Project Details

Search | All Active Projects


File Number
COM2528
Project Name
1822 Main Street Mister Car Wash
Description
Minor site improvement -- install one new trench drain across the exit of the car was to catch nuisance water from cars as they exit, preventing water from getting into the road. The trench drain will pipe to an existing storm drain system for collection. Approximately 20 feet of trench drain and 20 l.f. of storm drain piping into existing catch box.
Location
1822 Main Street, Colorado Springs
Parcels
6502407012 6502407012
Applicant
ESI Engineering
Brian Campbell ( brian.campbell@esieng.com )
(801) 953-4814
Brian Campbell ( brian.campbell@esieng.com )
(801) 953-4814
File Prefix
COM - Commercial over the counter
Year
2025
Project Manager
Miranda Benson
Status
Active
Created
11/12/2025 10:51:07 AM


Review Documents (2)

Link Document Date
View Road Impact Fee Acknowledgement 11/12/2025 10:51:09 AM
View Site Plan Drawing 11/12/2025 10:51:09 AM



Events (15)

Date Comment
12/31/2025 12:46:39 PM Request for Review Comments returned by EPC DPW Development Services - Engineering
12/26/2025 11:14:43 AM Request for Review Comments email sent for Project 1822 Main Street Mister Car Wash for review by Zachary Jannusch on behalf of EPC DPW Stormwater
12/26/2025 11:14:42 AM Request for Review Comments email sent for Project 1822 Main Street Mister Car Wash for review by Mikayla Hartford on behalf of EPC DPW Stormwater
12/26/2025 11:14:41 AM Request for Review Comments email sent for Project 1822 Main Street Mister Car Wash for review by Glenn Reese on behalf of EPC DPW Stormwater
12/26/2025 11:14:40 AM Request for Review Comments email sent for Project 1822 Main Street Mister Car Wash for review by Christina Prete on behalf of EPC DPW Stormwater
12/26/2025 11:14:39 AM Request for Review Comments email sent for Project 1822 Main Street Mister Car Wash for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
12/26/2025 11:14:38 AM Request for Review Comments email sent for Project 1822 Main Street Mister Car Wash for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
12/26/2025 11:14:36 AM Request for Review Comments email sent for Project 1822 Main Street Mister Car Wash for review by Justin Kilgore on behalf of PCD Project Manager
12/26/2025 9:47:35 AM Project Manager Assigned: Miranda Benson
12/22/2025 5:07:54 PM Fees paid: 12/22/2025 (Receipt: 1011467)
11/12/2025 10:51:10 AM Payment Request sent: 11/12/2025
11/12/2025 10:51:10 AM File # Assigned: COM2528
11/12/2025 10:51:09 AM Project Created
11/12/2025 10:51:07 AM Application Triaged/Accepted
11/11/2025 9:12:27 AM Application submitted