7/21/2026 1:46:10 PM
|
Request for Review Comments email resent for Project Dysart Boundary Line Adjustment for review by Hart Wright on behalf of Southwestern Hwy 115 Fire Protection District
|
|
7/21/2026 1:12:36 PM
|
Request for Review Comments returned by Southwestern Hwy 115 Fire Protection District
|
|
7/15/2026 4:16:29 PM
|
Request for Review Comments email sent for Project Dysart Boundary Line Adjustment for review by Hart Wright on behalf of Southwestern Hwy 115 Fire Protection District
|
|
7/15/2026 4:16:28 PM
|
Request for Review Comments email sent for Project Dysart Boundary Line Adjustment for review by LBS Review on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
|
7/15/2026 4:16:27 PM
|
Request for Review Comments email sent for Project Dysart Boundary Line Adjustment for review by on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
|
7/15/2026 4:16:26 PM
|
Request for Review Comments email sent for Project Dysart Boundary Line Adjustment for review by Zachary Jannusch on behalf of EPC DPW Stormwater
|
|
7/15/2026 4:16:25 PM
|
Request for Review Comments email sent for Project Dysart Boundary Line Adjustment for review by Mikayla Hartford on behalf of EPC DPW Stormwater
|
|
7/15/2026 4:16:24 PM
|
Request for Review Comments email sent for Project Dysart Boundary Line Adjustment for review by Glenn Reese on behalf of EPC DPW Stormwater
|
|
7/15/2026 4:16:23 PM
|
Request for Review Comments email sent for Project Dysart Boundary Line Adjustment for review by Erica Rylander on behalf of EPC DPW Stormwater
|
|
7/15/2026 4:16:22 PM
|
Request for Review Comments email sent for Project Dysart Boundary Line Adjustment for review by Christina Prete on behalf of EPC DPW Stormwater
|
|
7/15/2026 4:16:21 PM
|
Request for Review Comments email sent for Project Dysart Boundary Line Adjustment for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
|
|
7/15/2026 4:16:20 PM
|
Request for Review Comments email sent for Project Dysart Boundary Line Adjustment for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
|
7/15/2026 4:16:18 PM
|
Request for Review Comments email sent for Project Dysart Boundary Line Adjustment for review by Justin Kilgore on behalf of PCD Project Manager
|
|
7/15/2026 12:01:21 PM
|
Fees paid: 7/15/2026 (Receipt: 1012332)
|
|
7/15/2026 11:40:06 AM
|
Payment Request sent: 7/15/2026
|
|
7/15/2026 11:40:06 AM
|
File # Assigned: EXBL262
|
|
7/15/2026 11:40:03 AM
|
Submission Triaged
|
|
7/14/2026 8:09:30 PM
|
Submission received from Applicant
|
|
7/14/2026 7:21:15 AM
|
Submission request sent to Applicant
|
|
7/14/2026 7:21:05 AM
|
Submission request sent to Applicant
|
|
7/14/2026 7:21:00 AM
|
Submission Triaged
|
|
7/13/2026 3:39:53 PM
|
Submission received from Applicant
|
|
11/13/2025 8:15:48 AM
|
Submission request sent to Applicant
|
|
11/13/2025 8:13:55 AM
|
Project Manager Assigned: Miranda Benson
|
|
11/13/2025 8:13:55 AM
|
Project Created
|