Prairie Ridge Filing No. 1." The name referenced throughout the plat shall also be revised to reflect. 7/16/2021 11:30:38 AM
PCD Project Manager
7/15/2021 12:15:08 PM
PCD Planning Division has no further comments at this time. 7/15/2021 12:15:08 PM
View PCD Project Manager
7/15/2021 12:14:49 PM
PCD Engineering & EPC Stormwater comments - GEC plan 7/15/2021 12:14:49 PM
View PCD Project Manager
7/15/2021 12:14:28 PM
PCD Engineering comments - Financial assurance 7/15/2021 12:14:28 PM
View PCD Project Manager
7/15/2021 12:13:50 PM
PCD Engineering comments - Drainage report 7/15/2021 12:13:50 PM
EPC Stormwater Review
7/15/2021 10:54:21 AM
Review 1: EPC Stormwater comments have been provided (in orange text boxes) on the following uploaded documents:
- GEC Plan...............(to be uploaded by PM with PCD comments)

This project does not need an ESQCP, therefore I did not review the following submitted documents, as they are not required:
- SWMP
- SWMP Checklist
- PBMP Applicability

Reviewed by:
Christina Prete, P.E.
Stormwater Engineer III
christinaprete@elpasoco.com
7/15/2021 10:54:21 AM
PCD Engineering Division
7/14/2021 5:41:01 PM
Review 3 comments on the following documents will be uploaded by the project manager:
-Final Drainage Report
-GEC plan
-FAE

Comments on the following documents have been resolved:
-Final Plat
-Road Conditions Report

reviewed by
Daniel Torres
danieltorres@elpasoco.com
7/14/2021 5:41:01 PM
View EPC County Attorney's Office
7/13/2021 11:22:51 AM
7/13/2021 11:22:51 AM
View County Attorney - Development Review
6/29/2021 10:57:02 PM
Proposed changes to SIA attached. 6/29/2021 10:57:02 PM
View EPC Environmental Services
6/21/2021 2:03:16 PM
6/21/2021 2:03:16 PM
911 Authority - El Paso/Teller County
6/16/2021 7:48:04 AM
Comments for E911 as follows:
Driveway access points sufficient for development.
No new street names requested or required for this submittal.
Thank you
Justin
6/16/2021 7:48:04 AM
View PCD Project Manager
4/13/2021 9:07:40 AM
Water supply information summary comments attached. 4/13/2021 9:07:40 AM
View PCD Project Manager
4/13/2021 9:07:22 AM
Road condition report attached - includes PCD Engineering comments. 4/13/2021 9:07:22 AM
View PCD Project Manager
4/13/2021 9:07:00 AM
Letter of intent comments attached. 4/13/2021 9:07:00 AM
View PCD Project Manager
4/13/2021 9:06:45 AM
Final plat comments attached. 4/13/2021 9:06:45 AM
View PCD Project Manager
4/13/2021 9:06:20 AM
Drainage report comments attached - includes PCD Engineering comments. 4/13/2021 9:06:20 AM
PCD Engineering Division
4/12/2021 1:12:57 PM
Review 2 comments on the following documents will be uploaded by the project manager:
-Final Plat
-Final Drainage Report
-Road Conditions Report

Please submit the following documents:
-GEC plan: Please show the grading/improvements proposed to be done be the developer.
-GEC checklist
-FAE

The historic and developed drainage plans have been included in the final drainage report and do not need to be submitted separately. Any comments on these plans have been provided in the final drainage report.


