9/23/2026 4:27:47 PM
|
Request for Review Comments returned by EPC Code Enforcement
|
|
9/23/2026 12:01:31 PM
|
Request for Review Comments returned by EPC Environmental Services
|
|
9/23/2026 11:49:45 AM
|
Request for Review Comments returned by Pikes Peak Regional Building Department
|
|
9/22/2026 3:28:17 PM
|
Request for Review Comments returned by EPC DPW Stormwater
|
|
9/15/2026 2:09:21 PM
|
Request for Review Comments returned by EPC Parks Department
|
|
9/14/2026 4:16:23 PM
|
Request for Review Comments returned by PCD Administrative Notice
|
|
9/11/2026 8:13:02 AM
|
Request for Review Comments returned by RBD Floodplain
|
|
9/10/2026 7:12:59 AM
|
Request for Review Comments returned by E911 Authority - El Paso/Teller County
|
|
9/9/2026 4:05:01 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
|
9/8/2026 11:57:31 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Tony Cerrone on behalf of Black Forest Fire Protection District
|
|
9/8/2026 11:57:30 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Rachel Dunn on behalf of Black Forest Fire Protection District
|
|
9/8/2026 11:57:29 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Michael Alvarado on behalf of Black Forest Fire Protection District
|
|
9/8/2026 11:57:28 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by on behalf of Black Forest Fire Protection District
|
|
9/8/2026 11:57:28 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Fielding Lucas on behalf of Black Forest Fire Protection District
|
|
9/8/2026 11:57:27 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Cody Poole on behalf of Black Forest Fire Protection District
|
|
9/8/2026 11:57:26 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Chad Herdt on behalf of Black Forest Fire Protection District
|
|
9/8/2026 11:57:25 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Keith Curtis on behalf of RBD Floodplain
|
|
9/8/2026 11:57:24 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by on behalf of Pikes Peak Regional Building Department
|
|
9/8/2026 11:57:23 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Julie Reeves on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
|
9/8/2026 11:57:22 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by george san miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
|
9/8/2026 11:57:21 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
|
9/8/2026 11:57:20 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Mike Till on behalf of Colorado State Forest Service
|
|
9/8/2026 11:57:19 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Victoria Poulton on behalf of Colorado Parks and Wildlife
|
|
9/8/2026 11:57:18 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Travis Sauder on behalf of Colorado Parks and Wildlife
|
|
9/8/2026 11:57:17 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Tim Kroening on behalf of Colorado Parks and Wildlife
|
|
9/8/2026 11:57:16 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Peter Chapman on behalf of Colorado Parks and Wildlife
|
|
9/8/2026 11:57:15 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Karen Voltura on behalf of Colorado Parks and Wildlife
|
|
9/8/2026 11:57:14 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Carolyn Craveiro de Sa on behalf of Colorado Parks and Wildlife
|
|
9/8/2026 11:57:13 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
|
9/8/2026 11:57:12 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Mike Matz on behalf of Colorado Division of Water Resources
|
|
9/8/2026 11:57:11 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Ailis Thyne on behalf of Colorado Division of Water Resources
|
|
9/8/2026 11:57:10 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Victoria Chavez on behalf of Road Impact Fee Administrator
|
|
9/8/2026 11:57:09 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by on behalf of Parks Advisory Board
|
|
9/8/2026 11:57:08 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by on behalf of EPC Public Works, County Engineer
|
|
9/8/2026 11:57:07 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by on behalf of EPC Public Works, County Engineer
|
|
9/8/2026 11:57:06 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by on behalf of EPC Parks Department
|
|
9/8/2026 11:57:05 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Catherine McGarvy on behalf of EPC Health Department
|
|
9/8/2026 11:57:04 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by HEAEH LandUse on behalf of EPC Health Department
|
|
9/8/2026 11:57:03 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Kathy Andrew on behalf of EPC Environmental Services
|
|
9/8/2026 11:57:02 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Zachary Jannusch on behalf of EPC DPW Stormwater
|
|
9/8/2026 11:57:01 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Mikayla Hartford on behalf of EPC DPW Stormwater
|
|
9/8/2026 11:57:00 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Glenn Reese on behalf of EPC DPW Stormwater
|
|
9/8/2026 11:56:59 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Erica Rylander on behalf of EPC DPW Stormwater
|
|
9/8/2026 11:56:58 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Christina Prete on behalf of EPC DPW Stormwater
|
|
9/8/2026 11:56:57 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
|
|
9/8/2026 11:56:56 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
|
9/8/2026 11:56:55 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Justin Annan on behalf of E911 Authority - El Paso/Teller County
|
|
9/8/2026 11:56:54 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Glenn West on behalf of E911 Authority - El Paso/Teller County
|
|
9/8/2026 11:56:53 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Lori Seago on behalf of County Attorney - Water
|
|
9/8/2026 11:56:52 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Erika Keech on behalf of County Attorney - Water
|
|
9/8/2026 11:56:51 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by April Willie on behalf of County Attorney - Water
|
|
9/8/2026 11:56:50 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Lori Seago on behalf of County Attorney - Development Review
|
|
9/8/2026 11:56:49 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Erika Keech on behalf of County Attorney - Development Review
|
|
9/8/2026 11:56:48 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by April Willie on behalf of County Attorney - Development Review
|
|
9/8/2026 11:56:47 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Justin Kilgore on behalf of PCD Project Manager
|
|
9/8/2026 11:56:45 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by on behalf of PCD Administrative Notice
|
|
9/8/2026 11:56:44 AM
|
Request for Review Comments email sent for Project Raff Subdivision for review by Kurt Arnoldussen on behalf of EPC Code Enforcement
|
|
9/4/2026 9:15:50 AM
|
Project Manager Assigned: Joe Letke
|
|
9/4/2026 7:29:46 AM
|
Fees paid: 9/4/2026 (Receipt: 1012598)
|
|
8/25/2026 12:27:19 PM
|
Payment Request sent: 8/25/2026
|
|
8/25/2026 12:27:19 PM
|
File # Assigned: SF2621
|
|
8/25/2026 12:27:18 PM
|
Submission Triaged
|
|
8/25/2026 11:38:36 AM
|
Submission received from Applicant
|
|
8/10/2026 9:21:11 AM
|
Submission request sent to Applicant
|
|
8/10/2026 9:20:36 AM
|
Submission Triaged
|
|
8/7/2026 3:56:33 PM
|
Submission received from Applicant
|
|
4/24/2026 2:11:19 PM
|
Submission request sent to Applicant
|
|
4/16/2026 8:06:49 AM
|
EA Assigned: EA2649
|
|
4/16/2026 8:06:49 AM
|
Project Created
|