6/8/2026 2:16:45 PM
|
Request for Review Comments returned by Tri-Lakes-Monument Fire Protection District
|
|
6/4/2026 12:49:12 PM
|
Project Manager Assigned: Lacey Dean
|
|
6/1/2026 8:46:28 AM
|
Request for Review Comments returned by Colorado Department of Transportation - Pueblo Office
|
|
6/1/2026 6:54:26 AM
|
Request for Review Comments returned by Academy School District 20 Building Fund
|
|
5/29/2026 3:27:23 PM
|
Request for Review Comments returned by EPC Environmental Services
|
|
5/29/2026 7:08:23 AM
|
Request for Review Comments returned by 911 Authority - El Paso/Teller County
|
|
5/28/2026 1:54:32 PM
|
Request for Review Comments returned by County Attorney - Development Review
|
|
5/28/2026 10:38:23 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
|
5/28/2026 8:36:59 AM
|
Request for Review Comments returned by Woodmoor Water and Sanitation District
|
|
5/27/2026 3:09:00 PM
|
Request for Review Comments returned by Road Impact Fee Administrator
|
|
5/27/2026 3:03:19 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by on behalf of Woodmoor Improvement Association (HOA)
|
|
5/27/2026 3:03:18 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by on behalf of Pikes Peak Regional Building Department
|
|
5/27/2026 3:03:17 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Bill Crimmel on behalf of Northern EPC Coalition of Community Organizations, Inc. (NEPCO)(to also include the TLLU areas)
|
|
5/27/2026 3:03:16 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Justin Annan on behalf of 911 Authority - El Paso/Teller County
|
|
5/27/2026 3:03:15 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Glenn West on behalf of 911 Authority - El Paso/Teller County
|
|
5/27/2026 3:03:14 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Sabrina Untal on behalf of USAFA Base Planner
|
|
5/27/2026 3:03:13 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Matthew Fitzsimmons on behalf of USAFA Base Planner
|
|
5/27/2026 3:03:13 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Amy Kelley on behalf of USAFA Base Planner
|
|
5/27/2026 3:03:12 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by on behalf of USAFA Base Planner
|
|
5/27/2026 3:03:11 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Kimberly Wilkes on behalf of US Forest Service, Pikes Peak Ranger District
|
|
5/27/2026 3:03:10 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Jennifer DeWoody on behalf of US Forest Service, Pikes Peak Ranger District
|
|
5/27/2026 3:03:09 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Julie Reeves on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
|
5/27/2026 3:03:08 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by george san miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
|
5/27/2026 3:03:07 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by George San Miguel on behalf of US Fish Wildlife, Ecological Svcs. (USDOI, Fish & Wildlife Svc.)
|
|
5/27/2026 3:03:06 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Daniel Delgado on behalf of US Army Corps of Engineers-Pueblo
|
|
5/27/2026 3:03:05 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Mike Till on behalf of Colorado State Forest Service
|
|
5/27/2026 3:03:04 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Travis Sauder on behalf of Colorado Parks and Wildlife
|
|
5/27/2026 3:03:03 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Tim Kroening on behalf of Colorado Parks and Wildlife
|
|
5/27/2026 3:03:02 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Peter Chapman on behalf of Colorado Parks and Wildlife
|
|
5/27/2026 3:03:01 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Karen Voltura on behalf of Colorado Parks and Wildlife
|
|
5/27/2026 3:03:00 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Carolyn Craveiro de Sa on behalf of Colorado Parks and Wildlife
|
|
5/27/2026 3:02:59 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Colorado Geological Survey on behalf of Colorado Geological Survey
|
|
5/27/2026 3:02:57 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Mike Matz on behalf of Colorado Division of Water Resources
|
|
5/27/2026 3:02:57 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Ailis Thyne on behalf of Colorado Division of Water Resources
|
|
5/27/2026 3:02:56 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Teresa Guagliardo on behalf of Colorado Department of Transportation - Pueblo Office
|
|
5/27/2026 3:02:55 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Michelle Regalado on behalf of Colorado Department of Transportation - Pueblo Office
|
|
5/27/2026 3:02:54 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Kimberly Blanchard on behalf of Colorado Department of Transportation - Pueblo Office
|
|
5/27/2026 3:02:53 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Adam Lancaster on behalf of Colorado Department of Transportation - Pueblo Office
|
|
5/27/2026 3:02:52 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Woodmoor Water District on behalf of Woodmoor Water and Sanitation District
|
|
5/27/2026 3:02:51 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Jessie Shaffer on behalf of Woodmoor Water and Sanitation District
|
|
5/27/2026 3:02:50 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Peter Susemihl on behalf of Walden Metropolitan Districts 1&2
|
|
5/27/2026 3:02:49 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Scott Benson on behalf of Tri-Lakes-Monument Fire Protection District
|
|
5/27/2026 3:02:48 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Jonathan Bradley on behalf of Tri-Lakes-Monument Fire Protection District
|
|
5/27/2026 3:02:47 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Aaron Wood on behalf of Tri-Lakes-Monument Fire Protection District
|
|
5/27/2026 3:02:46 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Jeff Hodge on behalf of Donala Water and Sanitation District
|
|
5/27/2026 3:02:45 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Christina Hawker on behalf of Donala Water and Sanitation District
|
|
5/27/2026 3:02:44 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Tom Gregory on behalf of Academy School District 20 Building Fund
|
|
5/27/2026 3:02:43 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Donald Smith on behalf of Academy School District 20 Building Fund
|
|
5/27/2026 3:02:42 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Becky Allan on behalf of Academy School District 20 Building Fund
|
|
5/27/2026 3:02:41 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by General Email on behalf of Mountain View Electric Association, Inc.
