10/19/2026 8:25:55 AM
|
Submission request sent to Applicant
|
|
10/15/2026 6:17:14 PM
|
Request for Review Comments returned by EPC DPW Development Services - Engineering
|
|
10/15/2026 5:12:12 PM
|
Request for Review Comments returned by EPC DPW Stormwater
|
|
10/6/2026 7:34:00 AM
|
Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
|
|
10/5/2026 9:46:56 AM
|
Request for Review Comments returned by US Army Corps of Engineers
|
|
10/5/2026 7:46:54 AM
|
Request for Review Comments email sent for Project 4420 Green Mountain Dr for review by Daniel Delgado on behalf of US Army Corps of Engineers
|
|
10/5/2026 7:46:53 AM
|
Request for Review Comments email sent for Project 4420 Green Mountain Dr for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
|
|
10/5/2026 7:46:52 AM
|
Request for Review Comments email sent for Project 4420 Green Mountain Dr for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
|
|
10/5/2026 7:46:51 AM
|
Request for Review Comments email sent for Project 4420 Green Mountain Dr for review by Kimberly Blanchard on behalf of Colorado Department of Transportation - Pueblo Office
|
|
10/5/2026 7:46:50 AM
|
Request for Review Comments email sent for Project 4420 Green Mountain Dr for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
|
|
10/5/2026 7:46:49 AM
|
Request for Review Comments email sent for Project 4420 Green Mountain Dr for review by Zachary Jannusch on behalf of EPC DPW Stormwater
|
|
10/5/2026 7:46:48 AM
|
Request for Review Comments email sent for Project 4420 Green Mountain Dr for review by Mikayla Hartford on behalf of EPC DPW Stormwater
|
|
10/5/2026 7:46:47 AM
|
Request for Review Comments email sent for Project 4420 Green Mountain Dr for review by Glenn Reese on behalf of EPC DPW Stormwater
|
|
10/5/2026 7:46:46 AM
|
Request for Review Comments email sent for Project 4420 Green Mountain Dr for review by Erica Rylander on behalf of EPC DPW Stormwater
|
|
10/5/2026 7:46:46 AM
|
Request for Review Comments email sent for Project 4420 Green Mountain Dr for review by Christina Prete on behalf of EPC DPW Stormwater
|
|
10/5/2026 7:46:44 AM
|
Request for Review Comments email sent for Project 4420 Green Mountain Dr for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
|
|
10/5/2026 7:46:44 AM
|
Request for Review Comments email sent for Project 4420 Green Mountain Dr for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
|
10/1/2026 11:08:57 AM
|
Fees paid: 10/1/2026 (Receipt: 1012717)
|
|
10/1/2026 10:05:14 AM
|
Project Manager Assigned: Stormwater Mikayla Hartford
|
|
10/1/2026 10:04:40 AM
|
Payment Request sent: 10/1/2026
|
|
10/1/2026 10:04:37 AM
|
Submission Triaged
|
|
9/30/2026 3:41:21 PM
|
Submission received from Applicant
|
|
7/27/2026 2:34:32 PM
|
Submission request sent to Applicant
|
|
7/27/2026 2:31:02 PM
|
File # Assigned: CDR2612
|
|
7/23/2026 12:12:28 PM
|
Project Manager Assigned: Stormwater Christina Prete
|
|
7/23/2026 12:03:05 PM
|
Submission request sent to Applicant
|
|
7/23/2026 11:59:48 AM
|
Project Manager Assigned: Miranda Benson
|
|
7/23/2026 11:59:48 AM
|
Project Created
|