Project Details

Search


File Number
PPR1924
Project Name
BSK INVESTMENT CONTRACTOR'S EQUIPMENT YARD
Description
Site Development plan
Parcels
5308000007 5308000007
Applicant
DD GREER DESIGN STUDIO
DEBRA GREER ( DEB.J.GREER@GMAIL.COM )
(719) 499-3874
DEBRA GREER ( DEB.J.GREER@GMAIL.COM )
(719) 499-3874
EA Number
EA18189
File Prefix
PPR - Plot Plan Review
Year
2019
Project Manager
Lindsay Darden
Status
Closed
Created
6/21/2018 1:49:16 PM

View: Review Comments


Approved Documents (4)

Link Document
View Grading & Erosion Control Plan (24 x 36)
View Site Development Plan (24" x 36")
View Drainage Report - Final
View Financial Assurance Forms


Review Documents (18)

Link Document Date
View Application/Petition Form 5/10/2019 8:56:37 PM
View Legal Description (MS WORD Version required) 8/14/2019 6:18:01 PM
View Letter of Intent 8/14/2019 6:18:02 PM
View Title Commitment (Current within 30 days of submittal) 5/14/2019 1:29:16 PM
View Vicinity/Location Map 5/10/2019 8:56:41 PM
View Erosion and Stormwater Quality Control Permit (ESQCP) 8/14/2019 8:11:28 PM
View Grading & Erosion Control Plan (24 x 36) 10/11/2019 9:39:18 AM
View Landscape Plan drawings (24" x 36") 10/22/2019 3:41:20 PM
View Site Development Plan (24" x 36") 8/14/2019 8:11:29 PM
View Drainage Report - Final 10/11/2019 9:26:09 AM
View Detention Maintenance Agreement (MS WORD version required - attachments included) 9/19/2019 1:41:52 PM
View comments response 8/14/2019 8:11:30 PM
View drainage report comments response 8/14/2019 6:18:06 PM
View driveway permit 8/14/2019 8:18:09 PM
View Elevation Plans (24" x 36") 5/10/2019 8:56:38 PM
View Financial Assurance Forms 9/19/2019 1:41:53 PM
View Lighting Plan (24" x 36") 8/14/2019 6:18:03 PM
View Maintenance manual 8/14/2019 7:15:18 PM



Events (71)