reviewed by:
Daniel Torres
danieltorres@elpasoco.com
4/12/2021 1:12:57 PM
View EPC Parks Department
3/31/2021 2:23:51 PM
El Paso County Community Services / Parks Final Comments, Review #2 - Please See Attached Documents (PAB Endorsed 06/10/2020) 3/31/2021 2:23:51 PM
EPC County Attorney's Office
3/25/2021 8:20:44 AM
The water decrees (06CW100 and 06CW20) were issued in the names of Kenneth I. Rushing and Carol A. Rushing Revocable Trust Under Instrument Dated March 13, 1998. Please upload documentation showing that Sonship Properties/Justin Ensor currently own the water rights. We need to verify the chain of title for the water rights. Thank you. 3/25/2021 8:20:44 AM
View EPC Environmental Services
3/23/2021 12:05:15 PM
3/23/2021 12:05:15 PM
911 Authority - El Paso/Teller County
3/22/2021 8:00:02 AM
Comments for E911 as follows:
Driveway access points sufficient for development.
No new street names requested or required for this submittal.
Thank you
Justin
3/22/2021 8:00:02 AM
County Attorney - Development Review
3/17/2021 9:58:08 AM
No comments from County Attorney - Development Review at this time. 3/17/2021 9:58:08 AM
RBD Floodplain
3/9/2021 1:17:10 PM
floodplain note 9 should call out panel suffix 305G not 325G 3/9/2021 1:17:10 PM
View Parks Advisory Board
6/12/2020 2:05:13 PM
El Paso County Community Services / Parks Final Comments - Please See Attached Documents (PAB Endorsed on 06/10/2020) 6/12/2020 2:05:13 PM
View EPC Parks Department
6/12/2020 2:03:13 PM
El Paso County Community Services / Parks Preliminary Comments - Please See Attached Documents (To be presented to PAB for endorsement on 06/10/2020) 6/12/2020 2:03:13 PM
View County Attorney - Development Review
6/4/2020 12:25:01 PM
This project is subject to the El Paso County Road Impact Fee.

If the developer wishes to include the subdivision in Public Improvement District No. 2, please complete the attached petition in full and submit to the County Attorney's Office, along with a legal description of the subdivision in Word.

State law requires that legal notice of the BoCC hearing to include the property in the PID be published for three weeks. Developer is responsible for reimbursing the County Attorney's Office for the cost of publication.

The inclusion hearing must be held before the plat is recorded and requires 3 weeks of published notice. The County Attorney's Office makes every attempt to schedule the inclusion hearing on the date of BoCC or administrative approval of the plat, or as close thereto as possible. The developer and County Planning are responsible to keep the County Attorney's Office informed of the anticipated plat approval date.
6/4/2020 12:25:01 PM
RBD Floodplain
5/29/2020 3:52:46 PM
floodplain map should be 08041C0305G with Effective date December 7, 2018. 5/29/2020 3:52:46 PM
PCD Project Manager
5/29/2020 8:28:45 AM
Due to the number of comments, the second review will be treated as a first review. 5/29/2020 8:28:45 AM
View PCD Project Manager
5/29/2020 8:25:57 AM
Water supply information summary redline attached. 5/29/2020 8:25:57 AM
View PCD Project Manager
5/29/2020 8:25:37 AM
Water resources report redline attached. 5/29/2020 8:25:37 AM
View PCD Project Manager
5/29/2020 8:23:11 AM
Title commitment redline attached. 5/29/2020 8:23:11 AM
View PCD Project Manager
5/29/2020 8:22:49 AM
Signed court decree redlines attached. 5/29/2020 8:22:49 AM
View PCD Project Manager
5/29/2020 8:21:58 AM
Road condition report comments attached. Includes PCD Engineering comments. 5/29/2020 8:21:58 AM
View PCD Project Manager
5/29/2020 8:21:16 AM
Proportional contribution update comments attached. Includes PCD Engineering comments. 5/29/2020 8:21:16 AM
View PCD Project Manager
5/29/2020 8:20:08 AM
OWTS Report, Soils & Geology Report, Wastewater treatment report redline attached. 5/29/2020 8:20:08 AM
View PCD Project Manager
5/29/2020 8:18:25 AM
Letter of intent comments attached. Also includes PCD Engineering comments. 5/29/2020 8:18:25 AM
View PCD Project Manager
5/29/2020 8:14:53 AM
Historic drainage plan redlines attached. Includes PCD Engineering comments. 5/29/2020 8:14:53 AM
View PCD Project Manager
5/29/2020 8:13:51 AM
Drainage plan redlines attached. Includes PCD Engineering comments. 5/29/2020 8:13:51 AM
View PCD Project Manager
5/29/2020 8:20:30 AM
Drainage report redline attached. Includes PCD Engineering comments. 5/29/2020 8:20:30 AM
View PCD Project Manager
5/29/2020 8:06:42 AM
Fire protection commitment letter redline attached. 5/29/2020 8:06:42 AM
View PCD Project Manager
5/29/2020 8:22:15 AM
Final plat redline attached. Also includes PCD Engineering comments. 5/29/2020 8:22:15 AM
PCD Project Manager
5/28/2020 7:39:14 AM
You will need to provide a new, updated Subdivision Improvement Agreement specific to this project. You may use the old one as a template, or County staff can provide you with a blank template. 5/28/2020 7:39:14 AM
PCD Engineering Division
5/28/2020 9:30:39 AM
Review 1 comments on the following documents will be uploaded by the project manager:
-Plat
-Letter of Intent
-Drainage Report
-Historic Drainage Plan
-Developed Drainage Plan
-Road Conditions Report
-Proportional Contribution update

