Project Details

Search | All Active Projects


File Number
CDR267
Project Name
D20 Middle School Grading
Description
CDR needed because site grading is currently permitted under Homestead North F1. So need to separate the two projects.
Parcels
5233000022 5233000022
Applicant
Classic Consulting Engineers & Surveyors, LLC
Kyle Campbell ( KCampbell@classicconsulting.net )
(719) 492-1219
Kyle Campbell ( KCampbell@classicconsulting.net )
(719) 492-1219
File Prefix
CDR - Construction Drawing Review
Year
2026
Project Manager
Stormwater Glenn Reese
Status
Active
Created
4/15/2026 5:04:23 PM


Review Documents (8)

Link Document Date
View Erosion and Stormwater Quality Control Permit (ESQCP) 7/20/2026 4:08:34 PM
View Financial Assurance Estimate (FAE) Form 7/20/2026 4:08:33 PM
View Grading & Erosion Control (GEC) Checklist 6/26/2026 3:34:41 PM
View Grading & Erosion Control (GEC) Plan 7/20/2026 4:08:33 PM
View PCM Applicability Form 6/26/2026 3:34:42 PM
View Storm Water Management Plan (SWMP) 7/20/2026 4:08:35 PM
View Storm Water Management Plan (SWMP) Checklist 6/26/2026 3:34:41 PM
View Drainage Letter 7/20/2026 3:51:16 PM



Events (41)

Date Comment
7/21/2026 1:30:24 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by Tony Cerrone on behalf of Black Forest Fire Protection District
7/21/2026 1:30:24 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by Rachel Dunn on behalf of Black Forest Fire Protection District
7/21/2026 1:30:23 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by Michael Alvarado on behalf of Black Forest Fire Protection District
7/21/2026 1:30:22 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by on behalf of Black Forest Fire Protection District
7/21/2026 1:30:21 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by Fielding Lucas on behalf of Black Forest Fire Protection District
7/21/2026 1:30:20 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by Cody Poole on behalf of Black Forest Fire Protection District
7/21/2026 1:30:19 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by Chad Herdt on behalf of Black Forest Fire Protection District
7/21/2026 1:30:18 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by Tracy Doran on behalf of Upper Black Squirrel Creek GWMD
7/21/2026 1:30:17 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by Keith Curtis on behalf of RBD Floodplain
7/21/2026 1:30:16 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by William Vogl on behalf of El Paso County Conservation Dist
7/21/2026 1:30:15 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by Harry Thomas on behalf of El Paso County Conservation Dist
7/21/2026 1:30:14 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by Katie Miller on behalf of El Paso County Conservation Dist
7/21/2026 1:30:13 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by on behalf of El Paso County Conservation Dist
7/21/2026 1:30:12 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by Mariah Hudson on behalf of El Paso County Conservation Dist
7/21/2026 1:30:11 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by Daniel Delgado on behalf of US Army Corps of Engineers
7/21/2026 1:30:10 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by Peter Ristig on behalf of Academy School District 20 Building Fund
7/21/2026 1:30:09 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by Becky Allan on behalf of Academy School District 20 Building Fund
7/21/2026 1:30:07 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by General Email on behalf of Mountain View Electric Association, Inc.
7/21/2026 1:30:06 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by LBS Review on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
7/21/2026 1:30:05 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
7/21/2026 1:30:04 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by Trish Riber on behalf of Black Hills Energy-Aquila
7/21/2026 1:30:03 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by Marcus Henderson on behalf of Black Hills Energy-Aquila
7/21/2026 1:30:02 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by Bob Swatek on behalf of Black Hills Energy-Aquila
7/21/2026 1:30:01 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by Zachary Jannusch on behalf of EPC DPW Stormwater
7/21/2026 1:30:00 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by Mikayla Hartford on behalf of EPC DPW Stormwater
7/21/2026 1:29:59 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by Glenn Reese on behalf of EPC DPW Stormwater
7/21/2026 1:29:59 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by Erica Rylander on behalf of EPC DPW Stormwater
7/21/2026 1:29:58 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by Christina Prete on behalf of EPC DPW Stormwater
7/21/2026 1:29:57 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
7/21/2026 1:29:56 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
7/21/2026 1:29:55 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by Justin Kilgore on behalf of PCD Project Manager
7/21/2026 1:29:53 PM Request for Review Comments email sent for Project D20 Middle School Grading for review by on behalf of PCD Administrative Notice
7/21/2026 11:03:47 AM Fees paid: 7/21/2026 (Receipt: 1012361)
7/20/2026 4:25:38 PM Payment Request sent: 7/20/2026
7/20/2026 4:25:33 PM Submission Triaged
7/20/2026 4:09:32 PM Submission received from Applicant
4/15/2026 5:21:29 PM File # Assigned: CDR267
4/15/2026 5:21:20 PM Submission request sent to Applicant
4/15/2026 5:05:38 PM Submission request sent to Applicant
4/15/2026 5:04:27 PM Project Manager Assigned: Stormwater Glenn Reese
4/15/2026 5:04:27 PM Project Created