Project Review Comments

Back to List


Project Name
BSK INVESTMENT CONTRACTOR'S EQUIPMENT YARD
Description
Site Development plan
Location
Parcels
5308000007 5308000007
Applicant
DD GREER DESIGN STUDIO
DEBRA GREER ( DEB.J.GREER@GMAIL.COM )
(719) 499-3874
DEBRA GREER ( DEB.J.GREER@GMAIL.COM )
(719) 499-3874
EA Number
EA18189
File Number
PPR1924
Project Manager
Lindsay Darden
Status
Closed
Created
6/21/2018 1:49:16 PM

View: Project Documents



Review Comments (30)

Link Agency Comment
PCD Project Manager
10/22/2019 5:39:35 PM
All Planning comments addressed. Ready for approval pending BoCC approval of variance. Thanks! 10/22/2019 5:39:35 PM
PCD Engineering Division
10/22/2019 5:13:47 PM
Engineering documents have been approved.
Elizabeth Nijkamp 10/22/19
10/22/2019 5:13:47 PM
View PCD Project Manager
10/8/2019 8:36:32 PM
Drainage Report Redlines 10/8/2019 8:36:32 PM
View PCD Project Manager
10/8/2019 8:35:32 PM
GEC Redlines 10/8/2019 8:35:32 PM
PCD Project Manager
10/8/2019 8:26:42 PM
Comment from last review was not addressed.

The Motor Vehicle Lot Landscape Calculation is incorrect. It should read as follows:


Enter the provided number of vehicle parking spaces provided: (28)
Shade Trees: Required 2/Provided 0 (Alt request)
10/8/2019 8:26:42 PM
PCD Engineering Division
10/7/2019 10:57:40 PM
Review 3 comments on the following documents will be uploaded by the project manager:
-Drainage Report
-GEC

There are missing sheets in the above documents. Please upload the complete report and plans with your re-submittal. Signed engineering documents may be submitted.

reviewed by:
Daniel Torres
danieltorres@elpasoco.com
10/7/2019 10:57:40 PM
EPC County Attorney's Office
10/4/2019 1:22:02 PM
No further County Attorney review needed. 10/4/2019 1:22:02 PM
View PCD Project Manager
9/3/2019 3:20:41 PM
GEC redlines 9/3/2019 3:20:41 PM
View PCD Project Manager
9/3/2019 3:20:23 PM
Drainage Letter Redlines 9/3/2019 3:20:23 PM
PCD Project Manager
9/3/2019 3:16:45 PM
Landscape Plan - Motor Vehicle Lot Landscape Calcs:
Enter the provided number of vehicle parking spaces (28)
Shade Trees: Required 2/Provided 0 (Alt request)
9/3/2019 3:16:45 PM
PCD Engineering Division
8/28/2019 6:30:51 PM
Comments provided by Elizabeth Nijkamp, 719-520-7852.

The FAE submitted for this review appears to be a blank FAE form. As well, it is out of date. Please use the 2019 FAE form (you can find on our web site) and submit values in the blanks as appropriate. Note: this form will need to be signed by a professional Engineer for the state of Colorado.

Comments have been provided in the following documents and redlines will be uploaded by the project manager:

Final drainage letter
construction document (labeled GEC)
8/28/2019 6:30:51 PM
Colorado Springs Airport Advisory Commission
8/28/2019 4:06:34 PM
Airport staff has no additional comments beyond those already provided. 8/28/2019 4:06:34 PM
View EPC County Attorney's Office
8/15/2019 1:47:58 PM
Final version of Detention Maintenance Agreement attached (applicant missed some of the track changes in its most recent submission). No further changes needed. 8/15/2019 1:47:58 PM
View PCD Project Manager
6/25/2019 4:46:56 PM
See comments on the landscape plan. 6/25/2019 4:46:56 PM
View PCD Project Manager
6/25/2019 4:45:15 PM
See ESQCP redlines. 6/25/2019 4:45:15 PM
View PCD Project Manager
6/25/2019 4:44:26 PM
See redlines on the grading and erosion control plan. 6/25/2019 4:44:26 PM
View PCD Project Manager
6/25/2019 4:43:57 PM
See redlines on the legal description. 6/25/2019 4:43:57 PM
View PCD Project Manager
6/25/2019 4:43:37 PM
See redlines on letter of intent. 6/25/2019 4:43:37 PM
View PCD Project Manager
6/25/2019 4:43:16 PM
See redlines on Lighting Plan 6/25/2019 4:43:16 PM
View PCD Project Manager
6/25/2019 4:42:53 PM
See redlines on Site Plan 6/25/2019 4:42:53 PM
View PCD Project Manager
6/25/2019 4:42:31 PM
See redlines on Financial Assurance. 6/25/2019 4:42:31 PM
View PCD Project Manager
6/25/2019 4:42:11 PM
See redlines on Drainage Report. 6/25/2019 4:42:11 PM
View EPC Health Department
6/19/2019 2:59:03 PM
6/19/2019 2:59:03 PM
PCD Engineering Division
6/3/2019 1:43:53 PM
Engineering comments have been provided on the following documents, which will be uploaded by the project manager:
-Drainage Plan
-Grading and Erosion Control Plan
-Site Plan
-ESQCP
-Financial Assurance
6/3/2019 1:43:53 PM
Pikes Peak Regional Building Department
5/30/2019 10:25:54 AM
If there is to be a separate meter for site lighting an separate address will be assigned by Enumeration. Show location of meter. 5/30/2019 10:25:54 AM
View Colorado Springs Utilities, Dev, Svc.(includes water resources)
5/24/2019 9:16:41 AM
No comments - recommend approval. 5/24/2019 9:16:41 AM
View Colorado Springs Airport Advisory Commission
5/23/2019 4:43:36 PM
The attached land use summary with comments will be presented at the June 26, 2019 Airport Advisory Commission meeting. 5/23/2019 4:43:36 PM
View EPC County Attorney's Office
5/17/2019 3:45:18 PM
Revisions to Detention Maintenance Agreement attached. 5/17/2019 3:45:18 PM
Falcon Fire Protection District
5/16/2019 2:22:53 PM
Falcon Fire has reviewed this Plot plan for the BSK INVESTMENT CONTRACTOR'S EQUIPMENT YARD.
The site is existing, and no changes are proposed to the building, fencing or parking lot. Falcon Fire has no objections to this request. No other fire code concerns or comments are provided at this time.
5/16/2019 2:22:53 PM
View Mountain View Electric Association, Inc.
5/16/2019 1:09:47 PM
5/16/2019 1:09:47 PM