Please submit the following documents:
-FAE
-GEC
-GEC checklist

Reviewed by:
Daniel Torres
danieltorres@elpasoco.com
5/28/2020 9:30:39 AM
Pikes Peak Regional Building Department
5/27/2020 4:52:20 PM
STANDARD ENUMERATIONS COMMENTS-FINAL PLAT:

1. Enumerations will review the mylar prior to plat for address placement, street names and title block.

2. $10.00 per lot & tract platting fee will be due at the time of the review of the mylar (2 addresses per lot & tract). If an address is not needed on a tract then no fee applies. Check should be made out to PIKES PEAK REGIONAL BUILDING DEPARTMENT or PPRBD. Paid directly to the Enumerations Department.

3. A copy of the final recorded plat is required prior to plan submittal for RESIDENTIAL. A copy of the final recorded plat is required prior to approval in the Enumerations department on any COMMERCIAL plan submittal. Amy@pprbd.org

3.1. Standard final plat comments still apply, but with RBD being closed, there are a few new changes to Enumerations review of the Mylar. Please, send a pdf of the final plat document (intended plat of record) to the Enumerations reviewer that reviewed the project. We will then check the mylar for the normal things we look at on a plat, address, street names, title block and floodplain statement. Then we will stamp off on that document with an RBD check stamp, if all is accurate. This will be our copy of record that we plan to see once the document is recorded, minus a few signatures on the main sheet. Please contact your reviewer in Enumerations for instruction on payment. In this case there are 7 lots, $10.00 per lot & tract. No tracts, total is $70.00, due at the time of the review of the mylar.

Per Keith Curtis; floodplain map should be 08041C0305G with Effective date December 7, 2018.
5/27/2020 4:52:20 PM
View Colorado Division of Water Resources
5/27/2020 2:41:53 PM
August 6, 2007 letter 5/27/2020 2:41:53 PM
View Colorado Division of Water Resources
5/27/2020 2:41:29 PM
5/27/2020 2:41:29 PM
Lewis Palmer 38
5/27/2020 2:01:51 PM
The Lewis-Palmer School District requests cash in-lieu-of land for homes permitted in this development.
The LPSD Board of Education would also like to inform the Board of County Commissioners that the elementary school and middle school in this area already exceed capacity.
5/27/2020 2:01:51 PM
Black Forest Land Use Committee
5/19/2020 1:44:07 PM
The Black Forest Land Use Committee recommends approval of this request with one question:

Why is it necessary to have two side-by-side 30-foot flag easements for access to the inside lots? Couldn't they share one 30-foot easement for a flag and then have a Y-intersection at the end of the flag to the separate houses?
5/19/2020 1:44:07 PM
911 Authority - El Paso/Teller County
5/14/2020 7:20:20 AM
For the sake of streamlining navigation for emergency services, E911 recommends naming of the access easement running N/S off of Brown Rd.

No other comment for E911.

Thank you
Justin
5/14/2020 7:20:20 AM
Colorado Geological Survey
5/13/2020 5:12:02 PM
The seven-lot Prairie Ridge Subdivision, and Entech's Soil, Geology, Geologic Hazard, and Wastewater Study, Prairie Ridge (Entech Job No. 94477, May 31, 2007) were reviewed by CGS at preliminary/final plat; comments were provided in a letter dated September 21, 2007. The site is not exposed to any geologic hazards or unusual geotechnical constraints that would preclude the proposed residential use and density. Provided Entech's recommendations are adhered to, CGS has no objection to plat approval. 5/13/2020 5:12:02 PM
View EPC Environmental Services
5/8/2020 2:17:49 PM
5/8/2020 2:17:49 PM
EPC County Attorney's Office
5/8/2020 12:49:07 PM
The County Attorney's Office will provide a review of water sufficiency once findings are received from the Colorado Division of Water Resources. Thank you. 5/8/2020 12:49:07 PM
View Mountain View Electric Association, Inc.
5/7/2020 10:50:10 AM
5/7/2020 10:50:10 AM