|
|
5/27/2026 3:02:40 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Trish Riber on behalf of Black Hills Energy-Aquila
|
|
5/27/2026 3:02:39 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Marcus Henderson on behalf of Black Hills Energy-Aquila
|
|
5/27/2026 3:02:38 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Bob Swatek on behalf of Black Hills Energy-Aquila
|
|
5/27/2026 3:02:37 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Victoria Chavez on behalf of Road Impact Fee Administrator
|
|
5/27/2026 3:02:36 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by on behalf of Parks Advisory Board
|
|
5/27/2026 3:02:35 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Jeff Kramer on behalf of EPC Sheriff's Department
|
|
5/27/2026 3:02:34 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Lizz Floro on behalf of EPC Sheriff's Department
|
|
5/27/2026 3:02:33 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by on behalf of EPC Parks Department
|
|
5/27/2026 3:02:32 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Catherine McGarvy on behalf of EPC Health Department
|
|
5/27/2026 3:02:31 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by HEAEH LandUse on behalf of EPC Health Department
|
|
5/27/2026 3:02:30 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Kathy Andrew on behalf of EPC Environmental Services
|
|
5/27/2026 3:02:29 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Zachary Jannusch on behalf of EPC DPW Stormwater
|
|
5/27/2026 3:02:28 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Mikayla Hartford on behalf of EPC DPW Stormwater
|
|
5/27/2026 3:02:27 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Glenn Reese on behalf of EPC DPW Stormwater
|
|
5/27/2026 3:02:26 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Erica Rylander on behalf of EPC DPW Stormwater
|
|
5/27/2026 3:02:25 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Christina Prete on behalf of EPC DPW Stormwater
|
|
5/27/2026 3:02:24 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
|
|
5/27/2026 3:02:23 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
|
5/27/2026 3:02:22 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Kurt Arnoldussen on behalf of EPC Code Enforcement
|
|
5/27/2026 3:02:21 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Lori Seago on behalf of County Attorney - Water
|
|
5/27/2026 3:02:20 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Erika Keech on behalf of County Attorney - Water
|
|
5/27/2026 3:02:19 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by April Willie on behalf of County Attorney - Water
|
|
5/27/2026 3:02:18 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Lori Seago on behalf of County Attorney - Development Review
|
|
5/27/2026 3:02:18 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Erika Keech on behalf of County Attorney - Development Review
|
|
5/27/2026 3:02:17 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by April Willie on behalf of County Attorney - Development Review
|
|
5/27/2026 3:02:15 PM
|
Request for Review Comments email sent for Project Cathedral Rock Church - Minor Final Plat for review by Justin Kilgore on behalf of PCD Project Manager
|
|
5/20/2026 1:27:25 PM
|
Fees paid: 5/20/2026 (Receipt: 1012082)
|
|
5/20/2026 1:00:24 PM
|
Payment Request sent: 5/20/2026
|
|
5/20/2026 1:00:23 PM
|
File # Assigned: SF2611
|
|
5/20/2026 1:00:21 PM
|
Submission Triaged
|
|
5/20/2026 12:36:45 PM
|
Submission received from Applicant
|
|
5/20/2026 11:05:00 AM
|
Submission request sent to Applicant
|
|
5/20/2026 11:04:54 AM
|
Submission Triaged
|
|
5/20/2026 7:09:02 AM
|
Submission received from Applicant
|
|
10/1/2025 2:48:27 PM
|
Submission request sent to Applicant
|
|
10/1/2025 1:40:14 PM
|
Project Manager Assigned: Maria Lancto
|
|
10/1/2025 1:40:14 PM
|
EA Assigned: EA25107
|
|
10/1/2025 1:40:14 PM
|
Project Created
|