4/28/2026 2:38:01 PM
|
Request for Review Comments returned by EPC DPW Development Services - Engineering
|
|
4/28/2026 12:01:35 PM
|
Request for Review Comments email sent for Project 2895 Walton Creek Dr Rear Setback Variance for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
|
|
4/28/2026 12:01:35 PM
|
Request for Review Comments email sent for Project 2895 Walton Creek Dr Rear Setback Variance for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
|
4/28/2026 11:59:39 AM
|
Submission Triaged
|
|
4/28/2026 10:58:45 AM
|
Request for Review Comments returned by Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
|
4/28/2026 10:54:19 AM
|
Submission received from Applicant
|
|
4/27/2026 4:14:24 PM
|
Submission request sent to Applicant
|
|
4/27/2026 3:40:04 PM
|
Request for Review Comments returned by PCD Project Manager
|
|
4/27/2026 1:18:26 PM
|
Request for Review Comments returned by PCD Administrative Notice
|
|
4/27/2026 10:20:48 AM
|
Request for Review Comments returned by EPC DPW Stormwater
|
|
4/23/2026 4:30:40 PM
|
Request for Review Comments returned by EPC Code Enforcement
|
|
4/23/2026 7:46:38 AM
|
Request for Review Comments returned by EPC DPW Development Services - Engineering
|
|
4/23/2026 7:36:55 AM
|
Request for Review Comments returned by Mountain View Electric Association, Inc.
|
|
4/22/2026 1:17:12 PM
|
Request for Review Comments returned by Colorado Springs Planning & Community Development
|
|
4/21/2026 5:42:32 PM
|
Request for Review Comments returned by Cherokee Metro District
|
|
4/14/2026 11:41:56 AM
|
Request for Review Comments email sent for Project 2895 Walton Creek Dr - Setback Variance for review by Christina Prete on behalf of EPC DPW Stormwater
|
|
4/14/2026 11:41:55 AM
|
Request for Review Comments email sent for Project 2895 Walton Creek Dr - Setback Variance for review by Zachary Jannusch on behalf of EPC DPW Stormwater
|
|
4/14/2026 11:41:55 AM
|
Request for Review Comments email sent for Project 2895 Walton Creek Dr - Setback Variance for review by Mikayla Hartford on behalf of EPC DPW Stormwater
|
|
4/14/2026 11:41:54 AM
|
Request for Review Comments email sent for Project 2895 Walton Creek Dr - Setback Variance for review by Glenn Reese on behalf of EPC DPW Stormwater
|
|
4/14/2026 11:33:34 AM
|
Request for Review Comments email sent for Project 2895 Walton Creek Dr - Setback Variance for review by on behalf of PCD Administrative Notice
|
|
4/14/2026 11:10:46 AM
|
Request for Review Comments email sent for Project 2895 Walton Creek Dr - Setback Variance for review by Drew Foxx on behalf of Colorado Springs Planning & Community Development
|
|
4/14/2026 11:10:45 AM
|
Request for Review Comments email sent for Project 2895 Walton Creek Dr - Setback Variance for review by Allison Stocker on behalf of Colorado Springs Planning & Community Development
|
|
4/14/2026 11:10:44 AM
|
Request for Review Comments email sent for Project 2895 Walton Creek Dr - Setback Variance for review by Alexander Painter on behalf of Colorado Springs Planning & Community Development
|
|
4/14/2026 11:10:43 AM
|
Request for Review Comments email sent for Project 2895 Walton Creek Dr - Setback Variance for review by Tom Joyce on behalf of Cimarron Hills Fire District
|
|
4/14/2026 11:10:42 AM
|
Request for Review Comments email sent for Project 2895 Walton Creek Dr - Setback Variance for review by Brandon Zembles on behalf of Cherokee Metro District
|
|
4/14/2026 11:10:41 AM
|
Request for Review Comments email sent for Project 2895 Walton Creek Dr - Setback Variance for review by Jeff Munger on behalf of Cherokee Metro District
|
|
4/14/2026 11:10:40 AM
|
Request for Review Comments email sent for Project 2895 Walton Creek Dr - Setback Variance for review by General Email on behalf of Mountain View Electric Association, Inc.
|
|
4/14/2026 11:10:39 AM
|
Request for Review Comments email sent for Project 2895 Walton Creek Dr - Setback Variance for review by on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
|
4/14/2026 11:10:38 AM
|
Request for Review Comments email sent for Project 2895 Walton Creek Dr - Setback Variance for review by LBS Review on behalf of Colorado Springs Utilities, Dev, Svc.(includes water resources)
|
|
4/14/2026 11:10:37 AM
|
Request for Review Comments email sent for Project 2895 Walton Creek Dr - Setback Variance for review by Engineering Manager on behalf of EPC DPW Development Services - Engineering
|
|
4/14/2026 11:10:36 AM
|
Request for Review Comments email sent for Project 2895 Walton Creek Dr - Setback Variance for review by Gilbert LaForce on behalf of EPC DPW Development Services - Engineering
|
|
4/14/2026 11:10:35 AM
|
Request for Review Comments email sent for Project 2895 Walton Creek Dr - Setback Variance for review by Kurt Arnoldussen on behalf of EPC Code Enforcement
|
|
4/14/2026 11:10:34 AM
|
Request for Review Comments email sent for Project 2895 Walton Creek Dr - Setback Variance for review by Justin Kilgore on behalf of PCD Project Manager
|
|
4/14/2026 10:03:50 AM
|
Fees paid: 4/14/2026 (Receipt: 1011935)
|
|
4/13/2026 7:48:16 AM
|
Project Manager Assigned: Jen Uhler
|
|
4/13/2026 7:47:35 AM
|
Payment Request sent: 4/13/2026
|
|
4/13/2026 7:47:35 AM
|
File # Assigned: BOA262
|
|
4/13/2026 7:47:32 AM
|
Submission Triaged
|
|
4/10/2026 11:41:15 AM
|
Submission received from Applicant
|
|
4/7/2026 7:32:58 AM
|
Submission request sent to Applicant
|
|
4/7/2026 7:32:45 AM
|
Set Applicant to We Build Decks
|
|
9/15/2025 8:14:32 AM
|
Submission request sent to Applicant
|
|
9/15/2025 8:10:08 AM
|
Project Manager Assigned: Maria Lancto
|
|
9/15/2025 8:07:49 AM
|
Project Created
|