11/17/2026 8:35:04 AM
|
Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
|
|
11/12/2026 10:29:53 AM
|
Request for Review Comments email sent for Project CSU Midway to Kelker T-Line for review by Zaker Alazzeh on behalf of Colorado Springs Public Works
|
|
11/12/2026 10:29:52 AM
|
Request for Review Comments email sent for Project CSU Midway to Kelker T-Line for review by LaShunda Simpson on behalf of Colorado Springs Public Works
|
|
11/12/2026 10:29:51 AM
|
Request for Review Comments email sent for Project CSU Midway to Kelker T-Line for review by Jonathan Scherer on behalf of Colorado Springs Public Works
|
|
11/12/2026 10:29:50 AM
|
Request for Review Comments email sent for Project CSU Midway to Kelker T-Line for review by Joel Dagnillo on behalf of Colorado Springs Public Works
|
|
11/12/2026 10:29:50 AM
|
Request for Review Comments email sent for Project CSU Midway to Kelker T-Line for review by Hao Vo on behalf of Colorado Springs Public Works
|
|
11/12/2026 10:29:49 AM
|
Request for Review Comments email sent for Project CSU Midway to Kelker T-Line for review by Erin Powers on behalf of Colorado Springs Public Works
|
|
11/12/2026 10:29:48 AM
|
Request for Review Comments email sent for Project CSU Midway to Kelker T-Line for review by General Email on behalf of Colorado Springs Public Works
|
|
11/12/2026 10:29:47 AM
|
Request for Review Comments email sent for Project CSU Midway to Kelker T-Line for review by Brian Shevock on behalf of Colorado Springs Public Works
|
|
11/12/2026 10:29:46 AM
|
Request for Review Comments email sent for Project CSU Midway to Kelker T-Line for review by Daniel Delgado on behalf of US Army Corps of Engineers
|
|
11/12/2026 10:29:45 AM
|
Request for Review Comments email sent for Project CSU Midway to Kelker T-Line for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
|
|
11/12/2026 10:29:45 AM
|
Request for Review Comments email sent for Project CSU Midway to Kelker T-Line for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
|
|
11/12/2026 10:29:44 AM
|
Request for Review Comments email sent for Project CSU Midway to Kelker T-Line for review by Kimberly Blanchard on behalf of Colorado Department of Transportation - Pueblo Office
|
|
11/12/2026 10:29:43 AM
|
Request for Review Comments email sent for Project CSU Midway to Kelker T-Line for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
|
|
11/12/2026 10:29:42 AM
|
Request for Review Comments email sent for Project CSU Midway to Kelker T-Line for review by LBS Review on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
|
11/12/2026 10:29:41 AM
|
Request for Review Comments email sent for Project CSU Midway to Kelker T-Line for review by on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
|
11/12/2026 10:29:41 AM
|
Request for Review Comments email sent for Project CSU Midway to Kelker T-Line for review by Zachary Jannusch on behalf of EPC DPW Stormwater
|
|
11/12/2026 10:29:40 AM
|
Request for Review Comments email sent for Project CSU Midway to Kelker T-Line for review by Mikayla Hartford on behalf of EPC DPW Stormwater
|
|
11/12/2026 10:29:39 AM
|
Request for Review Comments email sent for Project CSU Midway to Kelker T-Line for review by Glenn Reese on behalf of EPC DPW Stormwater
|
|
11/12/2026 10:29:38 AM
|
Request for Review Comments email sent for Project CSU Midway to Kelker T-Line for review by Erica Rylander on behalf of EPC DPW Stormwater
|
|
11/12/2026 10:29:38 AM
|
Request for Review Comments email sent for Project CSU Midway to Kelker T-Line for review by Christina Prete on behalf of EPC DPW Stormwater
|
|
11/12/2026 10:29:37 AM
|
Request for Review Comments email sent for Project CSU Midway to Kelker T-Line for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
|
|
11/12/2026 10:29:36 AM
|
Request for Review Comments email sent for Project CSU Midway to Kelker T-Line for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
|
11/12/2026 8:46:29 AM
|
Fees paid: 11/12/2026 (Receipt: 1012884)
|
|
10/14/2026 4:19:05 PM
|
Payment Request sent: 10/14/2026
|
|
10/14/2026 4:19:05 PM
|
File # Assigned: CDR2614
|
|
10/14/2026 4:19:02 PM
|
Submission Triaged
|
|
10/14/2026 2:49:07 PM
|
Submission received from Applicant
|
|
8/21/2026 4:35:29 PM
|
Submission request sent to Applicant
|
|
8/21/2026 3:50:04 PM
|
Project Manager Assigned: Bret Dilts
|
|
8/21/2026 3:50:04 PM
|
Project Created
|