Date Comment
1/10/2020 4:32:22 PM Project Closed
1/10/2020 4:32:22 PM Project Approved: 1/10/2020
10/22/2019 5:40:25 PM Project Ready for Approval requests. Review Comment period is complete.
10/22/2019 5:39:57 PM Request for Review Comments returned by PCD Project Manager
10/22/2019 5:38:47 PM Request for Review Comments email resent for Project BSK INVESTMENT CONTRACTOR'S EQUIPMENT YARD for review by Lindsay Darden on behalf of PCD Project Manager
10/22/2019 5:36:35 PM Submission Triaged
10/22/2019 5:13:55 PM Request for Review Comments returned by PCD Engineering Division
10/22/2019 3:41:28 PM Submission received from Applicant
10/22/2019 3:35:51 PM Submission request sent to Applicant
10/20/2019 9:14:38 PM Request for Review Comments returned by PCD Project Manager
10/14/2019 8:48:27 AM Request for Review Comments email sent for Project BSK INVESTMENT CONTRACTOR'S EQUIPMENT YARD for review by Lindsay Darden on behalf of PCD Project Manager
10/14/2019 8:48:25 AM Request for Review Comments email sent for Project BSK INVESTMENT CONTRACTOR'S EQUIPMENT YARD for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
10/14/2019 8:47:32 AM Submission Triaged
10/11/2019 9:41:04 AM Submission received from Applicant
10/8/2019 8:37:56 PM Submission request sent to Applicant
10/8/2019 8:36:54 PM Request for Review Comments returned by PCD Project Manager
10/8/2019 8:33:47 PM Request for Review Comments email resent for Project BSK INVESTMENT CONTRACTOR'S EQUIPMENT YARD for review by Lindsay Darden on behalf of PCD Project Manager
10/8/2019 8:27:09 PM Request for Review Comments returned by PCD Project Manager
10/7/2019 10:57:58 PM Request for Review Comments returned by PCD Engineering Division
10/4/2019 1:22:07 PM Request for Review Comments returned by EPC County Attorney's Office
9/23/2019 1:51:41 PM Request for Review Comments email sent for Project BSK INVESTMENT CONTRACTOR'S EQUIPMENT YARD for review by Edi Anderson on behalf of EPC County Attorney's Office
9/23/2019 1:51:40 PM Request for Review Comments email sent for Project BSK INVESTMENT CONTRACTOR'S EQUIPMENT YARD for review by Lindsay Darden on behalf of PCD Project Manager
9/23/2019 1:51:38 PM Request for Review Comments email sent for Project BSK INVESTMENT CONTRACTOR'S EQUIPMENT YARD for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
9/23/2019 1:49:27 PM Submission Triaged
9/19/2019 1:54:34 PM Submission received from Applicant
9/3/2019 3:23:06 PM Submission request sent to Applicant
9/3/2019 3:20:54 PM Request for Review Comments returned by PCD Project Manager
8/28/2019 6:34:00 PM Request for Review Comments returned by PCD Engineering Division
8/28/2019 4:07:38 PM Request for Review Comments returned by Colorado Springs Airport Advisory Commission
8/15/2019 1:48:05 PM Request for Review Comments returned by EPC County Attorney's Office
8/15/2019 8:35:03 AM Request for Review Comments email sent for Project BSK INVESTMENT CONTRACTOR'S EQUIPMENT YARD for review by Kristine Andrews on behalf of Colorado Springs Airport Advisory Commission
8/15/2019 8:35:01 AM Request for Review Comments email sent for Project BSK INVESTMENT CONTRACTOR'S EQUIPMENT YARD for review by Edi Anderson on behalf of EPC County Attorney's Office
8/15/2019 8:35:00 AM Request for Review Comments email sent for Project BSK INVESTMENT CONTRACTOR'S EQUIPMENT YARD for review by Lindsay Darden on behalf of PCD Project Manager
8/15/2019 8:34:58 AM Request for Review Comments email sent for Project BSK INVESTMENT CONTRACTOR'S EQUIPMENT YARD for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
8/15/2019 8:33:23 AM Submission Triaged
8/14/2019 8:18:20 PM Submission received from Applicant
6/25/2019 4:50:41 PM Submission request sent to Applicant
6/25/2019 4:47:09 PM Request for Review Comments returned by PCD Project Manager
6/19/2019 2:59:31 PM Request for Review Comments returned by EPC Health Department
6/3/2019 1:44:13 PM Request for Review Comments returned by PCD Engineering Division
5/30/2019 10:26:13 AM Request for Review Comments returned by Pikes Peak Regional Building Department
5/24/2019 9:16:47 AM Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
5/23/2019 4:43:49 PM Request for Review Comments returned by Colorado Springs Airport Advisory Commission
5/17/2019 3:45:25 PM Request for Review Comments returned by EPC County Attorney's Office
5/16/2019 2:22:59 PM Request for Review Comments returned by Falcon Fire Protection District
5/16/2019 1:09:55 PM Request for Review Comments returned by Mountain View Electric Association, Inc.
5/16/2019 8:17:57 AM Request for Review Comments email sent for Project BSK INVESTMENT CONTRACTOR'S EQUIPMENT YARD for review by Cathy Hansen Lee on behalf of Mountain View Electric Association, Inc.
5/16/2019 8:17:54 AM Request for Review Comments email sent for Project BSK INVESTMENT CONTRACTOR'S EQUIPMENT YARD for review by Melissa Andrews on behalf of Falcon School District 49
5/16/2019 8:17:52 AM Request for Review Comments email sent for Project BSK INVESTMENT CONTRACTOR'S EQUIPMENT YARD for review by Chief Trent Harwig on behalf of Falcon Fire Protection District
5/16/2019 8:17:50 AM Request for Review Comments email sent for Project BSK INVESTMENT CONTRACTOR'S EQUIPMENT YARD for review by UDS Admin Staff on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
5/16/2019 8:17:48 AM Request for Review Comments email sent for Project BSK INVESTMENT CONTRACTOR'S EQUIPMENT YARD for review by Carl Schueler on behalf of Colorado Springs Planning & Community Development
5/16/2019 8:17:46 AM Request for Review Comments email sent for Project BSK INVESTMENT CONTRACTOR'S EQUIPMENT YARD for review by Kristine Andrews on behalf of Colorado Springs Airport Advisory Commission
5/16/2019 8:17:44 AM Request for Review Comments email sent for Project BSK INVESTMENT CONTRACTOR'S EQUIPMENT YARD for review by RBD Enumerations & Floodplain on behalf of Pikes Peak Regional Building Department
5/16/2019 8:17:38 AM Request for Review Comments email sent for Project BSK INVESTMENT CONTRACTOR'S EQUIPMENT YARD for review by on behalf of EPC Health Department
5/16/2019 8:17:36 AM Request for Review Comments email sent for Project BSK INVESTMENT CONTRACTOR'S EQUIPMENT YARD for review by Edi Anderson on behalf of EPC County Attorney's Office
5/16/2019 8:17:33 AM Request for Review Comments email sent for Project BSK INVESTMENT CONTRACTOR'S EQUIPMENT YARD for review by Lindsay Darden on behalf of PCD Project Manager
5/16/2019 8:17:31 AM Request for Review Comments email sent for Project BSK INVESTMENT CONTRACTOR'S EQUIPMENT YARD for review by Elizabeth Nijkamp on behalf of PCD Engineering Division
5/15/2019 11:48:43 AM Fees paid: 5/15/2019 (Receipt: 1001454)
5/15/2019 11:34:02 AM Payment Request sent: 5/15/2019
5/15/2019 11:31:14 AM File # Assigned: PPR1924
5/14/2019 4:04:59 PM Submission Triaged
5/14/2019 3:43:49 PM Submission received from Applicant
5/14/2019 1:25:38 PM Project Manager Assigned: Lindsay Darden
5/14/2019 1:22:48 PM Submission request sent to Applicant
5/14/2019 1:22:28 PM Submission Triaged
5/14/2019 12:39:43 PM Submission received from Applicant
4/11/2019 1:47:28 PM Submission request sent to Applicant
6/21/2018 1:52:17 PM Submission request sent to Applicant
6/21/2018 1:49:24 PM Project Manager Assigned: Len Kendall
6/21/2018 1:49:24 PM EA Assigned: EA18189
6/21/2018 1:49:24 PM Project Created