Project Details

Search | All Active Projects


File Number
P2610
Project Name
Siesta Grove Rezoning RR-5 to RR-2.5
Parcels
6100000292 6100000292
Applicant
Vertex Consulting Services, LLC
Nina Dossey ( nina.dossey@vertexcos.com )
(719) 433-2018
Nina Dossey ( nina.dossey@vertexcos.com )
(719) 433-2018
EA Number
EA2652
File Prefix
P - Rezoning to A-5; A-35; F-5; RR.5; RR2,5; and RR-2
Year
2026
Project Manager
Jen Uhler
Status
Active
Created
4/29/2026 9:10:50 AM

View: Review Comments | Submit/View Public Comment



Additional Documents (3)

Link Document Comment
View Neighbor Notice & Vicinity Map Notice of Application letters were mailed to surrounding property owners on 08/06/2026. JM
View Mailing Labels Mailing Labels for the 19 surrounding property owners that received notices. Cost = $14.82. JM
View Selected Range Selected Range was 500 feet. JM


Review Documents (5)

Link Document Date
View Application/Petition Form 6/24/2026 12:52:03 PM
View Legal Description (MS WORD Version required) 6/23/2026 2:20:42 PM
View Letter of Intent 6/24/2026 2:35:33 PM
View Zoning Map 7/17/2026 8:57:28 AM
View Mineral Rights Certification 7/24/2026 3:51:21 PM



Events (59)

Date Comment
8/14/2026 10:19:40 AM Payment Request sent: 8/14/2026
8/10/2026 9:42:18 AM Request for Review Comments returned by EPC Environmental Services
8/9/2026 6:03:29 PM Request for Review Comments returned by EPC Sheriff's Department
8/7/2026 11:16:43 AM Request for Review Comments returned by County Attorney - Water
8/6/2026 11:22:19 AM Request for Review Comments returned by PCD Administrative Notice
8/5/2026 12:39:41 PM Request for Review Comments returned by EPC Parks Department
8/4/2026 4:18:52 PM Request for Review Comments returned by Colorado Springs Planning & Community Development
8/3/2026 9:02:57 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by Kyle Fenner on behalf of Colorado Springs Planning & Community Development
8/3/2026 9:02:56 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by Drew Foxx on behalf of Colorado Springs Planning & Community Development
8/3/2026 9:02:55 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by Allison Stocker on behalf of Colorado Springs Planning & Community Development
8/3/2026 9:02:54 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by Alexander Painter on behalf of Colorado Springs Planning & Community Development
8/3/2026 9:02:53 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by on behalf of Pikes Peak Regional Building Department
8/3/2026 9:02:52 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by William Vogl on behalf of El Paso County Conservation Dist
8/3/2026 9:02:51 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by Harry Thomas on behalf of El Paso County Conservation Dist
8/3/2026 9:02:50 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by Katie Miller on behalf of El Paso County Conservation Dist
8/3/2026 9:02:49 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by on behalf of El Paso County Conservation Dist
8/3/2026 9:02:48 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by Mariah Hudson on behalf of El Paso County Conservation Dist
8/3/2026 9:02:47 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by Vicki Wood on behalf of Lewis Palmer School District 38
8/3/2026 9:02:46 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by Melissa Andrews on behalf of Lewis Palmer School District 38
8/3/2026 9:02:45 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by Brett Ridgway on behalf of Lewis Palmer School District 38
8/3/2026 9:02:44 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by Tony Cerrone on behalf of Black Forest Fire Protection District
8/3/2026 9:02:43 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by Rachel Dunn on behalf of Black Forest Fire Protection District
8/3/2026 9:02:42 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by Michael Alvarado on behalf of Black Forest Fire Protection District
8/3/2026 9:02:41 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by on behalf of Black Forest Fire Protection District
8/3/2026 9:02:40 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by Fielding Lucas on behalf of Black Forest Fire Protection District
8/3/2026 9:02:40 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by Cody Poole on behalf of Black Forest Fire Protection District
8/3/2026 9:02:39 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by Chad Herdt on behalf of Black Forest Fire Protection District
8/3/2026 9:02:38 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by General Email on behalf of Mountain View Electric Association, Inc.
8/3/2026 9:02:37 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by Jeff Kramer on behalf of EPC Sheriff's Department
8/3/2026 9:02:36 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by Heidi Williams on behalf of EPC Sheriff's Department
8/3/2026 9:02:35 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by Lizz Floro on behalf of EPC Sheriff's Department
8/3/2026 9:02:34 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by on behalf of EPC Parks Department
8/3/2026 9:02:33 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by Catherine McGarvy on behalf of EPC Health Department
8/3/2026 9:02:32 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by HEAEH LandUse on behalf of EPC Health Department
8/3/2026 9:02:31 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by Kathy Andrew on behalf of EPC Environmental Services
8/3/2026 9:02:29 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by Zachary Jannusch on behalf of EPC DPW Stormwater
8/3/2026 9:02:29 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by Mikayla Hartford on behalf of EPC DPW Stormwater
8/3/2026 9:02:28 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by Glenn Reese on behalf of EPC DPW Stormwater
8/3/2026 9:02:27 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by Erica Rylander on behalf of EPC DPW Stormwater
8/3/2026 9:02:26 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by Christina Prete on behalf of EPC DPW Stormwater
8/3/2026 9:02:25 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
8/3/2026 9:02:24 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
8/3/2026 9:02:23 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by Lori Seago on behalf of County Attorney - Water
8/3/2026 9:02:22 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by Erika Keech on behalf of County Attorney - Water
8/3/2026 9:02:21 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by April Willie on behalf of County Attorney - Water
8/3/2026 9:02:20 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by Justin Kilgore on behalf of PCD Project Manager
8/3/2026 9:02:18 AM Request for Review Comments email sent for Project Siesta Grove Rezoning RR-5 to RR-2.5 for review by on behalf of PCD Administrative Notice
7/26/2026 8:20:21 AM Fees paid: 7/26/2026 (Receipt: 1012377)
7/24/2026 3:59:21 PM Payment Request sent: 7/24/2026
7/24/2026 3:59:20 PM File # Assigned: P2610
7/24/2026 3:59:17 PM Submission Triaged
7/24/2026 3:51:32 PM Submission received from Applicant
7/17/2026 11:37:36 AM Submission request sent to Applicant
7/17/2026 11:37:30 AM Submission Triaged
7/17/2026 9:45:33 AM Submission received from Applicant
4/30/2026 11:25:15 AM Submission request sent to Applicant
4/29/2026 9:10:54 AM Project Manager Assigned: Jen Uhler
4/29/2026 9:10:54 AM EA Assigned: EA2652
4/29/2026 9:10:54 AM Project Created