Project Details
Search |
All Active Projects
-
File Number
-
ASB264
-
Project Name
-
Circle K Site Development Plan
-
Parcels
-
5312402016
5312402016
5312402021
5312402021
5312403003
5312403003
5312403004
5312403004
-
Applicant
-
Circle K Stores Inc.
Isis Oliva ( isis@copestoneconstruction.com )
Isis Oliva ( isis@copestoneconstruction.com )
-
File Prefix
-
ASB - As Builts
-
Year
-
2026
-
Project Manager
-
Stormwater Glenn Reese
-
Status
-
Active
-
Created
-
2/11/2026 9:49:02 AM
Review Documents (7)
|
Link
|
Document
|
Date
|
|
View
|
CAD Files
|
10/21/2026 4:22:45 PM
|
|
View
|
Engineering Record Drawings (As-Builts)
|
10/21/2026 4:22:45 PM
|
|
View
|
Concrete Testing
|
10/21/2026 4:22:48 PM
|
|
View
|
Density Testing
|
10/21/2026 4:22:48 PM
|
|
View
|
PCM Certification Letter and Revised MHFD Calcs (ASB)
|
10/21/2026 4:22:46 PM
|
|
View
|
Public Improvement Certification Letter
|
10/21/2026 4:22:47 PM
|
|
View
|
Utility Acceptance Letters
|
10/21/2026 4:22:46 PM
|
Events (16)
|
Date
|
Comment
|
|
10/21/2026 5:17:23 PM
|
Request for Review Comments email sent for Project Circle K Site Development Plan for review by Zachary Jannusch on behalf of EPC DPW Stormwater
|
|
10/21/2026 5:17:22 PM
|
Request for Review Comments email sent for Project Circle K Site Development Plan for review by Mikayla Hartford on behalf of EPC DPW Stormwater
|
|
10/21/2026 5:17:22 PM
|
Request for Review Comments email sent for Project Circle K Site Development Plan for review by Glenn Reese on behalf of EPC DPW Stormwater
|
|
10/21/2026 5:17:21 PM
|
Request for Review Comments email sent for Project Circle K Site Development Plan for review by Erica Rylander on behalf of EPC DPW Stormwater
|
|
10/21/2026 5:17:20 PM
|
Request for Review Comments email sent for Project Circle K Site Development Plan for review by Christina Prete on behalf of EPC DPW Stormwater
|
|
10/21/2026 5:17:19 PM
|
Request for Review Comments email sent for Project Circle K Site Development Plan for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
|
|
10/21/2026 5:17:18 PM
|
Request for Review Comments email sent for Project Circle K Site Development Plan for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
|
10/21/2026 5:17:17 PM
|
Request for Review Comments email sent for Project Circle K Site Development Plan for review by on behalf of EPC DPW Asset Management
|
|
10/21/2026 5:15:48 PM
|
Submission Triaged
|
|
10/21/2026 4:23:21 PM
|
Submission received from Applicant
|
|
10/9/2026 4:23:58 PM
|
Submission request sent to Applicant
|
|
2/11/2026 9:50:29 AM
|
Submission request sent to Applicant
|
|
2/11/2026 9:49:06 AM
|
No Fees
|
|
2/11/2026 9:49:06 AM
|
File # Assigned: ASB264
|
|
2/11/2026 9:49:05 AM
|
Project Manager Assigned: Stormwater Glenn Reese
|
|
2/11/2026 9:49:05 AM
|
Project Created. Parent Project: Circle K Site Development Plan (PPR2230)
|